F. Regis, 07-04-2011 LINAC4 – LBS & LBE LINES DUMP DESIGN.

Slides:



Advertisements
Similar presentations
Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
Advertisements

R.Valbuena NBI March 2002 CNGS Decay Pipe Entrance Window Structural and Thermal Analysis A.Benechet, P.Cupial, R.Valbuena CERN-EST-ME.
The JPARC Neutrino Target
1 THERMAL & MECHANICAL PRELIMINARY ANALYSIS ELM COIL ALTERNATE DESIGN Interim Review July 26-28, 2010 In-Vessel Coil System Interim Review – July 26-28,
Radiation Cooling of the ILC positron target LCWS 2014, Belgrade, Serbia 7 th October 2014 Sabine Riemann, DESY, Peter Sievers, CERN/ESS, Andriy Ushakov,
Vacuum, Surfaces & Coatings Group Technology Department Glassy Carbon Tests at HiRadMat 14 March 2014 C. Garion2 Outline: Introduction Context: Transparent.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
Study of a new high power spallation target concept
Horn design for the CERN to Fréjus neutrino Super Beam Nikolas Vassilopoulos IPHC/CNRS.
A NON LINEAR TRANSPORT LINE FOR THE OPTIMIZATION OF F18 PRODUCTION BY THE TOP LINAC INJECTOR C. Ronsivalle, L. Picardi, C. Cianfarani, G. Messina, G.L.
NML High Energy Beam Absorbers and Dump 29-August-2011 Beams-doc-3928.
First AWAKE dump calculations Helmut Vincke. Beam on dump Muon axis inside and outside CERN Distances: Beam impact point to end of West hall: ~300 m Beam.
The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze May 26, 2014.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
A. Bertarelli – R. Perret CERN TS – MME Group 1 CERN European Organization for Nuclear Research Mechanical Engineering and Thermo-mechanical.
Develop Epoxy Grout Pourback Guidance and Test Method to Eliminate Thermal/Shrinkage Cracking at Post- Tensioning Anchorages Project Manager Rick Vallier.
Calculation of Beam loss on foil septa C. Pai Brookhaven National Laboratory Collider-Accelerator Department
The Stripping Foil Test Stand in the Linac4 Transfer Line
CERN-SLAC meeting June, The LHC Collimator Project LHC Collimators for Phase 1 CERN-SLAC meeting – June, Palo Alto, Ca Alessandro Bertarelli.
Internal H0/H- dump M. Delonca, C. Maglioni On behalf of EN/STI Thanks to: A. Christov, S. Mathot, C. Pasquino, A. Patapenka.
STATUS OF H0/H- DUMPS M. Delonca – LIU meeting 29/11/2012 Thanks to: C. Maglioni, A. Patapenka, C. Pasquino, A. Perez, N. Mariani.
Status of Radiation Protection Studies for the Linac4 beam dumps Joachim Vollaire DGS/RP.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
Activation around dump shielding, and design of beam line mask Mathieu Baudin, RP Genevieve Steele, EN-STI Helmut Vincke, RP.
RF source, volume and caesiated extraction simulations (e-dump)
Presentation at BBC, Linac 4 Commissioning Dump at 50 and 100MeV 1 Øyvind Dahle Lauten, EN-STI.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
GRAN SASSO’S HADRON STOP Temperature’s behaviour under specified beam conditions Barbara Calcagno.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
Issues Raised by the Design of the LHC Beam Dump Entrance Window Ray Veness / CERN With thanks to B.Goddard and A.Presland.
3 MeV H - chopper beam dump Presentation by L.Bruno 1 3 MeV H - Chopper Beam Dump Pre-design study By L.Bruno AB/ATB M.Magistris AB/OP M.Silari TIS/RP.
Cooling of GEM detector CFD _GEM 2012/03/06 E. Da RivaCFD _GEM1.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
Simulation of heat load at JHF decay pipe and beam dump KEK Yoshinari Hayato.
Engineering studies for CN2PY secondary beam. LAGUNA-LBNO General Helsinki, 26/08/20141 F. Sanchez Galan (CERN) on behalf of the CERN Secondary.
ESS RFQ B. POTTIN and RFQ team CEA-IRFU. RFQ design Strategy 3 RF codes to validate calculations Consideration of machining and assembly possibilities.
Design for a 2 MW graphite target for a neutrino beam Jim Hylen Accelerator Physics and Technology Workshop for Project X November 12-13, 2007.
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
TS Cool Down Studies TSu Unit Coils (24-25) N. Dhanaraj and E. Voirin Tuesday, 10 March 2015 Reference: Docdb No:
Internal H0/H- dump M. Delonca On behalf of EN/STI Thanks to: A. Christov, C. Maglioni, S. Mathot, C. Pasquino, A. Patapenka.
SPS High Energy LSS5 Thermal contact & cooling aspects
ESS Front End diagnostic
High intensity electron beam and infrastructure Paolo Valente * INFN Roma * On behalf of the BTF and LINAC staff.
THERMO-MECHANICAL DESIGN | PAGE 1 CEA Saclay 2015.
Chiara Di Paolo EN-STI-TCD Material Choice for the Vacuum Window at the Exit of BTM.
Dark Current and Radiation Shielding Studies for the ILC Main Linac
16 T dipole in common coil configuration: mechanical design
ISIS TS1 Project: Target Design and Analysis
Update on PANDA solenoid design
Heating and radiological
X PS Internal Dump Core Review François-Xavier Nuiry Giulia Romagnoli
Proposal TDIS-TZM WP14 TDIS jaw validation testing
Options and Recommendations for TL and Dumps
Impact of TIDVG problem on LSS5 dump design schedule
F. Zocca, F. Roncarolo, B. Cheymol, A. Ravni,
Radiation protection of Linac4 M. Silari Radiation Protection Group
Peter Loveridge High Power Targets Group
Thermo-mechanical analysis of the D3 dump in the TT2 line (PS)
Dump Core Studied Design Solutions
Thermo-mechanical simulations jaws + tank
M. Calviani, A. Ferrari (EN/STI), P. Sala (INFN)
Federico Carra – EN-MME
First thermal calculations on the target made of aluminium
Beam Dump outline work plan (UK perspective)
Thermo-mechanical Analysis
ANALYSIS OF THE HORN UNDER THERMAL SHOCK – FIRST RESULTS
Presentation transcript:

F. Regis, LINAC4 – LBS & LBE LINES DUMP DESIGN

 LBS and LBE lines  Design specifications  Dump features  LBS dump: RP preliminary analysis  General design features  Energy deposition  Thermal analysis  Structural analysis  Conclusions and next steps  LBS dump: Scenario 1 vs. Scenario 2 2 Outline

3 LBS & LBE lines LBS line: Present layout LBE line LBS line

4 Design specifications LINAC4 Project Document No. L4-B-ES-0001 rev.1.0 LINAC4 standard pulses LBS line operational scenarioLBE line operational scenario LBS line 1- σ beam size LBE line 1- σ beam size Most severe thermo-structural scenario for LBS dump: Accident Most severe thermo-structural scenario for LBE dump: Commissioning For fatigue stress evaluation: most severe duty cycle. Absorbing core diameter: LBE beam size at vertical measurement, re- scaled at 5- σ

5 Dumps features Installation in the tunnel ceiling (≈4.5 m height) d min =200 mm from SEM grid (SEM grid vacuum tank, line installations, extra- shielding,...) Reduced particle fluence beyond the dump (soil activation issues and possible effects on TP9 Gallery) Reduced particle backscattering to the SEM grid Feasibility study presented in March 2010 (R. Chamizo, V. Boccone): starting point LBS Dump LINAC4 full intensity beam (40 mA average current, 2834 W average power) Most stringent thermo-structural constraints w.r.t. LBS dump Reduced particle backscattering towards instrumentation LBE Dump Let’s try a common design

6 LBS dump: RP preliminary analysis More calculations needed to evaluate concrete thickness necessary to reach 2.5 µSv/h SEM grid position still to be defined Induced activity in the water circuit Estimated activity based on steady water volume: conservative approach Refined analysis ongoing Irradiation profile Fluka model Courtesy of J. Vollaire 2 months – 12 W 1 month off 2 years – 8h x W 50 cm Upstream (mSv/h) 220 cm in the Soil (mSv/h) Prompt Dose10 3 / h101.00E-03 8h1< 1E-03 1w E-04

7 General Design Features R4550 Graphite Absorbing Core Cu10100 OFE Copper Jacket LBE: commissioning scenario 400 µs Rep. Rate = 1.11 Hz I avg = 40 mA P avg = 2834 W Beam size: vertical measurement scenario Beam parameters

8 Energy deposition Peak energy deposition: 0.833e9 J/m3 Nominal deposited power: 2834 W Total deposited power ≈ 2419 W Peak coordinates: z peak = 265 mm ANSYS Fluka Peak energy deposition: 0.804e9 J/m3 (-3.5% w.r.t Fluka) Total deposited power ≈ 2554 W (+5.6% w.r.t. Fluka)

9 Thermal analysis Maximum water speed to prevent from erosion/corrosion problem = 1.5 m/s Nominal Heat convection coefficient in cooling pipes = 7157 W/m 2 /K Perfect thermal contact Graphite/Copper Δ T in&out = 0.44 K (1/4 th model) Δ p ss ≈ bar (1/4 th model – straight section only) Steady state – 4 c.p. Vs. 8 c.p. n cp = no. of cooling pipes

10 Thermal analysis Transient analysis – Heat convection efficiency

11 Thermal analysis Absorbing Core – Regime T max Jacket – Regime T max Cooling pipe – Regime T max,wall Nominal convection T max =450°C T max =29°C T max =27°C

12 Structural analysis Mechanical R.T.R 4550Cu Young modulus E (GPa)11.5=f(T) R p02 (MPa) UTS - tension (MPa) UTS - compression (MPa)125- Quasi-Static Structural analysis (worst cooling scenario): First pulse: analysis of stress field in Graphite i th pulse on regime: global analysis of stress field Failure criteria: Stassi Criterion for Graphite VonMises Criterion for cooling jacket Dynamic stress - Graphite Heating process slower than stress relaxation due to elastic wave propagation

13 Structural analysis 1 st pulse – Stassi criterion Tension1 st pulse – Stassi criterion Compression 500 st pulse – Stassi criterion Tension500 st pulse – Stassi criterion Compression Beam σ max =3.30MPa σ max =3.88MPa σ max =-31.3MPa σ max =-28.72MPa

14 Structural analysis End 1 st pulse – Von Mises 500 st pulse – Von Mises GraphiteCopper Pulse σ T,max σ C,min σ vm,max Stress levels within failure limits for both Graphite and Copper No relevant mechanical properties degradation of Cu10100 (T max = 36 °C) Thermal conductance model between graphite core and copper jacket Definition of the assembly interference (shrink fitting) Fatigue analysis for the dump – worst case scenario Next steps σ max =0MPa σ max =13.5MPa

15 Conclusions and Next Steps A common solution for the LBS and LBE dump seems possible: further analysis needed Worst case for thermo-structural analysis have been selected for the LBE dump Dump configuration has been set according to LBS operation specification (back-scattering) Thermal analysis for cooling system design: steady-state and transient state Structural analysis performed on worst cooling conditions WHAT IS NEXT? Thermal conductance model for graphite to copper interface Refined thermo-structural analysis: assembly interference,... Detailed analysis of cooling water activation (RP) Possible reduction in dump size: open discussion with RP team

16 LBS Dump: Scenario 1 vs. Scenario 2 L z Magnet z Wall l1l1  H h s1s1 s2s2 s3s3 d/2 d l2l2 l SEM

17 LBS Dump: Scenario 1 vs. Scenario 2 Scenario 1: bending magnet ( α=54° ) and slit. The LBS dump placed in the tunnel ceiling. Scenario 2: bending magnet ( α=35° ) and no slit. The LBS dump placed in the tunnel shielding. First guess dimensions: 1.5 m max. length, 50 cm max diameter. Preliminary discussion with Civil Engineering (N. Lopez-Hernandez): 1.Scenario 1: more complicated installation. Detailed analysis of dump infrastructure needed. 2.Scenario 2: slot for dump will be drilled. No need for wall partial dismantling. 3.Time of operation: ≈3-5 days. 4.Drilling machine encumbrance: ≈1 m machine width + 1 m on each side. Preliminary discussion with RP (J. Vollaire): 1.Scenario 1: detailed evaluation of soil activation (fluence to TP9 gallery to be checked) 2.Scenario 2: issues about particle fluence to PSB tunnel