LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Status Update on Mechanical Prototype in Rome November 6,
F. Murtas LNF/INFN 9 July 2002 GEM Chamber 20x24 cm 2 Status Report F.Murtas for the GEM group  20x24 Prototype  PSI Test Beam  Module 0 Progress 
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
Mauro Raggi Status report on the new charged hodoscope for P326 Mauro Raggi for the HODO working group Perugia – Firenze 07/09/2005.
Operational prototype work at CERN Status report MM Gen. Meeting, 06/11/2013 J. Wotschack1.
CERN PH/DT 30/01/14 Francisco Perez Gomez CERN PH/DT.
Large-size micromegas for ATLAS (MAMMA) Status and prospects RD51 mini week, 17/01/2011Joerg Wotschack (CERN)1.
MM mechanical prototype Work progress at CERN MMM Rome, 15/07/20131.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
G. Martellotti CERN 22/04/20021 Tooling / Test Stations for MWPC (Meeting LNF, Roma1/Pz ) Production rate : 408 chambers (Fe + LNF) :192 R4 M1.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
SPD Mechanics and Cooling Status of the activity in Padova Rosario Turrisi Contents: Calibration of Johansson measuring machine Cooling components Half-stave.
LAV construction status Matthew Moulson (Frascati) NA62 Photon-Veto Working Group Meeting CERN, 27 May 2009.
RICH WG M.Lenti. Outlook Mirror Support Vidyo meeting on June 12, 20, 27 and on July 4 and 11 RICH WG meeting on august 27  Vessel status (see Ferdi’s.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Production Readiness Review Production steps and quality control 1.Panel production 2.HV bar gluing 3.Preparation of side material 4.Wiring and gluing.
First results of an aging test of a full scale MWPC prototype for the LHCb muon system Workshop on “Aging Phenomena in Gaseous Detectors”, October 2-5.
T.Schneider/LHCb Muon EDR
May 2001, Istanbul Workshop High Voltage Plates and Capacitor Status Jack Fowler.
The Bigbite second GEM tracker. SBS GEM Trackers Front Tracker Geometry x6 18 modules In Italy  50 cm x 40 cm Modules are assembled to form larger chambers.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
The LHCb Outer Tracker Front End, what does it look like and what is the status Talk for the LHCb Electronics Working Group /TS A Collaboration.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
Status of GEM T2 assembly Outline Status of the GEM components Summary Tests TOTEM Collaboration meeting CERN / Risto Orava for Kari Kurvinen.
11/05/2000Wire Chamber Working Group Visit to Fermilab Participants: –Giulio Auriemma, Thomas Schneider, Burkhard Schmidt General Remarks: –Visit was organized.
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
Panel production status Panels needed according to official plan Oct-05 A rate of 250/month is mandatory to match the chamber production schedule.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status.
Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August (still at 50% of FR4 sheets delivered by ELTOS) – Restarted.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
22/04/20011Wire Chamber Working Group Status on O-ring closed Prototype Foam panels from Frascati (size: 279mm*341mm) No pad structure 4 independent gas.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Chamber Quality Control Before the construction several checks are performed on:  Panels (cathode and pad PCB)  GEM foil Tests on assembled detector.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
Chiho Wang ATLAS TRT Krakow Workshop Duke University May, HV Plate Design & Assembly Chiho Wang Duke University.
Status of production at LNF E.Dane’ and C. Forti – Meeting with LHCb referees Firenze 14-mar-05 Christmas 3 ch/week Ch. 43.
Zaragoza, 5 Julyl Construction of and experience with a 2.4 x 1 m² micromegas chambers Givi Sekhniaidze On behalf of the Micromegas community.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Concept Design for LBNF Far detector (LAr single phase)
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Production and installation plan Construction sharing Production plan Installation sequence Material procurement P. Campana LNF – LHCb Muon EDR Cern April.
Chamber mechanics Chamber mechanics Production in China Peking University Group – 20 Aug
2010/12/14 Caltech Massimo Benettoni FDIRC FBox (almost) ready for production Box design finalized (as possible) Gives precise Fblock positioning wrt guiding.
T2 GEM Production in Helsinki Kari Kurvinen TOTEM T2 EDR meeting Radiation Detector Laboratory of Helsinki Institute of Physics (HIP) and Department.
1 Chamber Interfaces Adalberto Readout-, I2C-, HV-, LV-, Gas- and chamber support interface. Space issues.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Update on Pavia MM mechanical prototype
Service channels between Tracker and PP1
Production ad Quality control of RPCs for the CMS muon barrel system
Some proposals on HV circuits realization for segmented straw detector
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
Presentation transcript:

LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...

First long panel (M3R3) produced on last Thursday, measured on Friday. Quite satisfactory (within specs). No border effects, except in one point, where O-ring to avoid foam leakage was uncorrectly mounted. Some small improvements under way (better foam mixing). More panels under construction to test reliability of production. Meanwhile we proceed for construction of mould for stations M4, M5 (drawings ready) Mechanical characterization nearly completed in Potenza

Some more mechanics is needed to move easily the top cover of the mould and speed up operations, together with cooling system To study and to setup : production and quality controls procedures (at the company and at home) production time plan optimization of no. of moulds vs cost and production time: M3R3 (done), M5R2 (all R1 & R2 panels), all smaller panels obtained by cut ? Build also M2R3 ? About 5000 panels to be produced 2/hour = 70 weeks (to be verified)

Status of 3 protos All closed with glue, under HV training. In air up to 3.2 kV, 0 nA. Up to now, no problems. Soon after HV training, gain scan with source and equip with ASDQ. Bring to test beam in May. We are satisfied with geometry and construction procedures: HV bars at 2.5 mm level, 5 mm spacers, closing bars with protection for HV traces, cathode ground planes with no traces, gas bars with economic nipples for plastic pipes with independent I/O per each gap, no screws, only reference holes at the 4 corners

New type of glue (3M DP460) for chamber closing Araldite not good for structural gluing (does not attach on copper Fr4 plates). DP460 is tixthropic and can be handled for a while (few hours curing) : very strong attachement Two methods 1. “or-ing” of glue: a calibrated amount all around the frame 2. “peripheral”: glue on the outside part of the chamber, to seal against gas leaks Both methods fast and easy, although (2) seems better, but...

In a chamber glued on the periphery, we observed dark current (few nA) with wet atmospheric conditions, due to glue between outer traces and ground plane panel Wire bar glue May be this is due only to bad surface cleaning, but we want to investigate better this effect. No problems (no current) with the other gluing. Not yet fully tested the real gas leakage (not measurable with present setup: much less than 1 bubble/min) HV traces ground

Wire Tension Measurement Test done with 1 channel (KLOE /Atlas method) and “hand movement ”- 16 channels unit with serial interface under production Probe (100  m Al wire) WPC wires to ground Mechanical frame and automated movement needed

Status of other tooling / other activities (LNF) Tools for chamber assembly and gluing under definition: reference bars with ventouses, chariots, working tables, shelfs, etc... Wiring machine: we started to copy Fe & CERN ones Assembly clean area (delayed): civil works will start in May, ready in summer

Soldering machine : final cabling, ctrls and second head (to be used for proto 0) Drawings for all PNPI-INFN chambers (10 types) HV cards: 3 cards to fit all regions (prototypes ready to be tested) Mechanics of muon system: ready to mount the wall (half of M2)

Steps to INFN proto 0 M3R3 Pads, HV bars, closing bars, gas bars ordered (pads and HV bars in 3 pieces to be joined) Material for panels available ASDQ and SPB ordered and under arrival HV cards to be prepared Ferrara wiring machine adapted to M3R3 Plan to wire in Ferrara, bring to LNF, solder and close Work to be done in May-June, test in August Meanwhile, as M4M5 mould is ready, prepare above steps for proto M5R2

Open items : Wire choice (Toshiba vs Luma; Kloe had positive experience with Luma, 70 km, inspection tests) Gas flow and connections (as simple as possible!, plastics) Quality tests after closing : gas leakage, source test, CR (see Rome 1 contribution) 2002 and beyond production plan and material procurement

Cost update quotation on pads (in 3 pieces, one side, R3) around 100 FS/pad quotation on HV bars : 40 FS/m These prices can be lower for large production, and the company could produce long elements if needed gas bars (large #, Fr4, machined) : 6 FS/unit closing bars (large #, Fr4, machined) : 10 FS/m Prices in agreement with previous table costs

0.05 l/h 50cc/60min 1cc/min in 75 litri