Abstract Storage Ring Vacuum and Interface to Magnets Hsiao-chaun Hseuh, NSLS-II Project This presentation provided a quick overview of the storage ring.

Slides:



Advertisements
Similar presentations
Upgrade Plan of KEKB Vacuum system Pre-kickoff KEK1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring - Conventional Facilities Interfaces Erik Johnson, Accelerator Systems Interface Manager Accelerator Systems.
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
SSRF Light Source Complex Zhao Zhentang for the SSRF Project Team Shanghai Symposium on Intermediate Energy Light Sources Shanghai China, September 24-26,2001.
Damping ring K. Ohmi LC Layout Single tunnel Circumference 6.7 km Energy 5 GeV 2 km 35 km.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Electrical Issues John Escallier, NSLS-II Project To achieve high quality electrical characteristics for storage.
T. Montagne LTU – Beam Dump Installation April 16, LTU and Beam Dump Installation April 16, 2007.
Engineering Integration of the Double- Double Bend Achromat (DDBA) into the Diamond storage ring Jim Kay Diamond Light Source Low emittance ring 2013 workshop.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnetic Specifications and Tolerances Weiming Guo, NSLS-II Project In this presentation I briefly introduced the.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet Design Workshop: Magnet Design and Analysis Charles Spataro, NSLS-II Project NSLS-II is a new 3Gev synchrotron.
Vacuum system in the main Linacs C. Garion CERN/TE/VSC CLIC09 workshop, October.
BROOKHAVEN SCIENCE ASSOCIATES SR Chambers & RF Bellows ASAC Review, 3/26-27/ of 21 SR Chambers & RF Bellows H. Hseuh, Vacuum Group ASAC Review of.
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
1 Tetsuhiko Yorita JASRI/SPring-8 Acc. Div. SPring-8 Vacuum System Contents - Outline of Vacuum system - Pressure behavior - Some topics.
1 BROOKHAVEN SCIENCE ASSOCIATES Production of Vacuum Components H.C. Hseuh NSLS-II ASAC Review October 14-15, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Critical Points Layouts For Storage Ring and Beamlines Ken Chow March 14, 2014.
DR Vacuum Component Overview April 25, 2012 Joe Conway.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
SR Vacuum Systems and Front Ends
June 14th 2005 Accelerator Division Overview of ALBA D. Einfeld Vacuum Workshop Barcelona, 12 th -13 th September 2005 General 10 th September 2005.
June 14th 2005 Accelerator Division Overview of ALBA D. Einfeld Vacuum Workshop Barcelona, 12 th -13 th September 2005 General 10 th September 2005.
NSLS-II ASAC Review, 10/9-11/06 H-C. Hseuh,…, SR Vacuum Systems Storage Ring Vacuum Systems H-C. Hseuh, C. Foerster, J. Hu, G. Mahler, S. Pjerov, S. Sharma,
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS II: the Accelerator System Briefing Conventional Facilities Advisory Committee May 8 - 9, 2007 Satoshi Ozaki Director,
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review – May 11, 2007 S. Sharma NSLS-II Frontends and Canted Wigglers Options Sushil Sharma.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
Technical Challenges and Concerns S. Sharma and R. Alforque, R. Beuman, C. Foerster, E. Haas, E. Hu, P. Montanez, P. Mortazavi, S. Pjerov, J. Skaritka,
Orbit Control For Diamond Light Source Ian Martin Joint Accelerator Workshop Rutherford Appleton Laboratory28 th -29 th April 2004.
BROOKHAVEN SCIENCE ASSOCIATES 0 Top-Off Safety Yongjun Li ASAC Meeting October 22, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
SuperKEKB Vacuum System - for the positron ring - Y. Suetsugu KEKB Vacuum Group Outline Design and production status of key components Beam pipes for arc.
F. Mazzolini Vacuum Systems for Synchrotron Light Sources Barcelona, September 12– Front-end vacuum system F.Mazzolini.
Matthew Cox VSSLS Workshop Barcelona Sept SLIDE 1 1 Diamond Light Source Vacuum Systems Matthew Cox
Cornell ERL Vacuum System as a Model for ILC Damping Vacuum System Conceptual Design Yulin Li & Joe Conway C ornell L aboratory for A ccelerator-based.
ALBA Vacuum System, E. Al-Dmour Vacuum Systems for Synchrotron Light Sources 12 th -13 th Sep ALBA Vacuum System ALBA VACUUM SYSTEM E. Al-Dmour On.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
1 Tim Michalski October 6, 2015 Engineering Issues in MEIC.
41 st IUVSTA Workshop, Brdo pri Kranju, 21/06 – 24/06/2004 L. Schulz SLS Vacuum System Lothar Schulz Theo Bieri Nazareno Gaiffi Martin Steinacher.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
NSLS Vacuum Experience Eugene J. Hu National Synchrotron Light Source Brookhaven National Laboratory Upton, NY USA September 12-13, 2005 (prepared.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS II: the Accelerator System Briefing Experimental Facilities Advisory Committee May 10, 2007 Satoshi Ozaki Director,
Accelerator Vacuum Systems at DESY M.Seidel, DESY Workshop on Vacuum Systems of Synchrotron Light Sources Barcelona,
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
BROOKHAVEN SCIENCE ASSOCIATES SR Vacuum Systems ASAC Review, 7/17-18/ of 21 Storage Ring Vacuum Systems H. Hseuh, Vacuum Group ASAC Review of NSLS-II.
Canadian Light Source Commissioning Progress CLS Annual Users Meeting –
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
F. Mazzolini for the ELETTRA Vacuum Group OLAV CERN, April 11– The ELETTRA vacuum system F.Mazzolini, L.Rumiz, J.Miertusova, F.Pradal, E.Mazzucco,
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
1 BROOKHAVEN SCIENCE ASSOCIATES Beam Stability Overview NSLS-II CFAC Meeting May 8, 2007 S. Krinsky.
2008/12/10 INFN R&D on Low Impedance Beam Chamber and Components Y. Suetsugu, for KEKB Vacuum Group Contents Introduction Beam Chamber Components Connection.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
1 Workshop on Vacuum System Design for Synchrotron light Source ALBA - Barcelona, Sept New trends in the vacuum design and technology.
Primary Design Parameters July 13,2001 S. Childress Page 1 NuMI Besides design specifications driven by physics and Main Injector beam parameters, significant.
Report Technical Director Storage-Ring-Installation Completed
Low Emittance Rings 2014 Workshop
PROGRESS REPORT OF A NLNS-FFAG ADS MAGNET
Coupling Correction at the Australian Synchrotron
CEPC Vacuum System Dong Haiyi 2017/11/5.
Challenges for FCC-ee MDI mechanical design
Estimation and Protection on Synchrotron Radiation in CEPC Main Ring
XFEL Collimation and Beam Switchyard Vacuum Issues
The first shipment of SPEAR3 magnets (9 dipoles and 12 quadrupoles) arrived April 3. The second shipment (3 dipoles, 7 quadrupoles, and 6 sextupoles)
CEPC Vacuum Systems Design Consideration
Presentation transcript:

Abstract Storage Ring Vacuum and Interface to Magnets Hsiao-chaun Hseuh, NSLS-II Project This presentation provided a quick overview of the storage ring vacuum system for the NSLS II project. A typical cell layout was detailed including the various cross section shapes and materials, valve locations and types as well as the pumps and instrumentation used. In addition, the types and locations of the various photon absorbers and chamber interconnects were presented. The second half of the talk focused on interface between the various storage ring magnets and the vacuum chambers. Most of the problems encountered were caused by the lack of consistency in the coil shape and the positioning of the coils on the yokes. Providing the vendors with 'go-gauges' earlier in the project could have prevented some of the troubles we encountered. The importance of collaboration and communication between the various groups as well technicians and engineers was highlighted. Finally, the limitation on the extraction of ID and bending magnet fans due to the magnet dimensions as discussed. *Work performed under auspices of the United States Department of Energy, under contract DE-AC02- 98CH10886

Storage Ring Vacuum and Interface to Magnets April 11 th, 2012Prepared by: Charles Hetzel

Storage Ring Vacuum and Interface to Magnets Presented by: Hsiao-Chaun Hseuh Prepared by: Charles Hetzel Magnet Workshop April 11 – 12, 2012

Outline  SR Cell Layout  Vacuum System Details  Chamber-Magnet Clearance  Collaboration and Communication  Specification

1- Accelerator Tunnel 2- Experimental Floor MeV LINAC GeV Booster (C=158 m) 5 - RF Building, liquid He Plant 6 - Service Buildings Facility Overview  Nominal energy: 3 GeV  Nominal current: 500 mA  30 cells in 5 pentants  Ring circumference: 792 m

Typical Cell Layout G3 Dipole G4 Multipole G5 Dipole G2 Multipole G6 Multipole ID photon extraction 3PW photon extraction 3 pole wiggler (3PW)  Each 19-m cell (GV to GV) consists of 5 individual magnet/chamber girders.  3 focusing and 2 bending segments.  With RF gate valves at both ends of the cell.  Photon extraction takes place at G4 and G6.  Each cell is in-situ bakeable to > 130 o C  Design pressure: < 1x10 -9 Torr at 500 mA. Fast corrector and RF gate valve Fast corrector Fast corrector and RF gate valve

M M M D D S S FC Cell Chamber Extrusion Cross Sections Multipole cross section Dipole cross section Fast corrector S4A/S5A cross section ID beam line Front End BM beam line 90 multipole aluminum chambers, 3.7 – 4.5 m long 60 dipole aluminum chambers, 3 m long 60 short/narrow aluminum chambers - S4A, S5A 90 fast corrector inconel chambers - FC BM beam line Dipole Multipole ID/3PW fans

Typical Cell Layout – Valves  All metal RF gate valves isolate cells and straights.  Double position indicators.  Radiation resistant and bakeable.  Large RF gate valves to isolate SC cavities.  All metal gate valves at injectors and front ends.  Right angle valves  Roughing ports.  Vacuum gauge/RGA isolation. DN100 RF gate valve 60 units All metal gate valve ~ 40 units Right angle valve

Typical Cell Layout – Lumped Pumps and NEG Strips 200 l/s ion pump with TSP cartridge and roughing valve 100 l/s ion pump with TSP cartridge NEG strips in ante-chamber

Typical Cell Layout – Instrumentation  Instrumentation located at dipole chambers.  CCG and RGA at G3  CCG and TCG at G5  Gauge tree with isolation valve. Typical RGA scan RGA trend during bakeout

Typical Cell Layout – Absorbers Flange absorber 21mm(V) X 64mm(H) < 200 W (< 16 W/mm 2 )  Absorbers intercept unused dipole radiation.  Protect downstream flanges and bellows  All absorbers are made of GlidCop Al15. Stick absorber, X = 22 & 25mm < 700W (< 5 W/mm 2 ) < 130°C, Tube < 119°C Crotch absorber, X = +21mm < 1800W (< 57 W/mm 2 ) GlidCop < 180°C, Tube < 127°C

RF Shielded Bellows - > 220 units for Storage Ring Requirements:  Misalignment: +/- 2 mm  Stroke: +10/-15 mm  Angular deviation: +/-10 mrad  Low impedance GlidCop fingers Finger retainer Bellows weldment Contact springs Inconel 718 (w Ag) Stainless Sleeve (w Ag) Water cooled flange Coil spring (Be-Cu) inconel springs GlidCop fingersStainless sleeve

Vacuum Chamber Cross Sections Multipole cross section Dipole cross section Multipole Chamber in Sextupole M M M D D S S F F F Grooves are machined for magnet poles

Chamber-Magnet Clearance  Chamber-Magnet pole clearance - ≧ 2mm Not a lot when you consider:  Extrusion shape tolerance.  Bow and twist.  Distortion due to machining.  Machining tolerance.  Positioning according to BPM.

Chamber-Magnet Clearance  Grooves were machined to accommodate magnet poles for 2mm clearance  But coil dimensions are not well controlled which caused interference. Current design Should have coil-chamber clearance of 4mm. Machine grooves for coil clearance? Additional cost Chamber stability under vacuum

Chamber-Magnet Clearance  Clearance gauges should have been provided to manufacturers at the prototype stage.  Clearance check should have been added to the pre-ship check list for first articles.  Centering disk is required to ensure the profile is centered on pole tips. No centering disk = uneven gap With centering disk = even gap

Collaboration  Early and extensive collaboration with other groups.  Chamber design is driven by AP, Magnets, Diag., etc.  Changes in BPM and mounting resulted in re-development of extrusion (> 1 yr).  Some chamber materials were changed  RF bellows for slow correctors  S4A material development (In ⇒ SS ⇒ Al)  Inconel for FC chambers  RF shielding was added for BPM rogue modes.  Keep communication lines open  Attend other system meetings when possible.  3-D modeling can’t identified interference during assembly  Difficult to replace BPM buttons on girders  Difficult to assemble bellows due to photon extraction pipes  Significant impact to vacuum chambers due to small changes in magnets.  Increase in quadrupole length – 6 completed chambers were re-machined!  Oversized coils in 90 mm dipoles – re-design chamber ports and stands Current cross section Original cross section

Communication  Pro-a ctive communication and visits with manufacturers.  Establish relations with potential manufacturers as early as possible.  Visits early or before contracts are awarded can be very valuable  Is this allowed?  Encourage manufacturers to become more than manufacturers.  Ask manufacturer inputs to improve design and fabrication methods  Lack of quality control at some manufacturers – bi-metal flanges!  Close interaction between engineers and technicians.  Develop required tooling as soon as possible.  Use feedback from techs to improve and simplify the design and/or the fixtures.  Reference drawings are more useful to techs than a stack of engineering drawings.  Engineers should work through first few assemblies with technicians.

Establish a clear and complete set of specifications early on.  These can drive fundamental choices that can’t be changed.  i.e. comprehensive ray tracings early on for all possible insertion devices and beam positions to define  Geometric envelope vs. beam acceptance for SRP  Protection of vacuum components from large beam deviation  Allowable current without active interlock during commissioning  Maximum photon extraction openings are limited by the outboard dimensions of the magnets QM2:< - 2 mr for ID fan QL2/QH2:< - 5 mr for BM fan Specification QM2 QL2