Risk Management ©USC-CSSE.

Slides:



Advertisements
Similar presentations
Project management.
Advertisements

Software Quality Assurance Plan
Software Process Models
More CMM Part Two : Details.
University of Southern California Center for Systems and Software Engineering Risk Calculation Case Studies CS 510 Software Engineering Supannika Koolmanojwong.
Project What is a project A temporary endeavor undertaken to create a unique product, service or result.
University of Southern California Center for Systems and Software Engineering A Look at Software Engineering Risks in a Team Project Course Sue Koolmanojwong.
Using UML, Patterns, and Java Object-Oriented Software Engineering Royce’s Methodology Chapter 16, Royce’ Methodology.
Stepan Potiyenko ISS Sr.SW Developer.
University of Southern California Center for Software Engineering C S E USC Barry Boehm, USC USC-CSE Executive Workshop March 15, 2006 Processes for Human.
Software Risk Management and the COCOMO Model
University of Southern California Center for Software Engineering C S E USC Barry Boehm, USC CS 510, CS 577a Fall,2005 (
1 SOFTWARE PRODUCTION. 2 DEVELOPMENT Product Creation Means: Methods & Heuristics Measure of Success: Quality f(Fitness of Use) MANAGEMENT Efficient &
COMP8130 and 4130Adrian Marshall 8130 and 4130 Test Management Adrian Marshall.
Software Quality Assurance For Software Engineering && Architecture and Design.
Release & Deployment ITIL Version 3
Software Evolution Planning CIS 376 Bruce R. Maxim UM-Dearborn.
® IBM Software Group © 2006 IBM Corporation PRJ480 Mastering the Management of Iterative Development v2 Module 3: Phase Management - Inception.
What is Business Analysis Planning & Monitoring?
CMMI Course Summary CMMI course Module 9..
8. CMMI Standards and Certifications
CPTE 209 Software Engineering Summary and Review.
Introduction to Software Quality Assurance (SQA)
Introduction to RUP Spring Sharif Univ. of Tech.2 Outlines What is RUP? RUP Phases –Inception –Elaboration –Construction –Transition.
Chapter 2 The process Process, Methods, and Tools
Thirteenth Lecture Hour 8:30 – 9:20 am, Sunday, September 16 Software Management Disciplines Process Automation (from Part III, Chapter 12 of Royce’ book)
SPEAKER : KAI-JIA CHANG ADVISER : QUINCY WU DATA : Spiral Model.
Project Tracking. Questions... Why should we track a project that is underway? What aspects of a project need tracking?
University of Southern California Center for Systems and Software Engineering Incremental Commitment Spiral Model (ICSM) for CS 577 Barry Boehm, Supannika.
ECE450 - Software Engineering II1 ECE450 – Software Engineering II Today: Risk.
1 Project Risk Management Project Risk Management Dr. Said Abu Jalala.
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
IT Requirements Management Balancing Needs and Expectations.
Chapter 3 Project Management Details Tracking Project Progress Project Estimation Project Risk Analysis Project Organization RUP Project Management Workflow.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
© The McGraw-Hill Companies, Software Project Management 4th Edition Risk management Chapter 7.
CHECKPOINTS OF THE PROCESS Three sequences of project checkpoints are used to synchronize stakeholder expectations throughout the lifecycle: 1)Major milestones,
©Ian Sommerville 2000 Slide 1 Project management l Organising, planning and scheduling software projects l Objectives To introduce software project management.
University of Southern California Center for Systems and Software Engineering Barry Boehm, USC CS 510 Software Planning Guidelines.
Chapter 3 Project Management Chapter 3 Project Management Organising, planning and scheduling software projects.
University of Southern California Center for Systems and Software Engineering 09/02/09©USC-CSSE1 OCD Risk Management & DART CS 577a, Fall 2009 September.
Pre-Project Components
Ch 10 - Risk Management Learning Objectives You should be able to: List and describe risk management processes, inputs, outputs, and tools List and describe.
Search Engine Optimization © HiTech Institute. All rights reserved. Slide 1 What is Solution Assessment & Validation?
Requirements Management with Use Cases Module 10: Requirements Across the Product Lifecycle Requirements Management with Use Cases Module 10: Requirements.
J. Scott Hawker p. 1Some material © Rational Corp. Rational Unified Process Overview See and use the RUP Browser on lab machines.
Business Analysis. Business Analysis Concepts Enterprise Analysis ► Identify business opportunities ► Understand the business strategy ► Identify Business.
Software Project Management Lecture 5 Software Project Risk Management.
Chap 4. Project Management - Organising, planning and scheduling
Software Project Management (SEWPZG622) BITS-WIPRO Collaborative Programme: MS in Software Engineering SECOND SEMESTER /1/ "The content of this.
University of Southern California Center for Systems and Software Engineering Risk Management CS 577a, Fall 2010 November 24, /24/2010©USC-CSSE1.
Risk Analysis 19 th September, Risk vs. Problem Risk  An “uncertain event that “may” happen with some probability Problem  The above event.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
1 Software Risk Management : Overview and Recent Developments LiGuo Huang Computer Science and Engineering Southern Methodist University.
University of Southern California Center for Software Engineering C S E USC Barry Boehm, USC CS 510, CS 577a Fall 2015 Software Risk Management : Overview.
Project Management Strategies Hidden in the CMMI Rick Hefner, Northrop Grumman CMMI Technology Conference & User Group November.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
R i s k If you don’t attack risks, they will attack you.
Copy of the slides: (will also be put on the esse3 website)
Slide 3.1 © The McGraw-Hill Companies, 2002 SOFTWARE LIFE-CYCLE MODELS.
Software Development Process includes: all major process activities all major process activities resources used, subject to set of constraints (such as.
CMMI for Services, Version 1.3 Speaker: Business Excellence Date:
CS 577b: Software Engineering II
Software Risk Management : Overview and Recent Developments
Chapter 2 – Software Processes
CIS12-3 IT Project Management
Risk Management ©USC-CSSE.
Engineering Processes
Software Risk Management : Overview and Recent Developments
Presentation transcript:

Risk Management ©USC-CSSE

©USC-CSSE

Risk vs Issue A Risk is an uncertain event that could impact your chosen path should it be realised. Risks are events that are not currently affecting you – they haven’t happened yet.  Once a risk is realised, it has the potential to become an Issue Source: http://agile101.net/2009/07/26/agile-risk-management-the-difference-between-risks-and-issues/ ©USC-CSSE

Risk Management What is risk? What about problem, concern, issue? ©USC-CSSE

Reactively Managing a Software Development Problem System Integration Time: We just started integrating the various software components to be used in our project and we found out that COTS* products A and B can’t talk to one another This is a problem, caused by a previously unrecognized risk, that materialized: The risk that two COTS products might not be able to talk to one another; specifically that A and B might not be able to talk to one another) We’ve got too much tied up in A and B to change Our best solution is to build wrappers around A and B to get them to talk via CORBA** This will result in: a 3 month schedule overrun = $100K contract penalty a $300K cost overrun *COTS: Commercial off-the-shelf **CORBA: Common Object Request Broker Architecture ©USC-CSSE

Proactively Managing a Risk (assessment) System Design Time: A and B are our strongest COTS choices But there is some chance that they can’t talk to one another Probability that A and B can’t talk to one another = probability of loss: P(L) From previous experience, with COTS like A and B, we assess P(L) at 50% If we commit to using A and B, and we find out at integration time that they can’t talk to one another Size of loss S(L) = $300K + $100K = $400K We have a risk exposure of RE = P(L) * S(L) = (.5) * ($400K) = $200K ©USC-CSSE

Risk Management Strategy 1: Buying Information System Design Time: Let’s spend $30K and 2 weeks prototyping the integration of A and B This will buy information on the magnitudes of P(L) and S(L) If RE = P(L) * S(L) is small, we’ll accept and monitor the risk If RE is large, we’ll use one/some of the other strategies ©USC-CSSE

Other Risk Management Strategies Risk Avoidance COTS product C is almost as good as B, and we know, from having used A and C, that C can talk to A Delivering on time is worth more to the customer than the small performance loss Risk Transfer If the customer insists on using A and B, have them establish a risk reserve, to be used in case A and B can’t talk to each other Risk Reduction If we build the wrappers and the CORBA connections right now, we add cost but minimize the schedule delay Risk Acceptance If we can solve the A and B interoperability problem, we’ll have a big competitive edge on future procurements Let’s do this on our own money, and patent the solution ©USC-CSSE

Software Risk Management Identification Checklists Decision driver analysis Assumption analysis Decomposition Performance models Cost models Network analysis Decision analysis Quality factor analysis Risk exposure Risk leverage Compound risk reduction Buying information Risk avoidance Risk transfer Risk reduction Risk element planning Risk plan integration Prototypes Simulations Benchmarks Analyses Staffing Milestone tracking Top-10 tracking Risk reassessment Corrective action Risk Assessment Risk Analysis Risk Prioritization Risk Management Risk mgmt Planning Risk Control Risk Resolution Risk Monitoring ©USC-CSSE

Top 10 Risk Categories: 1989 and 1995 1. Personnel shortfalls 2. Schedules and budgets 3. Wrong software functions 4. Wrong user interface 5. Gold plating 6. Requirements changes 7. Externally-furnished components 8. Externally-performed tasks 9. Real-time performance 10. Straining computer science 1995 1. Personnel shortfalls 2. Schedules, budgets, process 3. COTS, external components 4. Requirements mismatch 5. User interface mismatch 6. Architecture, performance, quality 7. Requirements changes 8. Legacy software 9. Externally-performed tasks 10. Straining computer science ©USC-CSSE

Primary CS577 Risk Categories (all on 1995 list) and Examples Personnel shortfalls: commitment (This is team member’s last course; only needs C to graduate); compatibility; communication problems; skill deficiencies (management, Web design, Java, Perl, CGI, data compression, …) Schedule: project scope too large for 24 weeks; IOC content; critical-path items (COTS, platforms, reviews, …) COTS: see next slide re multi-COTS Rqts, UI: mismatch to user needs (recall overdue book notices) Performance: #bits; #bits/sec; overhead sources Externally-performed tasks: Client/Operator preparation; commitment for transition effort ©USC-CSSE

COTS and External Component Risks COTS risks: immaturity; inexperience; COTS incompatibility with application, platform, other COTS; controllability Non-commercial off-the shelf components: reuse libraries, government, universities, etc. Qualification testing; benchmarking; inspections; reference checking; compatibility analysis ©USC-CSSE

Risk Exposure Factors (Satellite Experiment Software) Unsatisfactory Outcome (UO) Prob (UO) Loss (UO) 10 8 7 9 3 4 1 5 2 Risk Exposure 3 - 5 4 - 8 5 6 8 1 2 30 - 50 24 - 40 28 - 56 45 15 24 8 30 7 4 A. S/ W error kills experiment B. S/ W error loses key data C. Fault tolerance features cause unacceptable performance D. Monitoring software reports unsafe condition as safe E. Monitoring software reports safe condition as unsafe F. Hardware delay causes schedule overrun G. Data reduction software errors cause extra work H. Poor user interface causes inefficient operation I. Processor memory insufficient J. DBMS software loses derived data ©USC-CSSE

Risk Reduction Leverage (RRL) Change in Risk Exposure / cost to implement avoidance method BEFORE - AFTER RISK REDUCTION COST Spacecraft Example LONG DURATION TEST FAILURE MODE TESTS LOSS (UO) PROB (UO) RE $20M 0.2 $4M $20M 0.2 $4M B B PROB (UO) RE 0.05 $1M 0.07 $1.4M A A COST $2M $0.26M 4-1 4- 1.4 = 1.5 = 10 RRL 2 0.26 ©USC-CSSE

Risk Management Plans For Each Risk Item, Answer the Following Questions: 1. Why? Risk Item Importance, Relation to Project Objectives 2. What, When? Risk Resolution Deliverables, Milestones, Activity Nets 3. Who, Where? Responsibilities, Organization 4. How? Approach (Prototypes, Surveys, Models, …) 5. How Much? Resources (Budget, Schedule, Key Personnel) ©USC-CSSE

Risk Management Plan: Fault Tolerance Prototyping 1. Objectives (The “Why”) Determine, reduce level of risk of the software fault tolerance features causing unacceptable performance Create a description of and a development plan for a set of low-risk fault tolerance features 2. Deliverables and Milestones (The “What” and “When”) By week 3 1. Evaluation of fault tolerance option 2. Assessment of reusable components 3. Draft workload characterization 4. Evaluation plan for prototype exercise 5. Description of prototype By week 7 6. Operational prototype with key fault tolerance features 7. Workload simulation 8. Instrumentation and data reduction capabilities 9. Draft Description, plan for fault tolerance features By week 10 10. Evaluation and iteration of prototype 11. Revised description, plan for fault tolerance features ©USC-CSSE

Risk Management Plan: Fault Tolerance Prototyping (concluded) Responsibilities (The “Who” and “Where”) System Engineer: G. Smith Tasks 1, 3, 4, 9, 11, support of tasks 5, 10 Lead Programmer: C. Lee Tasks 5, 6, 7, 10 support of tasks 1, 3 Programmer: J. Wilson Tasks 2, 8, support of tasks 5, 6, 7, 10 Approach (The “How”) Design-to-Schedule prototyping effort Driven by hypotheses about fault tolerance-performance effects Use real-time OS, add prototype fault tolerance features Evaluate performance with respect to representative workload Refine Prototype based on results observed Resources (The “How Much”) $60K - Full-time system engineer, lead programmer, programmer (10 weeks)*(3 staff)*($2K/staff-week) $0K - 3 Dedicated workstations (from project pool) $0K - 2 Target processors (from project pool) $0K - 1 Test co-processor (from project pool) $10K - Contingencies $70K - Total ©USC-CSSE

Risk Monitoring Milestone Tracking Top-10 Risk Item Tracking Monitoring of risk Management Plan Milestones Top-10 Risk Item Tracking Identify Top-10 risk items Highlight these in monthly project reviews Focus on new entries, slow-progress items Focus review on manger-priority items Risk Reassessment Corrective Action ©USC-CSSE

Project Top 10 Risk Item List: Satellite Experiment Software Mo. Ranking This Last #Mo. Risk Item Risk Resolution Progress Replacing Sensor-Control Software 1 4 2 Top Replacement Candidate Unavailable Developer Target Hardware Delivery Delays 2 5 2 Procurement Procedural Delays Sensor Data Formats Undefined 3 3 3 Action Items to Software, Sensor Teams; Due Next Month Staffing of Design V&V Team 4 2 3 Key Reviewers Committed; Need Fault- Tolerance Reviewer Software Fault-Tolerance May 5 1 3 Fault Tolerance Prototype Successful Compromise Performance Accommodate Changes in Data 6 - 1 Meeting Scheduled With Data Bus Bus Design Designers Testbed Interface Definitions 7 8 3 Some Delays in Action Items; Review Meeting Scheduled User Interface Uncertainties 8 6 3 User Interface Prototype Successful TBDs In Experiment Operational - 7 3 TBDs Resolved Concept Uncertainties In Reusable - 9 3 Required Design Changes Small, Monitoring Software Successfully Made ©USC-CSSE

Early Risk Management in 577 Project Tasks Risk Management Skills; Skill-building activities Select projects; form teams Project risk identification Staffing risk assessment and resolution - Readings, lectures, homework, case study, guidelines Plan early phases Schedule/budget risk assessment, planning Risk–driven processes (ICSM) - Readings, lectures, homework, guidelines, planning and estimating tools Formulate, validate concept of operation Risk-driven level of detail - Readings, lecture, guidelines, project Manage to plans Risk monitoring and control Develop, validate FC package Risk assessment and prioritization FC Architecture Review Risk-driven review process Review of top-N project risks Readings, lecture, case studies, review ©USC-CSSE

Software Risk Management Techniques Source of Risk Risk Management Techniques 1. Personnel shortfalls Staffing with top talent; key personnel agreements; team-building; training; tailoring process to skill mix; walkthroughs 2. Schedules, budgets, Process Detailed, multi-source cost and schedule estimation; design to cost; incremental development; software reuse; requirements descoping; adding more budget and schedule; outside reviews 3. COTS, external components Benchmarking; inspections; reference checking; compatibility prototyping and analysis 4. Requirements mismatch Requirements scrubbing; prototyping; cost-benefit analysis; design to cost; user surveys 5. User interface mismatch Prototyping; scenarios; user characterization (functionality; style, workload); identifying the real users ©USC-CSSE

Software Risk Management Techniques Source of Risk Risk Management Techniques 6. Architecture, performance, quality Simulation; benchmarking; modeling; prototyping; instrumentation; tuning 7. Requirements changes High change threshold: information hiding; incremental development (defer changes to later increments) 8. Legacy software Reengineering; code analysis; interviewing; wrappers; incremental deconstruction 9. COTS, Externally-performed tasks Pre-award audits, award-fee contracts, competitive design or Prototyping 10. Straining computer science Technical analysis; cost-benefit analysis; prototyping; reference checking ©USC-CSSE

Validation Results on Process Adoption Incidents of Process Selection and Direction Changes #of teams Results on Project Process Selection 8/14 Selected the right process pattern from the beginning 3/14 Unclear project scope ; re-select right at the end of the Exploration phase 1/14 Minor changes on project scope ; right at the end of the Valuation phase Major change in Foundations phase Infeasible project scope ©USC-CSSE

Top 10 Risk Categories: 1995 and 2010 1. Personnel shortfalls 1. Customer-developer-user team cohesion 2. Schedules, budgets, process 2. Personnel shortfalls 3. COTS, external components 3. Architecture complexity; quality tradeoffs 4. Requirements mismatch 4. Budget and schedule constraints 5. User interface mismatch 5. COTS and other independently evolving systems 6. Architecture, performance, quality 6. Lack of domain knowledge 7. Requirements changes 7. Process Quality Assurance 8. Legacy software 8. Requirements volatility; rapid change 9. Externally-performed tasks 9. User interface mismatch 10. Straining computer science 10. Requirements mismatch ©USC-CSSE

Primary CS577 Risk Categories (all on 1995 list) and Examples Personnel shortfalls: commitment (This is team member’s last course; only needs C to graduate); compatibility; communication problems; skill deficiencies (management, Web design, Java, Perl, CGI, data compression, …) Schedule: project scope too large for 24 weeks; IOC content; critical-path items (COTS, platforms, reviews, …) COTS: see next slide re multi-COTS Rqts, UI: mismatch to user needs (recall overdue book notices) Performance: #bits; #bits/sec; overhead sources Externally-performed tasks: Client/Operator preparation; commitment for transition effort ©USC-CSSE

Top 11 - Risk distribution in CSCI577 ©USC-CSSE

Comparing between risks in Fall and Spring ©USC-CSSE

Conclusions Risk management starts on Day One Delay and denial are serious career risks Data provided to support early investment Win Win spiral model provides process framework for early risk resolution Stakeholder identification and win condition reconciliation Anchor point milestones Risk analysis helps determine “how much is enough” Testing, planning, specifying, prototyping,… Buying information to reduce risk ©USC-CSSE

Quality Management ©USC-CSSE

Outline Quality Management In CMMI 1.3 In ISO 15288 In CSCI577ab (c) USC-CSSE

Objectives of QM To ensure the high quality process in order to deliver high quality products (c) USC-CSSE

Quality Management in CMMI 1.3 Process Areas Configuration Management (CM) Product Integration (PI) Causal Analysis and Resolution (CAR) Project Monitoring and Control (PMC) Decision Analysis and Resolution (DAR) Project Planning (PP) Integrated Project Management (IPM) Quantitative Project Management (QPM) Measurement and Analysis (MA) Requirements Development (RD) Organizational Performance Management (OPM) Requirements Management (REQM) Organizational Process Definition (OPD) Risk Management (RSKM) Organizational Process Focus (OPF) Supplier Agreement Management (SAM) Organizational Process Performance (OPP) Technical Solution (TS) Organizational Training (OT) Validation (VAL) Process and Product Quality Assurance (PPQA) Verification (VER) (c) USC-CSSE

PPQA - Product and Process Quality Assurance (c) USC-CSSE

PPQA - Product and Process Quality Assurance (c) USC-CSSE

PPQA for Agile development (c) USC-CSSE

CM – Configuration Management (c) USC-CSSE

CM – Configuration Management (c) USC-CSSE

CM – Configuration Management (c) USC-CSSE

MA – Measurement and Analysis (c) USC-CSSE

VER - Verification (c) USC-CSSE

VER - Verification (c) USC-CSSE

VAL - Validation (c) USC-CSSE

VAL - Validation (c) USC-CSSE

Quality Management in ISO 15288 Activities Plan quality management. Establish quality management policies Establish organization quality management objectives Define responsibilities and authority for implementation of quality management. Assess quality management. Assess customer satisfaction and report. Conduct periodic reviews of project quality plans. The status of quality improvements on products and services is monitored. Perform quality management corrective action. Plan corrective actions when quality management goals are not achieved. Implement corrective actions and communicate results through the organization. (c) USC-CSSE

Configuration Management in ISO 15288 Activities Plan configuration management. Define a configuration management strategy Identify items that are subject to configuration control. Perform configuration management Maintain information on configurations with an appropriate level of integrity and security Ensure that changes to configuration baselines are properly identified, recorded, evaluated, approved, incorporated, and verified. (c) USC-CSSE

Quality Management in 577ab IIV&V Configuration Management Defect Reporting and Tracking Testing Buddy Review Architecture Review Board Core Capability Drive through Design Code Review Document template Sample artifacts (c) USC-CSSE

Quality Guidelines Design Guidelines Coding Guidelines Describe design guidelines on how to improve or maintain modularity, reuse and maintenance How the design will map to the implementation Coding Guidelines Describe how to document the code in such as way that it could easily be communicated to others (c) USC-CSSE

Coding Guidelines C: http://www.gnu.org/prep/standards/standards.html Java: http://geosoft.no/development/javastyle.html Visual Basic: http://msdn.microsoft.com/en-us/library/h63fsef3.aspx (c) USC-CSSE

Quality Guidelines Version Control and History Chronological log of the changes introduced to this unit Implementation Considerations Detailed design and implementation for as-built considerations Unit Verification Unit / integration test Code walkthrough / review / inspection (c) USC-CSSE

Quality Assessment Methods Methods, tools, techniques, processes that can identify the problems Detect and report the problem Measure the quality of the software system Three methods of early defect identification peer review, IIV&V, Automated Analysis (c) USC-CSSE

Peer Review Reviews performed by peers in the development team Can be from Fagan’s inspections to simple buddy checks Peer Review Items Participants / Roles Schedule (c) USC-CSSE

Defect Removal Profiles (c) USC-CSSE