PMO Update to PRS Troy Anderson ERCOT Program Management Office December 17, 2009.

Slides:



Advertisements
Similar presentations
Page 1 Program Management Office “PMO” Update Steve Wallace February 3, 2003.
Advertisements

Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
ERCOT PMO Update Robert Connell Director Program Management Fourth Quarter Results (Through 12/31/04) January 11, 2005.
The University of Texas at San Antonio The Office of Information Technology Network Upgrade Overview.
RO Project Priority List Update EDW Projects Update RMS Meeting Adam Martinez Mgr, Market Ops Divisional Projects Organization ERCOT April 12, 2006.
Finance & Audit Committee Meeting December 13, 2005.
RMS Update to TAC January 3, Goals Update ► Complete and improve SCR745, Retail Market Outage Evaluation & Resolution, implementation and reporting.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
RMS Update to TAC May 8, RMS Update to TAC ► At April 9 RMS Meeting:  Antitrust Training  RMS Voting Items: ► NPRR097Changes to Section 8 to Incorporate.
1 Project Update and Summary of Project Priority List (PPL) Activity to Date August 14, 2014.
IO – CART Project Status Protocol Revision Subcommittee Update 06/22/06.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee June 4, 2009.
PMO Update to PRS Troy Anderson Program Management Office April 20, 2007.
PMO Update to RMS Troy Anderson Program Management Office April 12, 2005.
ERCOT Program Management Update RMS Meeting – May 15, 2003 Steve Wallace.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
ERCOT SCR745 Update ERCOT Outage Evaluation Phase 1 and Phase 2 TDTWG April 2, 2008.
ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745) TDTWG May 7, 2008.
ERCOT PMO Update Robert Connell Director Program Management Board of Directors Update February 2005.
ERCOT PMO Update Robert Connell Director Program Management March Board of Directors March 8, 2005 (Through 2/28/05)
PMO Report to RMS Troy Anderson ERCOT Program Management Office November 7, 2007.
Page 1 TAC Program and Projects Update March 6, 2003.
Managing Project Funding Changes David Troxtell Program Management Office March 14, 2007.
MO Projects Update Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT COPS Meeting May 23, 2006.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
ERCOT PMO Update Robert Connell Director Program Management May Board of Directors May 17, 2005 (Through 4/30/05)
1 New RO Projects Hope Parrish June NEW RO Projects for 2008 Requested by ERCOT - Overview Objective Objective of the following information is to.
PMO Update to PRS Troy Anderson ERCOT Program Management Office January 21, 2010.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
1 TAC Report to the ERCOT Board February 16, 2005.
Retail Operations 2008 Fund Release Proposal Retail Market Subcommittee June 11 th, 2008 Hope Parrish Market Operations Division Projects Organization.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management May 19, 2011.
2009 Project Prioritization Troy Anderson ERCOT Program Management Office February 20, 2008.
PMO Update to PRS Troy Anderson Program Management Office February 22, 2007.
ERCOT Market Services Organization Dale Goodman Director, Market Services (office) (cell) (fax)
17 February 2009 ERCOT Board of Directors Texas Nodal Market Implementation: Program Update Trip Doggett Sr. Vice President and Chief Operating Officer.
1 Project Priority List (PPL) Update Troy Anderson ERCOT Enterprise Project Portfolio Management January 2011.
1 Market Operations Presentation Board of Director’s Meeting January 17, 2006.
2008 Project Prioritization Review Troy Anderson ERCOT Program Management Office.
EIS Overview and Project Updates for DEWG Jackie Ashbaugh ERCOT April 13, 2006.
Market Coordination Team Update Retail Market Subcommittee April 11, 2007 Susan Munson Retail Market Liaison.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee October 1, 2009.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
PMO Update to PRS Troy Anderson Program Management Office December 13, 2007.
EIS Projects Update COPS Meeting Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT April 28, 2006.
PMO Update to PRS Troy Anderson Program Management Office May 22, 2008.
1 Yearly Project Prioritization Process Overview and New RO Projects Troy Anderson et. al. June 2007.
QSE Managers Working Group Meeting Notes 9 June, 2009 Report to WMS 17 June, 2009 David Detelich - Chairperson.
CO – CART Project Status Protocol Revision Subcommittee Update 08/17/2006.
ERCOT Project Process Karen Farley COPS 3/22/05. Project Process  Overview of Project Requests  Process for Market Requests  Process for Internal ERCOT.
August 2009 RO Projects Financial Overview Retail Market Subcommittee August 12, 2009 Heather Day Market Operations Division Projects Organization.
August 17, 2006 Data Extract Working Group EDW Project Updates 2006 / 2007 MO & RO PPL.
2007 RO Projects Financial Overview Retail Market Subcommittee January 9, 2008 Hope Parrish Market Operations Division Projects Organization.
ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745) TDTWG November 5, 2008.
MODPO Project Update Overview of December Implementations & EDW Changes Commercial Operations Subcommittee December 11, 2006.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management October 20, 2011.
PMO Update to RMS Troy Anderson Program Management Office December 16, 2004.
PMO Update to PRS Troy Anderson ERCOT Program Management Office May 20, 2010.
PMO Update to PRS Troy Anderson ERCOT Program Management Office May 21, 2009.
July 2008 RO Projects Financial Overview Retail Market Subcommittee August 13, 2008 Hope Parrish Market Operations Division Projects Organization.
PMO Update to PRS Troy Anderson ERCOT Program Management Office July 22, 2010.
Troy Anderson Program Management Office August 10, 2005
2011 Prioritization Update to Market Subcommittees
Troy Anderson ERCOT Program Management Office November 6, 2008
ERCOT SCR745 Update ERCOT Outage Evaluation Phase 1 and Phase 2
Enterprise Program Management Office
2015 January February March April May June July August September
Presentation transcript:

PMO Update to PRS Troy Anderson ERCOT Program Management Office December 17, 2009

2 PMO Update - Agenda –2009 Project Spending Forecast As of 12/10/2009 –Recent Project Implementations November 2009

Project Spending Update – 12/10/2009 CARTInitial BudgetCurrent BudgetSpending Forecast CO $ 1,145,000$ 2,711,490$ 3,098,319 IO $ 4,995,000$ 2,791,000$ 2,490,068 MO $ 520,000$ 861,413$ 769,359 RO $ 3,390,000$ 4,253,507$ 4,149,903 SO $ 1,350,000$ 1,035,639$ 994,680 Released but Not Yet Reallocated $ 0$ 161,809$ 0 Subtotal $ 11,400,000$ 11,814,858$ 11,502,329 Met Center Replacement $ 20,000,000$ 19,498,062$ 15,948,921 Data Center Expansion $ 6,750,000$ 5,887,080 Grand Total $ 38,150,000$ 37,200,000$ 33,338,330 Adjustments in project forecasts Transfer between MO/RO and Met Center Transfer between SO and CO

4 PMO Update - YTD 2009 Project Implementations January 2009 –ROPR-70007_01 MarkeTrak Enhancements (SCR749) –COPR-80003_01Employee Performance Management –COPR-80038_01ACL Audit Exchange –COPR-80036_01ERCOT / TRE Accounting Structure (p. 83) February 2009 –COPR-60058_01 Microsoft Project Server Upgrade (p. 44) March 2009 –COPR-70046_01 SEM Enhancement –IOPR-80026_01 Enterprise Visibility (p. 69)

5 PMO Update - YTD 2009 Project Implementations April 2009 –None May 2009 –CO PR-80016_01 Security Configuration Management –RO PR-80040_01 TIBCO Siebel Integration Enhancements (p. 25) June 2009 –IO PR-80044_01 Tape Hardware Backup Replacement Replacement of aging tape backup system Enhanced speed and capacity; power and space reduction in data center –SO PR-90022_01 Zonal AWS Wind Gen Forecast for QSEs SCR754 / PRR763 Replace ERCOT delivery of AWS forecast to QSEs with a more secure and programmatic mechanism

6 PMO Update - YTD 2009 Project Implementations July 2009 –CO PR-70034_01 Vendor Contract Information Database Enhancements Phase 2 of an effort to allow better management and reporting of vendor contracts by ERCOT’s Legal Department –CO PR-80042_01 Cyber-Security Project Upgrade and enhance ERCOT cyber-security capability –CO PR-90023_01 Single Time Entry Eliminate dual entry of project time reporting into project management system and time reporting system August 2009 –COPR-80016_01 Cyber-Security Project Upgrade and enhance ERCOT cyber-security capability –ROPR-90024_01 POLR Rule and Expedited Switch Expedited Switch portion of project implemented on 8/16 Effective 10/24/09, the switch cancellation and notification window is shortened from 5 business days to 2 business days prior to Scheduled Meter Read Date

7 PMO Update - YTD 2009 Project Implementations September 2009 –SO PR-60084_01 Mid Term Load Forecast Provide accurate Mid Term Load Forecasting tool to the System Operators. Provide ERCOT the ability to compare more than one forecast and give the flexibility to select from more than one source. –SO PR-90001_01 Reliability Assessment Tool Develop a reliability assessment tool to evaluate the reliability risk level in a quantitative way using probabilistic methods and provide the operations floor with a usable tool to advise when additional resources are needed to maintain operational reliability. –SO PR-90020_01 OOME Reliability Tool Develop an OOME tool which will immediately send electronic OOME deployments to sets of units either up or down when the operator needs to quickly alter flow to specific areas. –COPR-80047_01 TCC1 Data Center Expansion Expand the current 3000 sq ft data center to the adjoining 2000 sq ft of raised floor. Data center is to be ready for occupancy no later than 10/01/09 to meet Nodal space requirements. –ROPR-80031_01 Retail Application Upgrade Upgrade critical applications to become current with software versions, vendor support and to gain the efficiencies from the features in the newer releases of the applications. –ROPR-50061_01 EDW EAI Transition Implement data replication from the PaperFree and NAESB source systems to the EIS ISM database environments.

8 PMO Update - YTD 2009 Project Implementations October 2009 –SOPR-90021_01 14 Minute Ramp Period PRR803 Supports the PRR proposed by the IMM and advocated by the PUCT to change the ramping period for Balancing Energy Service deployment for Base Power Schedule Calculation and Balancing Energy Power Schedule from ten (10) minutes to fourteen (14) minutes. This will allow more Balancing Energy Services to be deployed and is expected to improve Dispatch efficiency. –COPR-80007_01 Procurement Process Flows Automate current manual Procurement processes through Lawson.

9 PMO Update - YTD 2009 Project Implementations November 2009 –None December 2009 (projected) –ROPR-80027_01 Advanced Metering Market Changes for PUCT 3461 –SOPR-80027_01 Improvements to VSA/DSA –COPR-40029_01 Budgeting Tool –COPR-60075_01 Cyber-Security Project –COPR-70014_01 Physical Security Project –IOPR-90003_01 Spectel Server Replacement –IOPR-90004_01 Data Storage –IOPR-90009_01 Infrastructure Monitoring Enhancement (Remedy Phase 3) –IOPR-90010_01 Monitoring and Reporting Tools