02/13/2009 RPG Wind Interconnection Survey Dan Woodfin Director, System Planning.

Slides:



Advertisements
Similar presentations
Welcome to the Travel Help Desk Ticket System. To access the Travel Help Desk Ticket System use this url To access the Travel.
Advertisements

RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
Jan 22, 2013 RPG Meeting Sharyland Atlas-Driver Load Integration Project – EIR update.
Regional Planning Group Charter Revisions May 2008.
Regional Planning Group Project
ERCOT Update on UFLS Annual Survey with TSP/DSP September 2014.
ERCOT Under Frequency Load Shed Testing
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
Ted Hailu Director, Client Services Market Notices.
Generation Interconnection Overview
SPA Updates Research Administrators Council November 20, 2013 Beth Callaway - Assistant Director, University Receivables David Thomas – Manager, Post Award.
1 Boundary and Annexation Survey (BAS) Laura Waggoner Legal Areas Team Lead Boundary and Annexation Survey Project Manager Michael Clements Geographer.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
Wind Power and the CREZ Case: What’s Decided, What’s Not, What’s Next Patrick R. Cowlishaw Jackson Walker LLP SBOT Public Utility Law Section August 15,
Synchrophasor Measurement Implementation in ERCOT
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
RTWG Report to TAC August 5, 2010 Howard Daniels.
1 Renewable Technology Working Group (RTWG) July 14, 2009 Henry Durrwachter.
November 10, 2009 NOIE DRG Settlements TF update to COPS Settlement Discussion for ALL DG < or = 1 MW Don Tucker on behalf of the NOIE DRG Settlements.
FACILITY SURVEY In MHPD. 2 Overview Getting started with the survey Facility-wide review Program review Completion of the survey and post-survey edits.
0 Photovoltaic Developers Perspective Photovoltaic and Storage Workshop ERCOT Aruna Ranaweera, Ph.D., P.E. OCI Solar Power October 15, 2012.
MP Online Data Entry Project Update WMS / ROS August 2013 Troy Anderson.
Renewables and Transmission Task Force Report to WMS March 20, 2007.
RPG Meeting Five Year Plan Extension Brad Schwarz.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
Single Electricity Market Update Liam Ryan SEMO. Background 2 years in operation Gross Mandatory Pool All Suppliers All Generations units over 10 MW Trading.
Wind ELCC Calculation Comparisons and ERCOT’s NERC LTRA Capacity Forecasts GATF Meeting, June 24, 2014.
March 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
1 OFFICE OF RESIDENTIAL CHILD CARE DHS Board Sub-Committee Keith D. Bostick, L.C.S.W., Director July 21, 2010.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Transmission Options for Mariah Project, Phase II 3/10/2010.
Wholesale Market Subcommittee Texas Interconnection Long-Term Study Update Warren P. Lasher April 8, 2011.
April 2, 2008 CRR Team Update PCRRs CRR Team UpdateApril 2, 2008 Table of contents 1.What is a PCRR? 2.Which NOIEs are eligible for PCRRs? 3.What.
CRR Issues Transparency provided by CRR Reports CRR EDS handbook Business process NPRR TPTF November 27, 2007.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
ERCOT Independent Review
NDSWG Report June 16, NDSWG Report Regular meeting held May 16 in Taylor Telemetry / State Estimator Update Naming Convention Electrical Bus Designation.
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
1 RTWG Report to TAC June 4, 2009 Henry Durrwachter.
May 15, 2009 Regional Planning Group CREZ Implementation Study Update Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Panhandle Renewable Energy Zone (PREZ) Study
1 With the increase in solar and wind generation we would like to stream line the process Currently TDSPS are required to send ERCOT ESI ID Generation.
Lead from the front Texas Nodal 1 Current Telemetry Dashboards NDSWG March 24, 2009.
2006 Report on the Capacity, Demand, & Resources for the ERCOT Region Technical Advisory Committee June 1, 2006 Kenneth A. Donohoo. P.E. Manager, Transmission.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting
Congestion Revenue Rights 1 TCR to CRR Transition Plan NOIE Workshop Nodal CRR registration process for NOIEs (REVISED) Beth Garza.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
2006 CDR Status Report Technical Advisory Committee May 4, 2006 Bill Bojorquez.
Real Time Balancing (RTB) & Resource Plan Statuses Change to the QSE practice of showing offline units as online and available ERCOT Presentation to ROS.
October 12, 2012 RPG Planning Guide 5.3.2(2) Developer obligation to keep RARF data updated Cathey Carter Resource Integration.
Profiling Working Group 1 PWG Update Report By Brad Boles of Cirro Energy ERCOT PWG Vice-Chair for COPS Meeting March 11, 2008.
Transition Plan Network Operations Model Change Requests 5/26/2010.
1 Customer Objections in Complete Status (CCO Clean-up Phase 3) Background Next Steps.
BSNL-Hungama SSA Portal – User Guide URL -
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
NPRRs 705NPRR Provides Consistency for References to the End Date of the Generation Interconnection Process. In the Resource Interconnection Handbook,
RCAP County Participation 83 Counties in some manner participated in the project 74 Counties eventually provided information for the project 57 Counties.
December 8, 2006 PUCT DR Workshop Status of LaaR Participation in RPRS.
MARS Taskforce RMS Update August 17, Initial Settlement As of August 7, 2011 Operating Date: July 31, 2011 AMC ESI ID Totals: 3,325,128 AMDG ESI.
Texas Congestion Management Work Group Update For WMS Marguerite Wagner, PSEG Texas.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
RPG - 10/12/2007 Competitive Renewable Energy Zones (CREZ) Update Bill Bojorquez Vice President, System Planning.
Warren Lasher Manager, Long-Term Planning and Policy
Project Update and Summary of Project Priority List (PPL) Activity
Study Scope - Quarterly Stability Assessment
Presentation transcript:

02/13/2009 RPG Wind Interconnection Survey Dan Woodfin Director, System Planning

2 RPG02/13/2009 Survey History ERCOT sent survey to participants in PUCT Docket and the contacts for all generation interconnection requests that were in process as of August 2008 Survey Questions, for reference: I. For each wind generation plant about which you submitted financial commitment testimony in PUCT Docket 33672, please provide responses to the following questions: A. Is the status of the plant Operational (as of 8/1/2008) or Planned? B. If Operational, please provide the name of the resource and “Unit Code” listed on the ERCOT Generation Asset Registration Form. C. If Planned, have you submitted an ERCOT generation interconnection request? 1. If yes, provide the GINR number of any associated ERCOT interconnection request and the latest estimated capacity in MW of the plant. 2. If no, provide the expected installed capacity in MW, location, and planned operational date of the plant. D. Do you believe that the plant (operational or planned) is or will be located within one of the CREZs designated by the PUCT? 1. If yes, then provide the name of the CREZ in which the wind generation is or will be located. E. If you have any update to the status, likelihood or characteristics of the plant since your financial commitment testimony was prepared, please provide this information. II. For each current wind generation interconnection request in the ERCOT “queue” with an assigned GINR number, please reaffirm or update the expected MW and in-service date. 1. If you desire the in-service date to be dependent on the CREZ lines in the area being completed, rather than a particular date, please indicate this for each request. 2. Please explain if the GINR includes more than one “phase” with different planned in-service dates

3 RPG02/13/2009 Operational = 8,111IAs = 1,442 CREZ Nominated = 28,245 Pre-IA INRs =51,808 Operational, CREZ Nominated = 2,318 IA, CREZ Nominated = 581 INR In Process, CREZ Nominated =22,743 No INR, CREZ Nominated = 2,603 INR in Process, Not CREZ Nominated = 29,065 Operational and IAs Not CREZ Nominated = 6,654MW Compiled Results

4 RPG02/13/2009 Results, by expected in-service year

5 RPG02/13/2009 Current Non-Confidential Wind GINRs – MW by County Notes Circles are not centered on county Projects in multiple counties are shown in 1 st county listed in GINR

Questions?