September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation DOE Annual Review Controls, Diagnostics, Vacuum, Cooling.

Slides:



Advertisements
Similar presentations
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
Advertisements

MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Costing Meeting Ajit Kurup 13 th June Page 2 Costing Meeting 13 th June 2011 Ajit Kurup Summary of CERN costing workshop. Proposed Level 3 breakdown.
Overview of the Schedule and Budget for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown.
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
MOM Report Galina Vankova RAL, MICE Video Conference.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
Collider-Accelerator Department EBIS Commissioning Accelerator Readiness Review (ARR) Training, Prior Reviews, Configuration Management Action Item Tracking.
1 BROOKHAVEN SCIENCE ASSOCIATES CCW Plant Expansion & CCW Piping Thomas F. Joos, PE Lead Civil/Structural Engineer CFAC Review March 10-11, 2009.
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
May 4, 2010 EBIS ARR Jim Alessi May 4- 7, 2010 Pre-commissioning and Commissioning.
D. Beavis (RSC) May 4, 2010 EBIS ARR Radiation Safety.
EBIS ARR Jim Alessi May 4- 7, 2010 Technical Overview.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
September 19-20, 2007 L. Snydstrup Structural Components WBS 1.1 Structural Components Status DOE Annual Review Lou Snydstrup September 19-20, 2007.
REMOTE-HANDLING OVERVIEW I. Bailey Cockcroft Institute / University of Liverpool.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
EBIS Accelerator Readiness Review Hazards and Controls for Pressure Systems May 4-7,
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Robert Pak, FVTX Annual Review Nov Mechanical Integration WBS Robert Pak Brookhaven National Laboratory.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Michał Matusiak Sławomir Wronka
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Overview on the Proposal for a new Gamma Irradiation Facility at CERN GIF++ Mar CAPEANS April 29 th, 2009 April 29, 091M.C.
Installation of the T600 at Fermilab CSN2, September 22,
Xenon Delivery Japan 1 MCHF 575 kCHF granted Additional grant 656 kCHF Last 50l subject to negotiation.
VAC – CTRL SYS internal meeting, 14 Dec A list of topics Start of the disassembly works: mid Jan. At first the W arm shall be off- service, then.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Accelerator Support and Maintenance Startup for Run 13.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
O. Kester, NuSTAR annual meeting, 27/02/2013
HTS-2 – FY17 Budget Request Joe Ozelis, Sr. Eng. Physicist PIP-II Budget Retreat 26 April, 2016.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
ELENA installation progress F. Butin / ELENA collaboration.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Francois and Lau EATM 17 July 2012
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
ARIEL Phase I Operations
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
as a prototype for Super c-tau factory
Progress in the ITER Neutral Beam Test Facility
Injector/Linac Design Status C. E
Presentation transcript:

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation DOE Annual Review Controls, Diagnostics, Vacuum, Cooling Systems, Installation Lou Snydstrup September 19-20, 2007

L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation EBIS Pre-Assembly Area Final Installation Site Booster 1.10 Installation – Facility Site Building 930 Now planning to install the EBIS Source at the final site ahead of baseline schedule of 9/08

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Installation – EBIS Pre-Assembly E-Gun Drift Tube Structure Electron Collector Superconducting Solenoid Vacuum and High Voltage Testing

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Installation – Pre-Assembly Area EBIS Stand Pre-Assembly Area Pre-Assembly Area and Superconducting Solenoid Acceptance Test

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation 5 SSMS 1.10 Installation – SSMS Stand/Transport

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Installation – SSMS Stand/Transport

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Installation – EBIS/Support Systems

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Installation – EBIS Install Flowchart EBIS Pre-Assembly Elec. Subsystems Power Distribution

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Controls Procurements < $25k –COTS items -- received –5 small orders of custom-built electronics -- received Procurements > $25k Scheduled Delivery –VME chassis (6)imminent –Dual channel PSIs (39)end-Sept –Quad waveform generators (19)mid-Dec –Single channel PSIs (66)mid-Dec EBIS cable and console computer orders deferred to FY08 Accelerator & Beam Line controls planned for FY08

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Controls EBIS Controls (>$25k) PO Value-unburden –VME chassis Placed $ 36k –PSI’s - Power supply interfaces Placed $116k –Quad waveform generators Placed $ 39k $191k Total Spent/Committed to date: $285k Total Expected Material Costs including Accelerator & Beam Line controls:$426k Percentage Spent/Committed: 67%

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Diagnostics Current Transformer Prototype in progress –Central Shops working on mechanical enclosure parts < 10% of construction budget spent (FY’08 procurements) Ferrite Core Iron Shield

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Vacuum Systems Qty POValue Pumps: –Turbo Pumps7 (all) Placed$73K –Cryo Pumps5 Placed $82K Vacuum ValvesEBIS Placed $51.4K Instrumentation/Controls –PLC Placed $12.6K –Gauge/Contr Placed$28.5K Beam Port Beam Tube Complete$24.5K Total Spent/Committed$272K* Total Expected Material Cost$789K Percentage Spent/Committed34% * $83K lower procurement costs than estimated

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Cooling Systems Preparation of Cooling Systems at Facility Site –Removed Legacy Piping –Extended Existing NSRL Power Supply DI Water –Tapped into Existing Chill Water System –Tapped into Existing Compressed Air Total Spent$17.8K Total Expected Material/Labor Cost$143K Percentage Spent12%

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation Facility Schedule Beam Port InstallationCompleted Building 930 Addition –Ready to Occupy9/30/2007 Electrical Distribution –Substation Installation8/6-9/28/2007 –Distribution Panels/Disconnects8/31-10/15/2007 –Cable Tray, Main Runs10/15-12/31/2007 Total Spent$105K Total Expected Material/Labor Cost$290K Percentage Spent36%

September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation 15 Summary For WBS 1.10 we are striving for the installation of the EBIS in the facility site by April-May 2008, ahead of the baseline schedule of September 2008 for all installed components (operating EBIS by December 2008). This goal depends on the delivery of certain primary components. Progress in WBS’s 1.2, 1.3, 1.7, and 1.8 is according to the scheduled plan. For WBS 1.9 the building infrastructure will be ready for an early EBIS installation.