STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.

Slides:



Advertisements
Similar presentations
Results of dosimeter readings in IR3 and IR7 DGS-RP High Level Dosimetry LHC Collimation WG meeting 03/09/2012.
Advertisements

The Preassembling Installation Survey & Alignment Accelerator Center of IHEP Qu Huamin 2006 / 4 / 27.
Sat 17/9 – Sun 18/9 07:00 Cryo problem in point 4 From E. Blanco: First beam dump caused by a cryo PLC not reachable anymore (UX45_QUI) and then 14 minutes.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Remote Handling design progress for the Collimation Upgrade project Keith Kershaw EN-HE 6 June 2011.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
TCDI operation until LS2 LIU-SPS-to-LHC Transfer Line Protection Devices (TCDI) Review 1 Oliver Aberle 26/03/2014 O. Aberle (EN-STI-TCD)
LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
LIU – TCDI. INTEGRATION STATUS 1 ST APRIL 2015 Frédéric Galleazzi EN/MEF/INT Antoine Kosmicki EN/MEF/INT EDMS :
Alice overview New detector and chamber ALICE TC.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Collimation Working Group #137 Collimator Alignment Controls Patrick Bestmann20/02/2012.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
News and hot topics Impedance meeting 14/04/2014.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
 Based on 2+2 Roman Pot Stations on each side of ATLAS at ~ 240 m from the Interaction Point  Aim in Run 2 at measuring the total cross section and.
Draft MD Planning Thu (3.11.) DayTimeMDMP Thu05:00 Ramp down, cycle 07: GeV: Injection stability and losses – check steering constraints, define.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
LHC machine status ~ Daily Summary ~ Daily beam commissioning meeting Week 42 - October 13 th, 2015 CERN, Geneva, CH M. Lamont and S. Redaelli for the.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12.
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE) Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE)
HiRadMat status report Adrian Fabich HiRadMat EAM, 4. March 2016 EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
Remote Measurement and Alignment Applications for Survey and Alignment P. Bestmann for BE/ABP/SU
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Collimation Activities during EYETS
Framework Schedule from EYETS 2016 to LS2
TAXS and TAXN ABSORBERS - OVERVIEW
Equipment simplified model SMR UR safety
ELENA installation and commissioning status
Installation of an Instrument on a CERN machine
LIU–PLI report LIU SPS meeting.
EN-STI activities in LHC during EYETS
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Planned activities on collimator for LS1
WPs concerned by L4 connection:
The 11T cryo-assembly: summary of design and integration aspects
Disabling Rules.
LHC Injection and Dump Protection
BLM planning 03/03/2014.
LS1 status 28/04/2014.
Cryomodule Assembly Plan
Experimental Areas – LS2 planning
Presentation transcript:

STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011

Overview  Situation today  Planned for Winter stop 2011/12  To be done in LS 1: 2013/14  To be done for LS2  Questions and Discussion 26/09/ CWG

Situation today 26/09/ CWG  Alignment in general:  Lower support part is aligned in the tunnel (with a dummy collimator (1/10 in weight);  Every collimator is prepared on surface to reference values Flange centre is the reference Aligned to the three supporting points Alignment transferred to fiducials on top of the collimator  Phase 1 installed and running since 2 years  Checks with beam based alignment procedure twice a year  Three versions:  Ring collimators in IR 3 and 7 (for remote handling and survey)  Ring collimators with “low” dose levels, not remote handling  Transfer line collimators (no plug-in system)

Situation today 26/09/ CWG  In March 2011, some collimators have been identified to need re-alignment. (an angular misalignment >1.9mrad on TCLA.A7R7.B1, TCTH.4L2.B1 and TCSG.A5L3.B2).  Reasons identified as:  conflict with adjacent vacuum chamber  Installation protection added on the support  IR extremities, dead end extrapolation

Situation today 26/09/ CWG  IR 3 and IR 7, warm section  TCSM locations prepared: 1. Base support installed 2. Cables up to the last few meters ready (No BPM!) 3. Rack space reserved, has to be reorganized 4. Vacuum replacement chambers ok TCSM + TCS slots

Situation today 26/09/ CWG  IR 7 is prepared for TIM manipulation  IR 3 will be equipped equally (stretched wire, additional targets)  Re-alignment upon request, two smoothening campaigns since first installation  LHC Smoothing should be followed by systematic collimator realignment in the future  All installed supports are “pre-aligned” but all installed new collimators need to be checked

Situation today 26/09/ CWG EMPTY PHASE II TCSM SLOT (30 IN TOTAL) PHASE I TCSG SLOT

Situation today – IR 2 26/09/2011 CWG 8 Current situation 4L2, part of VACSEC A4L2.C Insertion of a TCTVA Arc 1-2 IP2: ALICE Collimator areaID800 area Courtesy Eric Page

To be done in WS 2011/12 26/09/ CWG  IR 2 (if ECR is approved)  2 new TCTVA’s (TCLP collimators)  Layout change with new alignment (ca. 40 m on each side)  Use of mobile cryo-protections

To be done in LS 1: 2013/14 26/09/ CWG  IR 3 in 2013/14 (combined betatron/momentum cleaning in IR3 )  8 locations of phase 2 (TCSM) ok  Use Scraper location for additional TCP, Layout modification (Cooling and cables ok, supports and vacuum chambers to do)  IR 7 in 2013/14  22 locations to be equipped with phase 2 plug-ins. Alignment of supports for phase2.  Points to work on:  Pull cables for BPMs (IR3, other points, TCT?)  Work on flow rate/distribution for the final system (flow-fix?), upgrade of CV pumping system.  Auto retraction – clutch?

To be done in LS 1: 2013/14 26/09/ CWG  Produce and install cryo-protections?  IR 6 (Beam dump line modification (TCDQ, TCS...later?)  2 new TCSP’s  BPM cables  Start replacing TCT’s with TCTP’s (with BPM), IR with priority?  Pull cables for BPM’s to defined positions?

To be done/prepared for 2017? 26/09/ CWG  IR 1 and 5  4 TCLP’s (at Totem location)  Install supports, alignment  Produce and install cryo-protections? Mobile as for IR 2?  Replace all TCT’s with TCTP’s (with BPM)  Replace other collimators with BPM version  Cryo-solution?

Questions and Discussion 26/09/ CWG  Number of new collimators to be produced?: What type?  Change scraper locations (2) in IR 3 to TCP? Integration Change scraper locations (6) in IR 7 to hollow ebeam-lense?  Integrate TCT‘s into the Layout (IR 2 under study, IR 6, IR 8?)  Remove Roman Pots and install TCLP‘s to Point 1 and 5. When?  Keep and align Phase 2 slots?  Transfer lines?  Dump line?

Questions and Discussion 26/09/2011 CWG 14  Any alignment related observations during operation?  Tolerance for realignment IR7 and IR3 (OP needs vs. RP)  What can be compensated by the collimators (transversal offsets, rotations)  Requests for LS1