0 Calculation of Return on Investments Farrokh Alemi, Ph.D.
1 Present Value
2 “Show Me the Cash” Interest rate or opportunity cost of investment Years before receivin g the cash
3 Example of Present Value If we assume a 6% interest rate, receiving $1,000 in 5 Years is worth $747 today. Interest rate Years till return
4 Calculation of Return on Investment
5 Calculation of Return on Investment in 3 Steps 1.Calculate present value of future returns
6 Calculation of Return on Investment in 3 Steps 1.Calculate present value of future returns 2.Calculate present value of investments
7 Calculation of Return on Investment in 3 Steps 1.Calculate present value of future returns 2.Calculate present value of investments 3.Take the ratio
8 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value?$83,176$63,188$39,743$28,120$21,221 Assume 6% Interest Rate or 0.06
9 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value?$83,176$63,188$39,743$28,120$21,221 Shows returns in each year
10 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
11 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
12 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
13 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
14 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
15 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
16 Example Step 1: Present Value of IT Costs Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
17 Example Step 1: Present Value of IT Costs Present Value of 5-year Cost of Investment $235,450,000 Year 1Year 2Year 3Year 4Year 5 Cost in 000$88,167$70,999$47,335$35,501$28,399 Present value$83,176$63,188$39,743$28,120$21,221
18 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695,037 Shows future returns
19 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695,037
20 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604
21 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604
22 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604296,655,472
23 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604296,655,472279,883,522
24 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604296,655,472279,883,522264,050,432
25 Example Step 2: Present Value of Future Revenues Year 1Year 2Year 3Year 4Year 5Total $333,304,921$333,322,089$333,345,753$333,357,587$333,364,6891,666,695, ,438,604296,655,472279,883,522264,050,432249,109,4881,404,137,518 Present Value of 5-Year Future Revenues = $1,404,137,518
26 Example Step 3: Return on Investment
27 Example Step 3: Return on Investment
28 Take Home Lesson Calculate ROI in 3 easy steps as the ratio of present value of returns over present value of investment