MICE CM16 Goals Alain Blondel 8 October MICE CM 16 Collaboration meeting 8-11 October 2006 at RAL Goals of the meeting thanks to John Cobb & Marco Apollonio for organisation of the meeting and setting the agenda 66 MICE have registered
MICE CM16 Goals Alain Blondel 8 October NUFACT Accelerator baseline proton driver parameterValue Energy (GeV)10 ± 5 Beam power (MW)4 Repetition rate (Hz) 50 No. of bunch trains3,5 a) Bunch length, rms (ns)2 ± 1 Beam duration b) ( s) 40 a) Values ranging from 1–5 possibly acceptable. b) Maximum spill duration for liquid-metal target. NuFact ParameterValue Target+captureL Hg+ 20T solenoid phase rotation and bunching coolingyes stored muon energy upgradable to 20GeV 40GeV trains of both signs of muons separated by 100ns decays per straight angular divergence /yr 0.1/ RF Goals achieved!
MICE CM16 Goals Alain Blondel 8 October Competition is active! better beta beams: use higher Q isotopes (C.Rubbia) instead of He or Ne (Q~3 MeV) 8 B --> 8 Be e + e or 8 Li --> 8 Be e - anti- e + New production scheme would allow higher intensities --> altogether higher energy and higher rates for the same storage ring rigidity
MICE CM16 Goals Alain Blondel 8 October NUFACT detectors baseline distance detector km distance detector km detector 1largest MIND 1) (100 kton) 4cmFe/1cm scint res. 1cm + ECC 5-10 kton (Silver) detector 2MIND (30 kton) matter density uncertainty +- 2% effective muon selection threshold ~3 GeV (actual analysis to be used) beyond the baseline to be investigated large magnetic volume for Larg, TASD, MECC (Platinum) 1) Magnetized Iron Neutrino Detector MIND new selection old selection LAr GAr B≈ 0.1 1 T LHe HT c coil? hep-ph/ Frascati, 2005
MICE CM16 Goals Alain Blondel 8 October this minimal 3 family picture plots and similar plots within and beyond the minimal picture will continue to be refined and clarified as progress is made by proponents of the various options CHOICE will depend on -- --cost --timescale PRELIMINARY
MICE CM16 Goals Alain Blondel 8 October ISS--> IDS aspirational time line: ISS report: end of 2006 will include a description of the R&D and ressources necessary to produce InterimDesignReport in 2010 and CDR in 2012 Next « ISS » meeting second half of february CERN preparation of funding proposals Review of where we stand at NUFACT07 mid-2008 (NUFACT08) funded engineering phase begins 2010 IDS interim report 2012 CDR Meanwhile a European Oversight Committee should be put in place to coordinate neutrino-beam requests.
MICE CM16 Goals Alain Blondel 8 October Regional Oversight Committees Nufact study Accelerator Detectors Physics Betabeam study Accelerator Detectors Physics Superbeam study (or studies) Accelerator Detectors Physics Neutrino Oscillation Physics Working Group -- exact structure of each study to be decided by proponents -- Regional Oversight Committees will possibly converge to a single international committee for a future precision neutrino facility
MICE CM16 Goals Alain Blondel 8 October EP2010: « pursue an internationally coordinated, staged program in neutrino physics » CERN-SG: Studies of the scientific case for future neutrino facilities and the R&D into associated technologies are required to be in a position to define the optimal neutrino programme based on the information available in around 2012 ; Council will play an active role in promoting a coordinated European participation in a global neutrino programme. Towards a high-intensity neutrino programme
MICE CM16 Goals Alain Blondel 8 October Aspirational MICE Schedule now (date= ready to take data) 15 September 2007 NB: picture does not include target, beam line, hall infrastructure, electronics, DAQ, shifters etc… ! STEP I November 2007 STEP III: Winter 2008 STEP II STEP IV Fall 2008 STEP V Spring 2009 STEP VI Fall 2009
MICE CM16 Goals Alain Blondel 8 October STEP I: 15 September 2007 = 340 days to data taking! STEP II: soon after PHASE I MAIN GOAL of meeting: Understand where we stand in our preparations for Steps I and II (and III). More Generally: monitor status of experiment, make necessary decisions to move forward, identify issues that require action
MICE CM16 Goals Alain Blondel 8 October EXPECTED RESULTS --I-- (from CM15 to CM16) BEAM LINE -- target system: solution for heating of linear mechanism, test of system progress of first beam test (expected end of october 2006) -- status of beam solenoid -- beam line construction -- optics: full coverage of emittances and momenta? correction and tuning systems; collimators and controls -- diffuser size & mechanism
MICE CM16 Goals Alain Blondel 8 October EXPECTED RESULTS --II-- (from CM15 to CM16) DETECTORS -- results of test beams at Frascati and Fermilab -- upstream Cherenkov and TOF0/1 review at the end of the meeting -- tracker (first plane and QA?) -- downstream shield/TOF2/EMcal size! -- scraping issue -- funding and schedule issue! DAQ and controls -- workshop in Daresbury in September -- overview of system and proposal
MICE CM16 Goals Alain Blondel 8 October TOF Ennoying questions: TOF2 said to be mid Can this be brought forward? what will happen with x-ray radiation when we run with RF? Issue: particles crossing material in the downstream end of the spectrometer this is a beam of MeV/c, all generated with 4T field in spectrometer. How about the size of the hole in the shielding Preparations of TOF0 test on-going (Milano-Pavia) double layer allows measurement of resolution, meast is of this is the main aim of the test
MICE CM16 Goals Alain Blondel 8 October EXPECTED RESULTS --III-- (from CM15 to CM16) ANALYSIS -- run plan (time is expensive and people are few) -- time measurement discussion -- scraping, emittance propagation etc.. -- associated questions: time definition in MICE (master clock?) SOFTWARE -- launching MICE data Challenge? -- continuous improvements (last time was spectacular)
MICE CM16 Goals Alain Blondel 8 October EXPECTED RESULTS --IV-- (from CM15 to CM16) INFRASTRUCTURE -- general experiment infrastructure -- MICE-folks becoming official users at RAL -- HAZOP and safety report PHASE 2 -- UK bid under review -- LH2 R&D -- Coupling coil (First Harbin report in a collaboration meeting!) -- RF cavity progress at Fermilab -- power source progress -- RFCC and absorbers PHASE 3 -- how does MANX match to MICE?
MICE CM16 Goals Alain Blondel 8 October PERSONNEL (will be proposed to Collab. Board) Y. Torun has a new job (congratulations) -- VC planner K. Long --> JS. Graulich -- ANALYSIS Forum Y. Torun --> J. Cobb (TBC)