04ABR07Calo Commissioning Meeting - Xvc1 Power Supplies Xavier Vilasis-Cardona
04ABR07Calo Commissioning Meeting - Xvc2 Outline Status of ECS for the Global Commissioning test –Power Supplies –Other issues
04ABR07Calo Commissioning Meeting - Xvc3 Status of ECS for Global Commissioning Test HCAL FE card control – see Frederic’s presentation HV-LED System – see Anatoli’s presentation Databases – see Yuri’s presentation DSS – see Laurent’s presentation Power Supplies
04ABR07Calo Commissioning Meeting - Xvc4 Power Supplies – FE systems SystemsPower Supply TypePS location ECAL CrateWiener MarathonBehind Crate HCAL CrateWiener MarathonBehind Crate PRS/SPD CrateWiener MarathonBehind Crate HCAL HV-LED systemAgilentBarrack ECAL HV-LED systemAgilentBarrack PRS/SPD HV-LED systemAgilentBarrack PRS/SPD VFEWiener MarathonTop of FE Crates Monitoring Radiative Source *Wiener MarathonTop of FE Crates LED SystemWiener MarathonTop of FE Crates * Plus dedicated non interruptable 230V AC
04ABR07Calo Commissioning Meeting - Xvc5 Remote Controlled Wiener Marathon Power Supplies Power Supply close to FE/VFE electronics Remote Control Module in the barracks –One RCM can control up to 2 PS –Except for PRS/SPD VFE PS (double) –Each RCM has an IP address Soft Control for RCMs provided by Online Group –for crate PS –one central PC (or PVSS project) to control all –not for LED-VFE ones –Software is not ready for Remote Controlled PS (only for local ones)
04ABR07Calo Commissioning Meeting - Xvc6 Agilent Power Supplies Specific for the Calorimeter Five Agilent PS's will be used for producing middle voltages (100, 150, 30, 18 V) for calorimeter sub-detectors. –ECAL four units PS (100V, 30V,100V, 30V for A and C sides); –HCAL four units PS (100V, 30V,100V, 30V for A and C sides); –PS/SPD one unit PS (150V for side A); –PS/SPD one unit PS (150V for side C); –PS/SPD two units PS (18V, 18V for side A and C); May be will be excluded and on platform Maraton PS will be used Each PS has a control unit working by ethernet (IP address) Control to be provided by us (Calo Group)
04ABR07Calo Commissioning Meeting - Xvc7 Summary Wiener Marathon Agilent CratesHV-LEDVFE Wiener RCMs Agilent RCMs ECAL HCAL PRS/SPD Total
04ABR07Calo Commissioning Meeting - Xvc8 RCMs location Wiener Marathon RCM crates are located in rack B1B01 –Together with 380V PSs –One crate can host 21 RCM –We can use one crate per detector side Agilent PS and controls are located in rack D3B04 PS control PCs shall be located in D2C06 or D2C07 (TBD)
04ABR07Calo Commissioning Meeting - Xvc9 LV Control PCs Calorimeter LV control PCs –Control of Agilent PS –Control of Wiener Marathon for VFE (?) One PC could do it all We keep one PC per TFC partition –ECAL –HCAL –PRS/SPD
04ABR07Calo Commissioning Meeting - Xvc10 GCT – Involved Racks Start testing C-side Inner part of detector –HCAL - crate 23, rack L3A03 –ECAL - crate 14, 13, 12, 11 - racks L3B01, L3B02 –PRS/SPD - crate 2, 3 - racks L3B01, L3B02 –Power Supplies Marathon Control Modules and Primary Power for Marathon Power Supplies on crate B1B01 Agilent Power Supplies on D3B04 –Control PCs for SPECS and CAN on D2C03 –Control PCs for CCPC on D2C07 –Control PCs for Power Supplies on D2C06 or D2C07 tbd –Calo TELL1 and L0 on D3B01 - D3B02
04ABR07Calo Commissioning Meeting - Xvc11 Other issues Ordered Online PCs –SPECS HCAL C-side - hcdaq02w ECAL C-side Rad Source Monitoring –PS Control HCAL - hcdcs01w Created Online Accounts SPECS PCs Operating System –Windows ?