Afghan Water Task Progress Report September 7, 2006 EROS Data Center, Sioux Falls, SD Gregg J. Wiche Doug G. Emerson U. S. Geological Survey Bismarck, ND
B1: Streamflow Characteristics for the Helmand River Basin Digitize all daily streamflow for the period of record Develop a standard set of streamflow characteristics for each gage with 10 or more years of record Goals
B1: Streamflow Characteristics for the Helmand River Basin Digitized all daily streamflow for 43 stations with 591 station years of record Digitized daily storage for 2 reservoirs with 47 station years of record Developed a standard set of streamflow characteristics for each gage with 10 or more years of record—90 percent complete Accomplishments
B1: Streamflow Characteristics for the Helmand River Basin Digitized daily streamflow for all stations: Web based delivery via USGS NWIS CD version by October 31, 2006 Standard streamflow characteristics for each gage with 10 or more years of record Web based delivery by October 31, 2006 Deliverables
B2: Recovery of Historical Surface Water Information for the Helmand River Basin Recover all station description documents Develop pdf file of stage-discharge ratings for each gage Goals
B2: Recovery of Historical Surface Water Information for the Helmand River Basin Scanned station description documents for 10 stations in the Helmand River Basin Scanned stage-discharge rating for 10 gages Developed a form (discharge measurement information) for 10 stations Accomplishments
B2: Recovery of Historical Surface-Water Information for the Helmand River Basin Provide electronic documents to Afghan hydrologists involved in reestablishment of gaging stations Deliverables
B3: Recovery of Historical Surface Water Information for other Basins in Afghanistan Digitize all daily streamflow for about 100 gaging stations in Afghanistan, outside the Helmand Basin Provide public access to the data Goals
B3: Recovery of Historical Surface Water Information for other Basins in Afghanistan Kabul (Indus) River Basin Digitized daily streamflow for 42 stations with 548 years of record Northern River Basin Digitized daily streamflow for 6 stations with 66 years of record Accomplishments
B3: Recovery of Historical Surface Water Information for other Basins in Afghanistan Planned for 2007 Deliverables
B4: Water-Balance and Rainfall-Runoff Modeling for the Helmand River Basin Develop statistical water-balance model for estimating monthly streamflows Calibrate and verify a precipitation-runoff model of the Upper Helmand River Basin Provide software and documentation for running the rainfall-runoff model Goals
B4: Water-Balance and Rainfall-Runoff Modeling for the Helmand River Basin Stochastic water balance models have been calibrated and verified for four gaging stations in the Helmand Basin Time series models for generating potential future traces of water-balance inputs (precipitation and potential ET) have been developed Basin boundaries, stream network, and HRU’s delineated Loading FAO soils information into the GIS weasel Accomplishments
B4: Water-balance results for Helmand River
DEM of Helmand River Basin above Kajakai Reservoir (not including Tirin River) Tirin River Kajakai Reservoir Gardandewal Ghizab Helmand River above Kajakai Reservoir
Hydrologic Response Units (HRUs) for Helmand River Basin above Kajakai (not including Tirin River) Tirin River Helmand River above Kajakai Reservoir
B4: Water-Balance and Rainfall-Runoff Modeling for the Helmand River Basin Deliverables Written report summarizing water-balance model methods and results (Sept 30, 2006)
B1: Streamflow Characteristics for the Helmand River Basin Publish Open-file report by January 1, 2007 Produce pdf version of report on web Produce DC version of data Goals Cost $42,011
B2: Recovery of Historical Surface Water Information for the Helmand River Basin No additional data has been located. Thus, task has been suspended Goals No Costs anticipated
B3: Recovery of Historical Surface Water Information for other Basins in Afghanistan Digitize all daily streamflow for about 100 gaging stations in Afghanistan, outside the Helmand Basin Provide public access to the data Cost $65,696
B4: Water-Balance and Rainfall-Runoff Modeling for the Helmand River Basin Use statistical water-balance model to evaluate drought/flood probabilities Calibrate and verify a precipitation-runoff model of the Upper Helmand River Basin Provide software and documentation for running the rainfall-runoff model Prepare and publish USGS SIR report Goals
B4: Water-Balance and Rainfall-Runoff Modeling for the Helmand River Basin-- continue $227,455 Cost
The End
Characterization of the 1991 Flood in the Helmand River Basin Accomplishments Completed time series of Sistan Marshes water-surface area and volume estimates Used a snow-water equivalent model to compute water volume estimates for the Helmand River upstream of Kajakai Reservoir Provided daily water volume estimates for via Afghanistan website Estimated daily streamflow for the Helmand River below Kajakai Reservoir
Characterization of the 1991 Flood in the Helmand Basin Goals Complete indirect measurements of discharge at five locations Develop a flood hydrograph at each indirect measurement location Use remote sensing data to compute 1991 flood volumes as a check of the flood hydrograph
Water volume of Sistan Marshes Billions of Cubic Meters
Annual Flow for the Helmand River at Chahar Burjak
A Recovery of Historic Surface-Water Quality Data of the Helmand River Basin Entered 470 station years of daily streamflow for 35 streamgaging stations into NWIS Entered a total of 50 years of mean daily gage heights for 2 reservoirs Entered a total of 50 years of daily contents for 2 reservoirs Conducted quality assurance checks of the data Using NWISWeb to deliver the data via the Afghanistan website Accomplishments
NWISWeb Afghanistan Station List
Streamflow Loss between Kajakai Reservoir and Darweshan
Helmand River below Kajakai Reservoir
A Time Series of the Helmand River Goals Compiled all available historical rainfall records and developed techniques to produce orographically-enhanced rainfall estimates Assembled time-series grids of meteorologic data (rainfall, temperature, humidity, radiation, and wind) Develop time-series model
A Time Series of the Helmand River Accomplishments Compiled all available historical rainfall records and developed techniques to produce orographically-enhanced rainfall estimates Assembled time-series grids of meteorologic data (rainfall, temperature, humidity, radiation, and wind) Used grids to estimate snow water equivalent grids for 1957, 1958, 1959, and Started development of time series model
Installation and Demonstration of a Surface Water Gage Establish a demonstration gage to be used for initial training and mentoring Goals
Installation and Demonstration of a Surface Water Gage USGS team visited proposed gage site on the Panjshir River near Gulbahar Cross-section diagram of river obtained Measurements of bridge and cableway obtained Task is on hold until final location selected Accomplishments
Helmand River below Kajakai Reservoir