GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
Advertisements

GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
IFCT Plan for Next 3 Months Larry Wai June 26, 2003.
© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO.
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
GLAST LAT Instrument GLAST Monthly Mission Review October 29, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 29, 2007 Ken.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review I&T Plan.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
GLAST LAT Instrument GLAST Monthly Mission Review October 5, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 5, 2007 Ken Fouts.
GLAST LAT ProjectACD CDR, January 7 & 8, 2003 Section 10 Integration and Test 1 GLAST Large Area Telescope: ACD Integration & Test Jim La/ACD I&T Lead.
GLAST LAT Instrument LAT Monthly Status Review Aug 1, 2007 W N Johnson, NRL 1 GLAST Observatory TVAC at NRL Aug 1, 2007 Neil Johnson NRL
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
1 GLAST LAT Arrival at Spectrum Assuming That the LAT Transport Container Arrives on Flatbed Truck Question: Can Transport Cover Support Crane Lift With.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
GLAST LAT Project ACD CDR Jan 7-8, Section 7 Mechanical Ground Support Equipment GLAST Large Area Telescope: AntiCoincidence Detector (ACD) Mechanical.
From Research Prototype to Production
GLAST Large Area Telescope:
GLAST LAT I&T GLAST Monthly Mission Review Nov 3, 2005 wnjohnson 1 Monthly Mission Review LAT Environmental Test Planning November 3, 2005 W Neil Johnson.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
LATLAT CU Beam Test 3rd May GLAST Program CU Beam Test CU Integration Francesco Nicola
GLAST LAT ProjectEGSE Peer Design Review, August 17, S. WilliamsEGSE Overview Electrical Ground Support Equipment Overview Scott Williams Stanford.
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: Pre-Environmental Test.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 16 March 2005 LAT High Bay Operations Supporting Non-Test Events LAT Engineering.
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: LAT Pre-Ship Review Performance.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Overview LAT Environmental Test.
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Operations and Logistics LAT Environmental.
GLAST LAT Project Integration and Test IFCT Peer Review 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: LAT Pre-Shipment Review.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST LAT Project13 June 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review Project Overview 1 Presentation 1 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review W.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST Large Area Telescope:
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
Gayle K. Martin November 14, 2016
Mechanical Integration
Environmental Test Planning
Integration and Test GLAST Large Area Telescope:
Baseline Environmental Test Flow at NRL
GLAST LAT System Engineering
Peer Review Agenda (Suggested).
GLAST Large Area Telescope:
GLAST LAT System Engineering
LAT Pre-Environmental Test Plan
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
Integration and Test Organization Chart
Mechanical/Thermal Systems
Environmental Test Planning Meeting
GLAST Large Area Telescope
Integration and Test Organization Chart
Introduction and Overview
Presentation transcript:

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review Integration and Test Ken Fouts SLAC Gamma-ray Large Area Space Telescope

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 2 Integration and Test Presentation 11 of 12 Overview Review Current LAT Status –LAT I&T Organization –LAT Instrument Configuration –Procedure/Build Documentation Summary Review Transportation Planning –Shipping Plan –LAT Handling and Shipping Container Procedure Status of Observatory I&T Planning –Readiness for Post Ship Tasks at GD-SASS LAT/Observatory Schedule Review

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 3 Integration and Test Presentation 11 of 12 LAT I&T Team LAT I&T Team has a proven track record for safe program execution

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 4 Integration and Test Presentation 11 of 12 LAT Configuration Shipping Configuration –LAT-DS-1624 LAT Top Assembly except: No Radiators –Radiator MLI removed for shipping

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 5 Integration and Test Presentation 11 of 12DocumentStatus LAT-MD LAT Instrument Performance Verification PlanReleased LAT-MD LAT Performance and Operations Test PlanReleased LAT-MD LAT Assembly SequenceReleased LAT-MD LAT Instrument Survey PlanReleased LAT-MD LAT Systems LAT Top AssemblyReleased LAT-DS LAT Systems Instrument AssemblyReleased LAT-DS LAT Tower and Electronics AssemblyReleased LAT-DS LAT Tower AssemblyReleased LAT-DS CAL-TEM-TPS Module AssemblyReleased LAT-DS TRACKER-LAT IDDReleased LAT-DS CAL-LAT IDDReleased Key I&T Requirement Documents Requirements Verified during Integration and Test

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 6 Integration and Test Presentation 11 of 12DocumentStatus GSFC procedure 433-PLAN-0018, LAT Instrument Transportation Plan.Released LAT-PS LAT Test Procedure with LICOSReleased LAT-PS LAT Observatory Final AssemblyReleased LAT-PS Radiator Installation ProcedureReleased LAT-PS LAT Integration Safe to Mate TestsReleased LAT-PS Fastener Installation and Torqueing ProcedureReleased LAT-PS Connector Mate and DemateReleased LAT-PS LAT Auxiliary Cooling Set-up and OperationReleased LAT-PS Flight Hardware Bag and Purge ProcedureReleased LAT-PS AeroGo Bearing Reference GuideReleased LAT-PS LAT Data Collection ProcedureReleased LAT-MD LAT EGSE PlanReleased Key LAT Procedures I&T Standard Processes will continue to be used at GD-SASS

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 7 Integration and Test Presentation 11 of 12DocumentStatus LAT-PS LAT Environmental Test Implementation PlanReleased/Complete LAT-PS LAT Shipping Container ProcedureReleased/Complete LAT-PS LAT Environmental Test Handling ProcedureReleased/Complete LAT-MD LAT Environmental Test SequenceReleased/Complete LAT-MD LAT Dynamics Test PlanReleased/Complete LAT-MD LAT Thermal Vacuum Test PlanReleased/Complete LAT-MD LAT EMI/EMC Test PlanReleased/Complete LAT Test Document Status Assembly Instruction Data generated by I&T for requirement closure

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 8 Integration and Test Presentation 11 of 12 LAT Acceptance Data LAT Acceptance and build data contained in these documents

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 9 Integration and Test Presentation 11 of 12 I&T Build Document Summary In addition to the completed I&T Test Procedures, LAT Build Data is contained in: –eLogbook Individual Run Data Hardware Installation Connector Mate/Demate Material Mix Records –185 Electrical Assembly Inspection Data Sheets (AIDS) –60 Mechanical AIDS

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 10 Integration and Test Presentation 11 of 12 Transportation Plan Highlights LAT Transportation GSFC procedure 433-PLAN-0018, LAT Instrument Transportation Plan. –Environmentally controlled air ride van. –Purge cart and instrumentation maintained by GSFC –Procedures used previously for LAT shipment from SLAC LAT shipment contains all of the equipment required for set-up at GD-SASS EGSE Transportation Racks packed in custom crates used for shipment to NRL. Dedicated air ride van. Departed NRL on Tuesday (9/12) for Friday (9/15) arrival at GD. MGSE Transportation NRL tractor/driver Planned departure Saturday (9/16) for Monday (9/18) arrival at GD No critical use equipment.

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 11 Integration and Test Presentation 11 of 12 Shipping Manifest (1 of 2)

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 12 Integration and Test Presentation 11 of 12 Shipping Manifest (2 of 2)

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 13 Integration and Test Presentation 11 of 12 LAT Transport Container Process Clean Container Install GPR on LAT Lift LAT Off Of Test Stand Lift LAT Off Of Test Stand Install LAT On Container Base Install LAT On Container Base Install Lower Cover To Base Install Lower Cover To Base Desiccant Into Container Desiccant Into Container Install Purge Line Install Purge Line Install Environmental Monitoring Equipment Install Environmental Monitoring Equipment Install Remaining Cover Segments Install Remaining Cover Segments Install Container On Truck Install Container On Truck Install Ground Cables To LAT & Container Install Ground Cables To LAT & Container Transport To GD-SASS Transport To GD-SASS Remove Container From Truck Remove Container From Truck Remove Environmental Monitoring Equipment Remove Environmental Monitoring Equipment Remove Upper Container Cover Remove Upper Container Cover Remove Purge Line Remove Purge Line Remove Lower Cover Remove Lower Cover Ready For Post Ship Test Set-up Ready For Post Ship Test Set-up Remove GPR From LAT Remove GPR From LAT LAT-PS LAT Transport & Container User Procedure

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 14 Integration and Test Presentation 11 of 12 Shipping Container Operations LAT on container baseLower cover installed Final cover installedLoading LAT on the Truck

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 15 Integration and Test Presentation 11 of 12 Early Activities Flow at GD-SASS LAT Delivery –GSFC providing transportation to SASS and forklift to unload LAT –SASS support in place for all LAT activities –All GSE required for this phase is shipped with the LAT LAT Post-ship Inspection –Quality Assurance team will perform visual inspection, review transportation data. LAT Post-ship Electrical Test –Facility and network requirements for LAT EGSE is documented in ICN-99 and are in place –Performing same tests with same EGSE as at NRL LAT Hand-Off to GSFC –Process in place LAT Mechanical Installation –Pathfinding activities performed and lessons learned have been implemented in procedures

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 16 Integration and Test Presentation 11 of 12 LAT Procedure Delivery Status

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 17 Integration and Test Presentation 11 of 12 SLAC/GD-SASS Preparation Network Connectivity SLAC network hardware delivered and installed at GD-SASS –Basic network connectivity established between SLAC and FoF August 15. –Connectivity for post-ship tests will be verified when EGSE arrives (VSC, Mobile Computing Rack, BPU). –Network connectivity for Observatory Test configuration is in-work –Required for Observatory CPT mid October. –Demonstrate LAT data transfer via GD-SASS LAN. LAT to Spacecraft Integration Pathfinding at GD-SASS Completed August 23, 2006 Objectives –Dry run the LAT to Spacecraft integration procedure using spare grid with mass simulators. –Install all integration hardware to verify pinned bolted interface. Summary –LAT GPR and 4x4 Lift Fixture used to lift LAT Simulator –All interface hardware was successfully installed. –Integration procedure redlined during operation. –Documented Lessons Learned LICOS-AstroRT Test Environment Verification Command protocol demonstration at SASS completed 8/10 LAT LICOS test script validation on-going at SLAC

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 18 Integration and Test Presentation 11 of 12 LAT Pre-Integration Configuration

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 19 Integration and Test Presentation 11 of 12 Observatory Test Configuration

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 20 Integration and Test Presentation 11 of 12 LAT Flow at GD-SASS T- Bal Pre TV T- Cycle 3 days2 days Weight & CG Remove Radiator s Remove Radiator s Pack and Ship 39 days 9/16/06 PSR 9/15/06 9/7/069/12/067/5/06A CPT Unpack LAT CPT LAT Integration CPT Observatory EMI/EMC CPT Acoustic Test Sine Vibe Sep Shock CPT Ship to Launch Site T- Bal Pre TV T- Cycle CPT LAT FSW Install/Test CPT 3 days5 days 2 days3 days 8 days3 days 9/18/069/23/06 9/28/06 Install Radiator s Install Radiator s 10/1/06

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 21 Integration and Test Presentation 11 of 12 LAT Plan

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 22 Integration and Test Presentation 11 of 12 LAT Staffing Plan Current staffing plan for GD-SASS: –Single long shift 5 days per week –24 hour staffing for CPT duration. –Weekends as required/available

GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 23 Integration and Test Presentation 11 of 12 Summary The LAT instrument as-built configuration is in accordance with current engineering and instrument level requirements. Documentation, preparation and pathfinding for transporting and handling the LAT have been completed. All EGSE and MGSE have been identified and its use has been demonstrated. The LAT instrument is ready for shipment. The team has the necessary preparations in place for successful integration of LAT with the observatory.