DEPARTMENT OF PUBLIC WORKS, ROADS AND TRANSPORT SELECT COMMITTEE ON PUBLIC SERVICES 2 AUGUST AUGUST
PRESENTATION OUTLINE 1.Progress on EPWP 2.Progress on EPWP – Roads Infrastructure 3.Planned 2011/12 EPWP Outputs – Roads Infrastructure 4.Project Management Team 2
SECTOR2011/12 Target 1 st Quarter Target Work Opportunities Achieved (1 st Quarter) % of Annual Target Achieved % of Q1 Target Achieved Environment and Culture %414% Infrastructure %273% Social %275% TOTAL %293%
The Department has maximized on the Provincial Road Construction and Maintenance Grant of R1,016 billion through the S’Hamba Sonke initiative in realizing all the EPWP imperatives. The programme identified and categorized maintenance projects as follows: Routine maintenance Regraveling Preventative maintenance i.e. Emergency patching, reseal, fogs-pray and light rehabilitation Bridge repair
Sub-programmes2011/12 budget (R’000)FTE Routine maintenance Preventative maintenance Regional regraveling including CRDP Bridge repair Emergency maintenance Coal haulage road rehabilitation Siyatentela Total Table showing Full-time Employment (FTE) Targets /12
The Mpumalanga Roads Infrastructure Section has a well set up project team consisting of both in-house and external teams. In-House Project Team General Manager Senior Managers (Planning, Design and Material, Construction and Maintenance) Chief Engineers (x3) Project Coordinators (x4) Regional Chief Engineers (x4)
External Project Team CAPEX Programme Management Unit (PMU) Coal Haulage Implementation Managers (CHIM) Regional Maintenance Consultants (x3 Regions) Roads Asset Management Consultant
Roads Infrastructure Project Team Working Relationship;