PS and East Area re-commissioning with beam from the CCC after a 17 month shut-down R. Steerenberg with help of many colleagues from different groups PS.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

October 12, 2006 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Good Field Region and Tuning Strategy 1 Undulator Good Field Region and.
F.Brinker, DESY, July 17 st 2008 Injection to Doris and Petra Fitting the detector in the IP-region Radiation issues Beam optic, Target cell Polarisation.
Preliminary results and ideas for the SPS upgrade MDs on LHC beams in 2011 G. Rumolo on behalf of all the MD team (Elena, Thomas, Karel, Christina, Holger,
BEAM PREPARATION IN INJECTORS AND BEAM CHARACTERISTICS K.Cornelis BE-OP-SPS.
The TIMING System … …as used in the PS accelerators.
Proton beams for the East Area The beams and their slow extraction By : Rende Steerenberg PS/OP.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
F Antiproton Source Apertures Steve Werkema DOE Tevatron Operations Review March 22, 2006.
BI day 2011 T Bogey CERN BE/BI. Overview to the TTpos system Proposed technical solution Performance of the system Lab test Beam test Planning for 2012.
SPS re-commissioning with beam K. Cornelis PS-SPS days.
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
The Quadrupole Pick-up in the CPS -intro and progress report PPC 3 Dec 1999 A. Jansson.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
PS losses during CT extraction, a history about 30 year long... J. Barranco, S. Gilardoni CERN - AB/ABP.
June 2006LHCCWG / J. Wenninger1 Orbit response measurements and analysis J. Wenninger AB-OP Principle Software status Example from SPS ring and lines Potential.
Andreas Jansson, "Quadrupole Pick-ups", LHC BI-Review, November 19-20, Quadrupole Pick-ups  What is a quadrupole pick-up?  PS pick-ups and experimental.
Content  The LHC beams produced  LINAC2 & PSB  The PS  The SPS  Super Cycles and N0n-LHC physics  Conclusions IEFC Workshop, 8 March 2012 Rende.
Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV B.Goddard F.Velotti, A.Parfenova, R.Steerenberg, K.Cornelis,
LHC Injection Sequencing MD 16/23/2009 Injection sequencing / BCM R, Giachino, B. Goddard, (D. Jacquet), V. Kain, M. Meddahi, J. Wenninger.
1 Run7 startup M. Sullivan MAC Review Nov , 2007 M. Sullivan for the PEP-II Team Machine Advisory Committee Review November 15-17, 2007 Run 7 Startup.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
MG - APC meeting 29/02/20081 MTE commissioning strategy and requirements M. Giovannozzi What is needed to implement MTE ScheduleCommissioning Acknowledgements:
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
Controls Issues Through the Backbone R. Steerenberg with help of many colleagues ATC – ABOC Days 23 January 2007 ATC – ABOC Days 23 January 2007.
19 January 2006 PS&SPS DAYS AD equipment tests and startup with beam Slide 1 AD and AD experimental areas: equipment tests and startup with beam Tommy.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
CO Timing Review: The OP Requirements R. Steerenberg on behalf of AB/OP Prepared with the help of: M. Albert, R. Alemany-Fernandez, T. Eriksson, G. Metral,
BooNE Meeting, January 15, Prebys 1 How are we doing? Best running Power loss (W) Protons (p/min) Energy Lost (W-min/p) Best running again ? Mysterious.
LIU-Ions overall status and outlook: LEIR H. Bartosik for the LIU-IONS LEIR team* with lots of material from “Beam dynamics studies on LEIR”, H. Bartosik,
Practical experience with the AD Stochastic Cooling Murphy’s Law R. Louwerse.
MTE commissioning status S. Gilardoni, BE/ABP With C. Hernalsteens and M. Giovannozzi.
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
HiRadMat Primary Beam Overview C. Hessler, B. Goddard, M. Meddahi On behalf of the HiRadMat Primary beam line working group HiRadMat Project Review
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
Threading / LTC/ JW1 How difficult is threading at the LHC ? When MADX meets the control system … J. Wenninger AB-OP &
Beam Commissioning Adam Bartnik.
Orbit Response Matrix Analysis
Status and Plans for InCA
LEIR IMPEDANCE AND INSTABILITY MEASUREMENTS
ELENA Overview and Layout Start of ELENA Commissioning Next Steps
Renovation of the 45-year old PS magnets
Coupling Correction at the Australian Synchrotron
Summary Friday h38: Ramp down and pre-cycle.
Multiturn extraction for PS2
PS Machine Changes during the 2009 Shutdown
SPS Transverse Damper System
Tuesday 20 March 2012.
Introduction to LHC beam production in PSB and PS
Multi-Turn Extraction for PS2 Preliminary considerations
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Friday 28 October 2011.
PSB magnetic cycle 900 ms MeV to 2 GeV
Another Immortal Fill….
Achieving Nominal Ion Beam PS Ion Progress
LHC An LHC OP guide… under construction J. Wenninger
Presentation transcript:

PS and East Area re-commissioning with beam from the CCC after a 17 month shut-down R. Steerenberg with help of many colleagues from different groups PS - SPS-Days 19 January 2006 PS - SPS-Days 19 January 2006

PS - SPS Days 18 January 2006 R. Steerenberg 2 Topics: Main Magnets renovation and realignment PS inflector zone MPS and B-trains RF issues Internal dumps PS trajectory and orbit measurement (CODD) Extraction bumps TT2 realignment and low beta insertion modifications Slow Extraction and East Area Octupoles Control system and Software Other important changes Schedule and rough planning Request for support form all groups Conclusions

PS - SPS Days 18 January 2006 R. Steerenberg 3 PS Main Magnet Revision 25 Main Magnets are renovated and re-installed: All magnetic polarities of each circuit will be measured in the ring. Cabling errors can lead to two main problems: One inversion early in the chain  Easy to detect as the optics is very different for required current. Two inversion not too far separated from each other  Optics wrong by a percentage which is equal to twice the number of magnet that have the wrong polarity. Difficult to detect and long search necessary to locate wrong connections. If not detected this will limit the machine performance CODD and tune measurement are necessary !!! Are the new PFW’s identical to the old ones ?

PS - SPS Days 18 January 2006 R. Steerenberg 4 Ring realignment (1) About 20 years ago, 10 main magnets were voluntarily displaced up to several mm to correct the orbit at ‘high’ energy. 5 in the horizontal plane 5 in the vertical plane At present the main magnets will be realigned along a smooth curve with fixed points at the injections (26, 42) and extractions (16, 61), taking out these voluntary misalignments. During the start up with beam the ‘High’ energy orbit will be re-corrected using the same method.

PS - SPS Days 18 January 2006 R. Steerenberg 5 Ring realignment (2) Orbit measurements will be made at ~10 GeV/c. New corrections will be calculated and magnets will be voluntarily displaced to re-correct the orbit. If the magnet needs to be displaced by more than 0.5mm (very likely) we have to break the vacuum. Local displacements can be made at a rate of 3 magnets per day. This means 3 to 4 days work depending on the amount of magnets concerned. Since this consumes quite some start up time, we hope that one iteration will be enough.

PS - SPS Days 18 January 2006 R. Steerenberg 6 PS Inflector zone The PS inflector zone was built to be able to continue running the PSB while accessing the PS straight sections 0 to 17 and 41 to 99. At present it is not possible to close the inflector zone rapidly during the machine run in case of a problem or work in the PS. This may lead to loss of valuable start-up, Physics or MD time. The first case is the displacement of the main magnets for the correction of the PS ‘high’ energy orbit. Preliminarily planned for week 17. PS access is necessary. Might last for more than a week. Coincides with first week of ISOLDE physics.

PS - SPS Days 18 January 2006 R. Steerenberg 7 When PS was stopped in 2004 there was a problem with the MPS regulation. Solution to the problem is found and implemented Fine adjustments to be made On-line test to be performed If not all our cycles and optics need to be modified B-train responsibility will be transferred from AB/PO to AT/MTM AT/MTM has no piquet service, but will provide a specialist service. What when specialist cannot be reached ? FMR system, for diagnosing B-train problems, is under revision, to improve remote use. Should be available at start up. MPS and B-trains

PS - SPS Days 18 January 2006 R. Steerenberg MHz cavities These cavities are used for longitudinal blow up at different energies and for applying a 200 MHz structure on the Fixed Target beam for the SPS. Initially 8 cavities: 6 cavities in SS06 (non tuneable) 2 cavities in SS08 (tuneable) Cavities in SS08 will be removed, we will only have 6 cavities in SS06. New configuration: C201, C204, C205, C206 (non tuneable) C202, C203 (tuneable) Cavity controls and matrix application need to be modified.

PS - SPS Days 18 January 2006 R. Steerenberg 9 Beam Control issues Control of the phases for bunch splitting and re-bucketing are now remotely available.  to be tested Many RF by-passes are dismantled and reinstalled during the magnet renovation project.  They should be carefully checked. In 2004 the RF by-pass of SMH16 had a bad contact and this made that the current in the first quadrupole in the TT2 line was heavily perturbed.

PS - SPS Days 18 January 2006 R. Steerenberg 10 Internal Dumps Caused many problems last years, but … Both dumps are renovated and should be reinstalled one of these days to be available at the start up. New power supplies are installed on the surface and not next to the dumps as in the past. The system was tested outside the tunnel. Preparations for new controls have been made. Old controls will be used during If the dumps do not work, setting up will be more difficult.

PS - SPS Days 18 January 2006 R. Steerenberg 11 CODD pick ups New head amplifiers have been installed to measure also ions down to 1E9 charges per bunch (was 1E10). Many efforts went in to reducing the noise levels, by using new design and better shielding. For all gains the displacement sensitivity is 40mm (was mixed: 20mm and 40mm). The gain curve is much more linear with only maximum 0.5 dB error (was 10 dB) RT task will be adapted and as a consequence the CODD application needs to be modified.

PS - SPS Days 18 January 2006 R. Steerenberg 12 CODD pick ups Old system New system, still some gain to spare Courtesy of J. Belleman Laboratory measurements show the improvement New calibrations will have to be done CODD is one of the first system that is needed for a good start-up Will it be available on the 1 st or 2 nd day ?

PS - SPS Days 18 January 2006 R. Steerenberg 13 Bump 16 Consists of 4 magnets connected in Series- Parallel: (SS12-SS22)||(SS14-SS20) To prepare future Multi-turn Extraction the bump needs to be modified. First step: SSOld typeNew typeComment Spare Spare from DHZ From SS35 of BSW31 Magnetic differences are negligible. PO will check regulation.

PS - SPS Days 18 January 2006 R. Steerenberg 14 Bump 31 Consists of 2 magnets connected in Series: SS27 and SS35 Will be eliminated in future for new Multi- turn Extraction, but for 2006 it will be: SSOld typeNew typeComment From SS22 of BSW Remains unchanged Magnetic differences are negligible. PO will check regulation.

PS - SPS Days 18 January 2006 R. Steerenberg 15 TT2 line: Realignment TT2 is realigned taking in account the available correctors. Courtesy of M. Martini New steering to be found, only few correctors available….. mm mm

PS - SPS Days 18 January 2006 R. Steerenberg 16 TT2 line: Low beta insertion 4 new quadrupoles are added, which should have zero current for proton operation. F16.QDE163, F16.QDE207, F16.QDE213, F16.QDE217 First 2 quads from each string are separate now. F16.QDE210s consisted of 14 quads and became now: F16.QDE210 (1 quad with separate power supply) F16.QDE220s (13 quads in series on 1 power supply) F16.QFO215s consisted of 13 quads and became now: F16.QFO215 (1 quad with separate power supply) F16.QF0225s (12 quads in series on 1 power supply) For proton operation the quads should have the same currents as before (2004), values will only be different for future ion operation. Magnetic polarities should be checked.

PS - SPS Days 18 January 2006 R. Steerenberg 17 Slow Extraction 1 sextupoles in SS7 and 2 in SS19. For the future Multi-turn Extraction the vacuum chamber in SS19 needs to be enlarged. The sextupoles in SS19 need to be moved to SS03. Both quadrupolar pick-ups SS03 and SS04 will be removed. Wall Current Monitor SS03 remains. In 2006 we will have: 1 sextupole in SS7 (remains as it was) 2 sextupoles in SS19 (will be removed in 2007) 2 sextupoles in SS3 (future SE configuration) This year we should make the new configuration work, otherwise we need to construct 2 new large aperture sextupoles for SS19.

PS - SPS Days 18 January 2006 R. Steerenberg 18 F61S.BHZ01: a new magnet with improved cooling system will soon arrive and will be installed before the start up. F61S.QDE02, F61N.QDE01 and QFO02 New magnets are under construction, but delivery date is still uncertain. If not in time run with present magnets and their problems. ZT7.QFO01 and ZT10.QDE01 are or will be changed before the shut down. The MNP23 in T9: Had an earth current problem, probably due to conductivity problem in cooling water. No spare magnet available. If problem persists the beam line will run with lower energy !!! East Area(1)

PS - SPS Days 18 January 2006 R. Steerenberg 19 Is the cause known ? This cannot be confirmed nor excluded. Conductivity measurements system broke down in 2004  no systematic measurements. Could be due to demineralisation modules. Is the problem solved ? The measurement chain is repaired and recalibrated. demineralisation modules will be changed systematically An additional off-line measurement system is put in place. East AreaCooling water

PS - SPS Days 18 January 2006 R. Steerenberg 20 Octupoles In 2006 there will be 6 octupoles out of originally 8 available for adding Landau damping in the transverse plane. This should be no problem: Instabilities are better under control without using octupoles. More than enough power available with remaining octupoles

PS - SPS Days 18 January 2006 R. Steerenberg 21 Control system and Software The PS complex will restart using the applications that were used in The existing diagnostic tools will be supported, new ones will be coming. The Oasis observation system will be used, not Naos. The PS ‘MD’ signals will be on Oasis too. Very limited FESA implementation nevertheless means that we will have to use two alarm trees in parallel.  less convenient, risk of incoherence ?! TT2, Inj. 26 and AD beam screens (MTV’s) VOS application has been modified to be able to control GM and FESA MTV’s, using knobs. However, FESA MTV alarms, like “screen in” will not appear in the X-motif alarm tree.

PS - SPS Days 18 January 2006 R. Steerenberg 22 Other important changes The PS telegram is now send every basic period instead of every cycle. Front-ends adapted to see only first telegram of a cycle, to avoid problems with RT-tasks. Workstation always received a telegram per basic period via the network. Technical Network is now isolated from General Purpose Network. Access can only be done with trusted machine or via a terminal service. What will the impact be for access to machine parameters from other places than the CCC.

PS - SPS Days 18 January 2006 R. Steerenberg 23 Schedule A thorough cold check-out reduces start-up problems Set up and make the beam go around Cope with realignments and changes Set up beams for users: SFTPRO / CNGS AD East Area LHC beams (Pilot, 25ns)

PS - SPS Days 18 January 2006 R. Steerenberg 24 Rough planning A more detailed planning of both the cold check-out and start-up with beam is being made. Check list and procedures will be in the CCC.

PS - SPS Days 18 January 2006 R. Steerenberg 25 Support We ask all the groups to test and debug their equipments and systems as much as possible well before the Cold Check-Out. Measurement and diagnostic systems are necessary to set up the beam and it should not be the other way around. CO will provide a piquet service as in Two people during day for start up. OP will be in the CCC: We will have the same level of control as in the MCR All diagnostics tools and signals will be available However, we cannot intervene locally on equipments as we did from MCR. This means that the first line or equipments specialists will be asked more frequently to intervene on their equipment.

PS - SPS Days 18 January 2006 R. Steerenberg 26 Conclusions The list is not exhaustive and all additional information is very welcome. Many changes have been made, of which some might cause trouble during the start up. Ring realignment and orbit correction is a time consuming work (magnet movements and perhaps bake-out) There are no real show stoppers at the horizon, but we are never 100% sure..... The 2006 start-up will be challenging for many reasons, but by continuing to put all efforts and goodwill in, together we will make it work again !!!