1 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Cathay Life Insurance (VN) Date: 27 March 2009
2 Cathay Life Insurance Ltd. (Vietnam) 27/03/ ENGAGED PROJECT THIS MONTH System SupportSystem Development - Network Support - PBX Setting - Support - Maintenance Agreement - Develop the BCS (Business Core System)
3 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Improve the air conditioner of data center in N’orch Building : Install the voltage stabilizer. A Completed to setting the Leased line connected from Danang to Data Center. B Setup Network, PCs, Printer, Scanner in Danang Service Center. C Network System Support
4 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Data Center relocation survey: send report to BOD with no relocation suggestion. D Completed to change the memory of staging system. E Setup MRTG software to monitor the traffic of all routers. F Network System Support (con’t)
5 Cathay Life Insurance Ltd. (Vietnam) 27/03/ The MRTG Software Demonstration
6 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Completed to setting up the temporary PBX System included ITG function in Danang Service Center A Danang’s telephone number is: B Danang’s fax number is: C PBX Setting
7 Cathay Life Insurance Ltd. (Vietnam) 27/03/ ITG Setting From \ ToTaiwanN'orchHanoi The World Center DaNang Taiwan N'orch Hanoi The World Center DaNang
8 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Setting Setup the message disclaimer to system A Setup the business account for all divisions and departments. B
9 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Message Disclaimer Demonstration
10 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Business List Demonstration
11 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Maintenance Agreement Send to BOD for signing the Microsoft EA contract. A Prepare the Approval of Windows Server MA B Discuss about IBM Middleware MA with supplier and checking the contract. C
12 Cathay Life Insurance Ltd. (Vietnam) 27/03/ Developing the BCS (Business Core System) Install to BCS system support the R03 product. A Print the invoice with our President’s signature automatically. B Change the new version of receipt C Implement the Computer Job Acceptance Confirmation form from March of 2009 D
13 Cathay Life Insurance Ltd. (Vietnam) 27/03/ PLANNING PROJECT FOR NEXT MONTH Implement the normal Nortel PBX system for Danang Service Center A Maintain BCS and B2E system. B Continue to monitor the network quality. C Sign the Server MA, IBM Middleware MA contract. D