Hartford Civic Arena Roof Collapse

Slides:



Advertisements
Similar presentations
Roof Framing A Quick Primer
Advertisements

Post and Lintel Ana Cristina Ayala.
2.2 STRUCTURAL ELEMENT BEAM
2.2 STRUCTURAL ELEMENT Reinforced Concrete Slabs
Reinforced Concrete Design-8
Lecture 33 - Design of Two-Way Floor Slab System
We are reviewing Chapt. 1&2 and we assigned Chapt. 3 & 4 for
Ma.Carlota Fermín Jorge Matheus
CEA UNIT 3 TERMS & DEFINITIONS. BEAM A structural member, usually horizontal, that carries a load that is applied transverse to its length.
ONE-WAY SLAB. ONE-WAY SLAB Introduction A slab is structural element whose thickness is small compared to its own length and width. Slabs are usually.
Chp.12 Cont. – Examples to design Footings
Skilled Trades 1201 Floor Framing
1 Design and drawing of RC Structures CV61 Dr. G.S.Suresh Civil Engineering Department The National Institute of Engineering Mysore Mob:
Approximate Analysis of Statically Indeterminate Structures
The University Sciences Building Northeast, USA Final Presentation Chris Dunlay Structural Option Dr. Boothby.
COLUMNS. COLUMNS Introduction According to ACI Code 2.1, a structural element with a ratio of height-to least lateral dimension exceeding three used.
Villanova University Dept. of Civil & Environmental Engineering CEE 8414 – Structural Dynamics Northridge Earthquake 1 Northridge Earthquake - Concrete.
Umm Al-Qura University Department of Civil & Structural Engineering 1 Design of reinforced concrete II Design of one-way solid slabs Lecture (1)
ID-2125 Marianela Najul KARLYS PULIDO PARICIA CAMACHO FRAMED STRUCTURE.
Static Pushover Analysis
Reinforced Concrete Design
Rockville Metro Plaza II Rockville Pike John Vais | Structural Option PSU AE Senior Thesis 2014 Faculty Advisor – Dr. Hanagan Rockville, Maryland
1 Presented by the Wood Truss Council of America.
© Dr S R Satish Kumar, IIT Madras1 SECTION 7 DESIGN OF COMPRESSION MEMBERS.
7. APPROXIMATE ANALYSIS OF INDETERMINATE STRUCTURES
1 Design and drawing of RC Structures CV61 Dr. G.S.Suresh Civil Engineering Department The National Institute of Engineering Mysore Mob:
Duquesne University Forbes Expansion
©Teaching Resource in Design of Steel Structures IIT Madras, SERC Madras, Anna Univ., INSDAG 1 COMPOSITE FLOORS - II.
Howard County General Hospital Patient Tower Addition Columbia, MD Kelly M. Dooley Penn State Architectural Engineering Structural Option.
MAE243 Section 1 Fall 2006 Class 2
Nicholas Reed Structural Option Seneca Allegany Casino Hotel Addition AE Senior Thesis 2013 Courtesy of Jim Boje, PE.
L’Ambiance Collapse Group 15 David Lawlor Emma Quinn Daniel O’Sullivan Cian O’Sullivan.
L'Ambiance Plaza Collapse Bridgeport, Connecticut April 23, 1987
H ARTFORD C IVIC C ENTRE A RENA R OOF C OLLAPSE..
Mechanics of Materials(ME-294) Mechanics is the branch of physics that is concerned with the analysis of the action of forces on matter or material systems.
Lecture 15 - Timber Wall Framing Example
Milford Haven Bridge Collapse Cathal Kennedy Terence Meade Sara Farivarz Padraig O’Rourke.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
Vietnam Institute for Building Science and Technology (IBST)
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
Claudia Pérez Laura Rendeiro
BFC (Mechanics of Materials) Chapter 7: Statically Determinate Plane Trusses Shahrul Niza Mokhatar
Results Verification Has the model been correctly implemented?
Competency: Draw wall sections and details
Hartford Arena Roof Collapse.  January 18th  Snowstorm.  Roof plummeted 83 feet to the arena floor.  What caused the 300-x 360ft. roof to collapse?
ENGINEERING MECHANICS (15BS105)
Royal Plaza Hotel, Thailand
Supporting pin at boom of a Con ’ c pump car broken to hit the victim (Serious Accidents in Construction) Construction The copyright to this material.
Group 16 Ian Bray Aodhin Mc Bride John McElwee. Background Collapsed January 18 th 1978 – 5 years after construction Large snowstorm caused heavy loading.
Post and Lintel University Simón Bolívar English 2 Francis Martínez
786 Design of Two Way floor system for Flat Plate Slab
Design of Beams for Flexure
Competency: Draw wall sections and details
Week 2 Experimentation TS Term 2.
SECTION 7 DESIGN OF COMPRESSION MEMBERS
Engineering Mechanics (17ME1001)
Wood Structures Topic 8 Quality Workmanship
786 Design of Two Way Floor System for Slab with Beams
San Francisco Earthquake Fire Disaster
MODULE 8 – The Ontario Building Code
Arch205 building construction Windows- glazed curtain wall, skylights
Competency: Draw wall sections and details
Building section A vertical cut or slice through a structure that illustrates the type of foundation, wall, and roof construction to be used.
Building Construction
Progressive Collapse Resistant Design of Structures
سیستم های ساختمانی پیشرفته (2)
Floor Plan A horizontal section view of a structure taken about 4’ from floor level, It shows all exterior and interior walls, doors, windows, patios,
2.2 STRUCTURAL ELEMENT Reinforced Concrete Slabs
Floor Truss Ribbon Board Load Path
Wall and Ceiling Construction
Presentation transcript:

Hartford Civic Arena Roof Collapse Group 16

Overview: Introduction. Structural design. Causes of collapse. Conclusions. Sources.

Introduction. Collapse occurred 18th of January 1978 Large snowstorm. The roof collapsed while Arena was not in use. No fatalities or injuries.

Structural design: Fraoli, Blum & Yesselman, Engineers were employed to design arena. The engineers used an innovative design. It was based on space frame design. Spanning 91.44m x 109.72m. 25.29m above floor level. The predicted deflection = 330.2mm at midpoint and 150mm at edges.

Structural design: Differed from standard space frame design: Cross-shaped built up sections used. Top horizontal bars intersected at different points to diagonal bars rather than at the same point. Short posts on the nodes supported the roofing panels. Four columns were 13.71m inside roof edges. The space frame was not pre-chambered.

Structural design: Diagrams;

Causes of collapse: Three contributary factors Structural design. Construction. Project Management.

Structural design: Cross-shaped members. Intersection of top horizontal and diagonal bars, not connected at the same point. Inaccurate computer analysis, torsional buckling not considered. Top layer’s interior and exterior compression members overloaded. Very little redundancy. No independent recheck of structural design.

Project management; No overall project manager responsible for the entire project. No qualified structural engineer employed to perform inspections of structure during construction. Overall, no hierarchy of responsibility

Construction: Connections were not fabricated or assembled to design specifications. Excessive deflections noted on ground assembly. After frame was complete, deflection was measured to be twice that predicted by computer analysis (660.4mm). No responsibility taken by contractor towards the performance of the project.

Conclusions: Employ Project Manager to take responsibility for entire project. Employ Qualified Structural Engineer to investigate and report structural deficiencies. Recheck design calculations and analysis, when unexpected deformations occur. Investigate any possible structural deficiencies. Include as large amount of redundancy as is feasible. Independently check design calculations.

Sources: Hartford Civic Arena Roof Collapse. Rachel Martin. Probability-Based Load Criteria for Structural Design. Bruce R. Ellingwood. Failure Case Studies in Civil Engineering Education.