G. Steinbrück 6/21/2005 1 Premounting of AOHs for the TEC in Hamburg Georg Steinbrück Hamburg University AOH Meeting, CMS Week 6/21/2005  Status of AOH.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Clean Room Plans Monday, August 23, Hybrids--- Frames--- SensorsModules.
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
EMB PAR, 23 nov P. Perrodo, LAPP, Annecy1 ATLAS EMB SERIE MODULE CABLING Experience started with three successive prototype modules (module 0) in.
Status Brussels GANTRY Ê We have observed a significant influence due to temperature 4 we had a lot of problems with our cooling system (ventilation) Ë.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
L2 L3 CMS tracker manager meeting June W. Beaumont Universiteit Antwerpen 6/10/01 l2l3UAjune2001b.sdd Module Long term test activities University.
1/8/04Lance Simms Thermal Testing of TOB/TEC Hybrids at UCSB.
Tracker Week – UCSB Gantry Status – April 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara Dean White.
Tracker Week – UCSB Gantry Status – July 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
1 Hybrid & Module Testing Status Week of 4/25-4/29.
US CMS Silicon Tracker : Schedule J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004.
Slide 1CMS Database Issues-Derek BargeDOE review, January 20, 2004 CMS Database Issues Derek Barge.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
4/25/2006 Puneeth Kalavase, UC, Santa Barbara On behalf of US Tracker Outer Barrel group Construction and Testing of CMS “Rods”
1 Hybrid & Module Testing Status Week of 6/6-6/10.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 13 October 2003 Sam Burke Lance Simms.
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
CMS Week – UCSB Gantry Status – June 8, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave Staszak.
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
Andrea Giammanco CMS Tracker Week April DS ROD Prototype: “final” optohybrids “final” CCUM integrated in the rod with new FEC_to_CCUM adapter (Guido.
March 17, 2003 Catania, Meeting ST - CMS CMS Sensor Quality Frank Hartmann – University of Karlsruhe 1 Summary of Sensor Quality Tests List of Problems.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 21 July 2003 Sam Burke UCSB HEP Group.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
CMS Tracker Week, CERN, Apr Apr 2004CMS Tracker Week - Module ProductionSalvatore Costa - Catania Module Production ___________ Report on.
1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
CMS TRACKER STATUS REPORT Dimitri PandoulasCMS Week
CMS Tracker Week, CERN, April Apr 2005CMS TrackerWeek - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
CMS Week, CERN, Mar Mar 2004CMS Week - Module ProductionSalvatore Costa - Catania Report on Module Bonding Salvatore Costa Università di.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Guido_Tonelli / CMS_TSC / 5 February Time stability of ST sensors The problem The sensors re-measuring campaign Failure analysis Conclusions.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
12/Dec/2012SBS-Meeting1 of 24 Status of the Front Tracker GEM and INFN Electronics 2012 – Dec – 12 SBS Weekly Meeting GEM Assembling SRS – INFN Electronics.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
Commissioning and Operation of the CMS Tracker analogue optical link system at TIF with CMSSW: R.Bainbridge, A.Dos Santos Assis Jesus, K.A.Gill, V. Radicci.
CMS Week, CERN, June June 2004CMS Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group Meeting Salvatore.
Brussels Module Production Ê We have producted 57 R6 modules and 26 R5N modules 4 of which 67 grade A and 9 grade B and 7 outside specifications Ë We have.
8. February 2012 Thomas Bergauer (HEPHY Vienna) SVD Construction Database SVD-PXD meeting.
Status of NA62 straw electronics Webs Covers Services Readout.
14-Dec-15S.Movchan Straw manufacturing and QC1 Straw manufacturing procedure and QC tape and straw parameters specification conditions of straw production:
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
CMS Tracker Week, CERN, Oct Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
1 KU MRI What is the MRI? What is KU doing? Firmware/testboards Optical hybrids Sensors.
Lyon Gantry Status CERN 15 Sept D. Contardo Calibration Plates and Tools Readiness for production.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
Module Assembly Jig Status Cambridge and DESY came to Liverpool Nov. 15 th -16 th for training on module assembly – A complete jig set was sent back with.
Juan Valls - LECC03 Amsterdam 1 Recent System Test Results from the CMS TOB Detector  Introduction  ROD System Test Setup  ROD Electrical and Optical.
J. Valls, CMS L2-L3 Meeting, Sept ROD Production at CERN  ROD Flow During Production  ROD Flow at CERN  ROD Testing Areas  Infrastructure  Equipment.
Optoelectronics internal report, 17 August 2007
Hamburg Bonding Report
Vienna Module Production
CMS Perugia Modules Production Review
Module production in Italy
SBS Front Tracker GEM short update on inefficient sectors
Module Production in Brussels
L.Fiore Gantry Meeting during the CMS TK week
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Presentation transcript:

G. Steinbrück 6/21/ Premounting of AOHs for the TEC in Hamburg Georg Steinbrück Hamburg University AOH Meeting, CMS Week 6/21/2005  Status of AOH Mounting in Hamburg  AOH related issues  AOH availibility for TEC

G. Steinbrück 6/21/ AOH Mounting in TEC. In the context of the Tracker Reorganization it was decided in Dec 2004 to reduce the number of Petal Integration Centers for the TEC. Petal integration was delayed by the availability of modules (hybrids and sensors missing.)  Time waiting for modules can be used constructively by premounting AOHs on petals. Mounting of AOHs and handling of the fibers is a delicate task and takes up a considerable fraction of mounting petals. Hamburg agreed to take care of AOH mounting for TEC with two assembly lines. Rate: Mounting AOHs on two petals/day.  ~9 Months, starting April 2005

G. Steinbrück 6/21/ Grey room with two setups AOH test kit. Fiber protection.

G. Steinbrück 6/21/ Procedure -Optical inspection of petal and AOHs -Mount CCUs, test -Mount fiber clips. -Mount AOHs in groups, connect fibers to patch panel, mount hybrids, perform tests: including baseline test, frame test with min. gain requirement. -Disconnect fibers from patch panel and store in transport box. -Store fibers in Fiber Channel and close fiber channel with carbon profile. -Upload db xml file to db and make all xml files available on local WEB site. Frame test Fiber storage for transport.

G. Steinbrück 6/21/ Petal with AOHs (and Silicon) Silicon Modules Optohybrids Fibers (in fiber channel)

G. Steinbrück 6/21/ Status - AOH mounting going very well. Have mounted AOHs on 81 petals so far. -Initialy had problems with optical gains: baseline amplitude and/or frame amplitude often too low.  All solved by cleaning all optical connections properly! (Discussions with Francois Vasey). -Few bad AOHs: 20/1000 lost in TEC so far -14 in Hamburg: -10 broken fibers -2 different fiber length -2 rejected by assembly program (1 bias scan failed, 1 wrong type in db) -Other centers -5 overvoltages -1 damaged by closing fiber channel Bad AOHs will be collected and sent back to CERN. Availability of AOHs for TEC: See linked spreadsheet.

G. Steinbrück 6/21/ Web page