Booster Beam Notching Installation Update PIP Talk Salah Chaurize February 20, 2013.

Slides:



Advertisements
Similar presentations
Booster Cogging Robert Zwaska Fermilab (University of Texas at Austin) Accelerator Physics & Technology Seminar Dec. 8, 2005.
Advertisements

PIP and the Booster Notch Bob Zwaska October 12, 2011 PIP Meeting.
Proton Beam Measurements in the Recycler Duncan Scott On Behalf of the Main Injector Group.
Chris Smith Booster RF Cavity Upgrade Contents: The Booster Existing RF Cavities Why Upgrade? New Cavities Prototype Plans University Involvement Prototype.
Booster Corrector Upgrade October William Pellico.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
LINAC LASER NOTCHER READINESS REVIEW August 5 th, 2014 Kevin Duel – Mechanical Support Engineer.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
Craig Drennan Linac and Booster Beam Diagnostics Proton Source Workshop December 7 and 8, 2010.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Booster Beam Notching Overview for 2012 S. Chaurize December 7, 2011.
Booster Cogging Upgrades Craig Drennan, Kiyomi Seiya, Alex Waller.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Magnet Motion Produces Luminosity Loss. NLC Feedback Operation Kicker Gain Bunch Charge Measure deflected bunches with BPM and kick other beam to eliminate.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
STATUS OF NOKER PULSER FOR SHORT MAGNETS C. C. JENSEN DECEMBER 4, 2013.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Upgrading 600L/s IPPS Gustavo Alverio University of Central Florida August 5, 2003.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Accelerator Science and Technology Centre Extended ALICE Injector J.W. McKenzie, B.D. Muratori, Y.M. Saveliev STFC Daresbury Laboratory,
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
D.E. Johnson, T.R. Johnson, K.L. Duel, M. Gardner, V. Scarpine, R.J. Tesarek Motivation Notching process in the Booster creates about 30-35% of the total.
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Proton Source Improvement Workshop Cogging W. Pellico Dec 6&
Booster collimation system: status and future Valery Kapin PIP-II Collaboration Meeting 9-10 November 2015.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize.
PIP Wednesday March 21, /21/12 Agenda Project Update(s) Pellico - PIP Status Talk(s) 1.Ryan Crawford: Linac Power Distribution - Shutdown 2012 activities.
Craig Drennan Linac and Booster Beam Diagnostics Proton Source Workshop December 7 and 8, 2010.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Update of Booster Alignment & Magnet Moves February 20, 2013 Bill Marsh, Kiyomi Seiya, Dean Still, Kent Triplet Alex Waller.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
PIP Update Talk Booster Notched Beam Kicker Pulser General Talk The Long and Short of It S. Chaurize October 24, 2012.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Booster bpm’s Jim Crisp 3/29/06. Plate width and linearity with the response linearized along the axis 60 and 20 degree plates become nonlinear in the.
Booster Beam Notching PMG Meeting Salah Chaurize August 21, 2013.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update May 28 th Agenda Summary Update – Current Activities/Updates – Ken Domann.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Booster High Power RF at PIP-II Era John Reid February 18, 2014.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
PPP Booster. Outline of Booster PPP tasks Beam Quality Goals K Seiya W Pellico Injection Dave Johnson CY Tan W Pellico Capture CY Tan K Seiya W Pellico.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
MI/RR Status January 3, 2014 D. Capista. MI Preformance.
Booster Corrector Review, Oct. 10 th, 2006 E. Prebys Introduction/Specifications Eric Prebys Proton Plan Manager.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
BEAM TRANSFER CHANNELS, INJECTION AND EXTRACTION SYSTEMS
Hall C Down Stream Beam Pipe And Dump Interface Design
CNGS Primary Beam Results 2010
Presentation transcript:

Booster Beam Notching Installation Update PIP Talk Salah Chaurize February 20, 2013

Notching Pre-Shutdown – A 3 bucket gap is created using two kickers located at Long 5 and Long 12 Notcher – A High Voltage(55kV) Kicker at Long 5 Noker - Lower Voltage Kicker (20-40 kV) at Long 12 – Used to clean out remnant Notched Beam in buckets At 700 MeV – Beam is kicked vertically into collimator region at Long 6 and Long 13 with upstream gradient magnets seeing some deposited notched beam loss. – The notch timing and synchronization is accomplished by modules in the Booster LLRF Room and local timing modules. – Beam notch for non-cogged cycles occurs at 400 Mev – Cogged notch occurs close to 700 MeV

Notching Post Shutdown – A 3 bucket gap is created using three 1M Long kickers located at Long 12 3 Notchers – High Voltage(46kV) Kicker at Long 12 Notcher converted to NOKA Noker converted to NOKB Build/Commission new NOKC. – Beam is kicked Horizontally into new absorber at Long 13 – The notch timing and synchronization is accomplished by modules in Booster LLRF Room. (Same as before) – Extra Wide Aperture BPM and Short Corrector Spool needed. – Beam notch for non-cogged cycles occurs at 400 Mev. (Same as before) – Cogged notch occurs close to 700 MeV. (Same as before)

The Notch 3 Bucket Notch Width non-cogged Cycle 400MeV Cogged Cycle ~700MeV Extraction Loss

L5 Notcher Current Location Notcher magnet will be moved to L12 Vertical Pinger magnet will be removed from L12 and put here in its placeNotcher Hor. Pinger

L5 Notcher Power supply components such as these Will need to be moved to support Long 12 region CX1168 tube Low Level equipment CX1168 tube cabinet

L12 Pre-shutdown De-commissioned Horz. Pinger Ver. Pinger Noker MKS04 Beam direction

L12 Post Shutdown NOKC MKS04 NOKB NOKA

Kicker magnets rotated to kick Horizontally

Kicker Magnet Beam tubes exposed for alignment

L12 Noker & Extraction Kicker MKS04 Power supply components such as these will need to be installed/relocated to support notch2 & notch3 in east Booster Gallery CX1168 tube cabinet Beam sync Modules and other NIM crate Support modules.

Make Room For 2 more systems In East Gallery

Current Configuration In East Gallery NOKA NOKB NOKC goes Here

Current Configuration In East Gallery Noker PS Charging Resistors and load resistors

Current Configuration In East Gallery NIM Gate Modules Altera Based CAMAC Controls and Ramp Cards LeCroy Delay modules & CAMAC Trigger

Current Configuration In East Gallery Absorber Motion Controls

Current Configuration In East Gallery NOKA NOKB NOKC MKS04

Long 13 Beam direction Before After Standing at downstream end of absorber

Long 13 Notched beam absorber Beam direction Before After

Long 13 New absorber

Looking upstream towards L13 30” 75” 10 ‘ Before After

Reason to redesign S12 Spool piece Need to kick beam horizontally at L12 with beam Nokers to create a notch in the beam. Current aperture restriction at S12 is BPM plates and upstream and down stream bellows which are all 4.5in.

Reason to redesign S12 Spool piece New Extra Wide aperture BPM will give us 5 in aperture with new spool. New spool would use some of original spool design without the standard BPM components inside and larger aperture bellows at magnet spool flanges

Extra Wide Aperture BPM

S12 Corrector Original Standard aperture 4.5 Inch

S12 Corrector New 5” Aperture Spool

Preliminary Results and Commissioning – Using 2 Nokers to create gap in beam at 400MeV – S12 New BPM giving data but needs some gain tweaks – Absorber motion controls working well. – Notched beam loss is currently low due to low intensity running but is as expected.

Preliminary Results and Commissioning

NOKA(CH1) & NOKB(CH2) Notched Bunches

Thanks to: - L13 Notched Beam Absorber Assembly- PPD Experiment Fabrication- L13 Absorber Build and Assembly D.Erickson, J. Judd, W. Blaszynski, W. Gatfield V. Sidorov - L13 Absorber Mechanical Design APC Energy Deposition Simulations by- N.Mokhov, I. Tropin, S.Drozhdin M. Coburn L13 Absorber Motion Controls -L12, S12, L13 Upgrade Support- Mechanical Support/ Instrumentation Groups – L13/S12 BPM and Corrector R. Reily, B. Ogert, J. Kubinski, J. Briney,D. Wallace, J. Fitzgerald Controls Group CAMAC modules Booster Techs - Power supply and load reconfiguration New timing module build and support electronics R. Mraz, T. Boes, D. Dick Operations - Database work, O. Marshall, R. Jones AMG-L12, S12,L13 alignment Radiation Safety – Joel Fulgham Consultation – J. Lackey, B. Pellico Machine Shop, Welding Shop Many More I missed