AFE IIt Project Status
Current Status AFE II Prototype Testing Complete u Detailed ch by ch testing has been done s 3071 good channels out of 3072 through comprehensive test u Continuing with some long-term (weeks) testing of cryo control and stability on the VLPC CC cryostat Packaged TriPt (MOSIS) in house TriPt/FPIX submission - OUT Design input for AFE IIt board finished Schematic Complete – 6/20 4 weeks behind - but Layout Complete – 6/28 about 2 weeks behind u We have authorized OT and it is being used u Will try to add a second Layout tech towards the end. For technical reasons this is not appropriate at this time Only issue u Could use 1 additional person to work on FPGA programming
Current Status AFE II Prototype- Gain
Current Status AFE II Prototype - Noise 1 pe 6 fC
Current Status - TriPt Out for Fab Proposed reticule layout for TriPt/FPIX Proposed wafter map 70 reticules
Current Status - Layout
Current Status - TriPt TriPt: u Packaged “MOSIS” parts are here u Robot tester work progressing: adapter board in layout (estimate: 1 week) u Mechanical parts for robot complete
Response to Recommendations from Director’s Review We have modified the project plan to include: u A second submission of the TriPt chip s This, of course, does produce a delay in the project completion. The funds are there if needed, however s We believe that the probability for a successful run is very high u Production of 350 boards. u Over time for layout technician(s) for AFE IIt board Bob Demaat has joined the AFE IIt project as L2 production manager Weekly reporting will occur via the AFE IIt production meeting with progress and schedule status from the L3 managers written up and published as minutes of this meeting
Milestone List with 2 nd TriPt submission AFE II/TriPt Project Start1/5/04 AFE II Prototype Testing Complete5/12/05 AFE IIt Layout Complete 6/17/05 Ready for Production TriPt Testing7/18/05 AFE II Prototype Under Test7/18/05 Certify for Production10/13/05 TriPt Production Started (Round 1)5/20/05 TriPt Production Started (Round 2)10/31/05 TriPts Ready for Board Stuffing3/6/06 AFE IIt pre-Production Board under Test3/20/06 Certify for Full Production 4/19/06 Board Assembly Complete 6/29/06 First Crate Ready for Installation7/13/06 203 Boards Ready 8/10/06