TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

Saturday May 02 PST 4 PM. Saturday May 02 PST 10:00 PM.
TB Peter Glässel, Heidelberg1 TPC Status.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
MONDAYTUESDAYWEDNESDAYTHURSDAYFRIDAYSATURDAYSUNDAY WEEK WEEK WEEK WEEK WEEK CALENDAR PROJECT.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
winter shutdown planning A.Tauro
MoEDAL MoU EDMS No Issues from LHCb & CERN  MoEDAL at IP8  Infrastructure  TimePix Deployment  Access & Safety  General Conditions MoEDAL.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
108 Mar 2007L. Musa TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa Outline Pre-commissioning above ground (2006) Preparing for.
ALICE 5 o’clock meeting Wk 49
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
SU ACTIVITIES PENDANT LS1 CMS ALICE. Antje Behrens | SU pendant LS1 day| | EDMS | page 2 CMS Quoi (quelles activités prévues pendant.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
Inventory of radioactive sources present in the cavern at pit 8 Gloria Corti Experimental Area Meeting 05 August 2008.
1/6 ALICE GLIMOS, Marc Tavlet Hazards and Safety in ALICE - Ways to reduce the risks Presentation at the ALICE Club, Monday, December 1 st, 2003 by Marc.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
Changes to the Hours of Service Regulations For Truck Drivers Rob Abbott Vice-President of Safety Policy American Trucking Associations.
Marc Tavlet - GLIMOS1 Paperwork needed to come and work at CERN 1. Access Rights – Registration 2. Tests with Beams 3. Safety Procedures to work at Point-2.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
ALICE planning meeting /2/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 9&10 A.Tauro
1 Safety and Database Subsection ADO - PO - SA Main safety projects / activities Main safety projects / activities RP issues RP issues Patrols Patrols.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
TPC Collaboration Meeting Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
LHC ACCESS SYSTEM 1 EDMS: January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January.
ALICE 5 o’clock meeting Wk 49
Access system global tests M. Gruwé LHCCWG January 15 th 2007.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
ALICE 5 o’clock meeting Wk 51.
ALICE planning meeting
Some arrangements for personnel safety 1- Procedures for access
TS2 preparatory meeting
LS1 planning meeting
Helium spill in LHC tunnel
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
ALICE TC meeting – Plans for the next technical stop
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
Cryogenic Risk Assessment in LHC
LHCb & EYETS
ALICE 5 o’clock meeting Wk
Presentation transcript:

ALICE 5 o’clock meeting Wk 51

INDICO You’ll find this meeting here: – The full shutdown planning is here: –

20/12/105 o’clock meeting3 Access request Cavern and surface You should submit an ADI and a task procedure Two persons minimum Work breakdown structure – risk associated at each step ADI Task procedure Template EDMS Attach task procedure

20/12/105 o’clock meeting4 ALICE Christmas break schedule OpenExperiment TRD EMCal CloseExperiment Open L3 doors Close L3 doors

20/12/105 o’clock meeting5 UX25 access Rules for access restrictions: Removal/installation of shielding (restriction includes RB24 triplets) PX24 blocks: no access CR5 and UX25 PX24 beams (35t): no access CR1-5, Expo, and UX-25 All other blocks: no access to UX-25 LHC evacuation test (7/12 after 18:00 and 24/12 tbc) – no access UX25 Gas functional test (10/ hrs) – no access UX25 and CR1-5 AUG test (20/1) (Arrêt Urgence General – General Emergency Stop) – no access UX25 DSO test (12-13/1) (Department Safety Officer) – no access UX25 No access SX2 during manipulation of blocks in SX2 (except ACR and WRs)

20/12/105 o’clock meeting6 L3 (and MNF) access EMCal No Ventilation Wks 50 and 4: access (TPC) to be coordinated with TC (transport) Wks 1-2: no access during EMCal SMs insertion inside L3 (see day-by-day) When moving from low-beta to yellow platform: no access to MNF When inserting the module: no access L3 and MNF Watcher needed in wk 49 and from wk 4 onwards Wk 6 or 7 (tbd): Kr calibration – TPC T stability (all interventions to be agreed by TC/RC) 31 Evac. No Ventilation 243 No Ventilation 13 7

Day-by-day schedule UX25 and MNF - Wk 51

20/12/105 o’clock meeting8 GS/ASE: UX25 fire detection maintenance ALTEADL unload in SXL2 2 EMCal modules Activities: TRD: installation BBF rails SR16-15 Survey: TRD and EMCal survey TPC: replacement 1 FE card (A-side) PMD+Pieter: move detector in parking position Week /12 Monday

20/12/105 o’clock meeting9 Activities in UX25 - Week /12 Monday TRD and EMCal Survey Prepare TRD 16 installation EMCal Survey (1/2 day) TPC FEC

20/12/105 o’clock meeting10 Activities in MNF - Week /12 Monday Move PMD in parking position

20/12/105 o’clock meeting11 Google Streetview visit (5 people). 16:15 GS/ASE: UX25 fire detection maintenance DAQ: switch off DAQ. The ACR PCs will be left ON to give access to the DCS for the detectors teams who need it DCS: the access restrictions to the DCS network will be enforced from December 21st towards the end of working hours Activities: TRD: install TRD16 Philippe+Didier: removal ladder BKF PMD: replacement electronics chains Week /12 Tuesday

20/12/105 o’clock meeting12 Activities in UX25 - Week /12 Tuesday Install TRD 16

20/12/105 o’clock meeting13 Activities in MNF - Week /12 Tuesday PMD: replacement electronics chains

20/12/105 o’clock meeting14 Activities in UX25 - Week /12 Wednesday TRD Survey Prepare TRD 15 installation Connect TRD 16 Visit: RIKEN RIBF Accelerator technical coordination group. Ken Oyama

20/12/105 o’clock meeting15 Activities in MNF - Week 51 22/12 Wednesday PMD: replacement electronics chains

20/12/105 o’clock meeting16 Activities in UX25 - Week /12 Thursday Install TRD 15 Connect TRD 16 TRD Survey

20/12/105 o’clock meeting17 Activities in MNF - Week /12 Thursday PMD: replacement electronics chains

20/12/105 o’clock meeting18 Activities in UX25 - Week /12 Friday LHC evacuation test. no access UX25

20/12/105 o’clock meeting19 Activities in MNF - Week /12 Friday LHC evacuation test. no access UX25

20/12/105 o’clock meeting20 Activities in UX25 - Week /12 Saturday Christmas day

20/12/105 o’clock meeting21 Activities in MNF - Week /12 Saturday PMD: replacement electronics chains

20/12/105 o’clock meeting22 Activities in UX25 - Week /12 Sunday TRD team at CERN: 26 to 30/12

20/12/105 o’clock meeting23 Activities in MNF - Week /12 Sunday PMD: replacement electronics chains

20/12/105 o’clock meeting24 DCS plans Wk 51 –Contingency for system upgrades –Support to detectors restarting/testing their systems after upgrades Detectors shall test functionality as much as possible –Tue 21/12 PM: Limit access to DCS cluster during end-of-year closure Register with your SRC if you require access (see message Peter 2/12/2010) Wk 52 – Wk 01 –Only ‘best effort’ support during CERN closure André / Peter

20/12/105 o’clock meeting25 AOB -