EHN1 North Wall Dismantling Schedule Bastien Rae
EN-CV Task before end of CMS TaskStartDuration Install new cooling system Barrack BE-BIMon day Reroute CMS cold box to raw waterMon week Reroute Vertex cold box to raw waterMon week Reroute Atlas cold box to raw waterMon week Install scaffolding on Jura side (EN-MEF-SI?)Thu days Cut drinking waterMon days Cut Ventilation duct and pipe on Jura sideWed day Remove drinking water from NW (Asbestos)Thu days
EN-CV Task after CMS run TaskStartDuration Disconnect cooling system from CMS Barrack 902Mon day Install scaffolding on Salève side (EN-MEF-SI?)Mon day Cut and remove chilled water pipeWed week Cut Ventilation duct and pipe on Salève sideWed day Install new Chilled water pipe (Gallery + Barrack BE-BI)Thu days Connect the new cooling system for Barrack BE-BITue day Rerouted Gallery Pipes (2 demi water, 2 raw water, 1 compressed air)Mon weeks