SC Project Review of NCSX, April 8-10, 2008 Job 1260 Neutral Beam Transition Duct (NBTD) P. L. Goranson.

Slides:



Advertisements
Similar presentations
Test Chamber Assembly, 1.5M Long (59.00”) Vacuum Tube, 4.00 OD x 3.50 ID Vacuum Tube, 3.75 OD x 3.51 ID 3.375” CFF, Non-Rotatable Feedthrough, Ceramtec.
Advertisements

FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
Hg Delivery System Fabrication Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting May 5, 2006.
Project Management Considerations B. Nelson US ITER TBM Meeting INEL August 11, 2005.
SC Project Review of NCSX, April 8-10, 2008 NCSX Heater Control System P. L. Goranson Work package 1270.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
WBS activity and Cost Summary (Focus on Design) Clement Wong TBM Conference Call Oct. 27, 2005.
SC Project Review of NCSX, April 8-10, 2008 NSCX Poloidal Field Coils Michael Kalish.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
NCSX VACUUM VESSEL PL Goranson Comprehensive Final Design Review May 05, 2005 Vacuum Vessel Supports Heating/Cooling System NCSX.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
SC Project Review of NCSX, April 8-10, 2008 Central Controls and Computing WBS51 & 52 P. Sichta WBS5 Work Package Manager.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
Key Design Issues and Recent Reviews Tom Peterson, Fermilab DFBX PRR, October 23, 2002 US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley.
M. Gilchriese Overview of Production Plan for Pixel Global Support and Disk Support Rings M. G. D. Gilchriese Lawrence Berkeley National Laboratory February.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
SC Project Review of NCSX, April 8-10, 2008 NCSX Fueling and Vacuum Pumping Systems W. Blanchard WBS 21 and 22 Manager.
12/2/2004Module 2A1 The NCSX Engineering Web – An Overview Part I Work Planning, Project Files, Management Plans and Procedures.
Vacuum Vessel lateral loading (Neutral beam port only)
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by Vacuum Pumping, Gauging and RGA Systems W. Blanchard Princeton Plasma.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
NCSX NCSX CDR May 21-23, 2002 H.W. Kugel Slide 1 Conceptual Design for NCSX Auxiliary Systems Heating, Fueling,Wall Conditioning and Vacuum Systems.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
NCSX NCSX Vacuum Vessel R&D, Risk Management and Manufacture NCSX Preliminary Design Review October 7-9, 2003 Princeton, NJ Mike Viola, Phil Heitzenroeder,
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
October, 2009 Cost of SRF Components Gary McIntyre October, 2009 Internal Review.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
NCSX VACUUM VESSEL HEATING/COOLING PL Goranson Final Design Review April 4, 2006 Coolant Hose Assemblies and Thermo- hydraulics NCSX.
Preparations for working on Station 1 November 22, 2005.
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
NCSX Day 1 ECC (Extra Cheap Cryostat) Cryostat Configuration Status Report – September 30, 2006.
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Progress and Issues with VTS Upgrade
LARP Phase II Secondary Collimator RC-1
Project Management Considerations
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Instrumentation
SNS PPU Cryomodule Space Frame
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
SC1R Cold Box PDR Assembly Sequence
SNS PPU Cryomodule Design Overview
Presentation transcript:

SC Project Review of NCSX, April 8-10, 2008 Job 1260 Neutral Beam Transition Duct (NBTD) P. L. Goranson

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 2 Functional requirements NBTD provides interface for: - Man access into Vacuum Vessel (opening 13.5” wide x 34” tall) - Mounting vacuum pumping system (13.5” id Port) - Mounting Neutral Beam units - Mounting diagnostics - Mounting Lateral Supports and positioning VV toroidally In addition, the NBTD must penetrate and seal to the Cryostat. NBTD operates at 350C at its mounting flange during bakeout; most of construction must be Inconel.

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 3 Design Status Models were completed (2003) and were reviewed several years ago - Must reaffirm design, hold peer review and work toward SRD - A PDR is required Baseline was changed for a time to incorporate simplified ducts (Man Access Ports) which did not mount NB’s. Lateral support drawings were completed.

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 4 NBTD showing Lateral Supports Vacuum Pumping Port NB Port Man Access Lateral Support (top and bottom) VV Interface

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 5 NBTD Preliminary Drawings TOP VIEW

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 6 Labor Cost Title I an II Design Peer Review to Establish Requirements80Based in recent MDL & NCSX experience Review and Update Assbly Dwgs80Assume 2 40 hr each - based on MDL & NCSX experience Prepare for PDR Neutral Beam Transition Duct40Based in recent MDL & NCSX experience PDR for NBTD0Milestone - no resources Resolve PDR Chits40Based in recent MDL & NCSX experience Review and Update Port Mod Dwg40Assume 1 40 hr each - based on MDL & NCSX experience Review and Update Large Rect Port Dwg40Assume 1 40 hr each - based on MDL & NCSX experience Review and Small Large Rect Port Dwg40Assume 1 40 hr each - based on MDL & NCSX experience Review and Update Weldment Dwgs120Assume 3 40 hr each - based on MDL & NCSX experience Review and Update Misc Det & Cuts Dwgs40Assume 2 20 hr each - based on MDL & NCSX experience Review of Drawings40Assume 2 people for ~1/2 Weeks - based on MDL & NCSX experience Stress analysis160Based in recent MDL & NCSX experience Prepare for FDR Neutral Beam Transition Duct40Based in recent MDL & NCSX experience Final Design Review0Based in recent MDL & NCSX experience Resolve PDR Chits40Based in recent MDL & NCSX experience Subtotal Title I & II Design 800 Title III Disposition of deviation requests and non-conformances40Based in recent MDL & NCSX experience Update of drawings as Needed80Based in recent MDL & NCSX experience Procurement coordination20Based in recent MDL & NCSX experience Subtotal Title III Design140

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 7 M&S Cost Costs reflects recent significant increase in Inconel price. Lateral supports added. This element consists of the port duct, seals, and all cover flanges weight of shell assembly, with ports1400lbs $/lb for fabrication51$/lbIncludes recent vendor Inconel quotes subtotal, fab cost shell $71,400 Ports 8" o.d. flange, 6" tube 225 $/ea MDC catalog 10 8" o.d. rotatable cover flange 125 $/ea MDC catalog 10 no. of 8" ports 7ea cost for 8" ports$2, " x 16.5" flange with tube(ss)1500$/ea NCSX/MDL experience blank 14.5" x 16.5" flanges(ss)1000 $/ea NCSX/MDL experience no. of 14.5" x 16.5" ports 2ea cost for 14.5" x 16.5" ports$5, " o.d. flange, 14" tube 1000 $/ea MDC catalog " o.d. rotatable cover flange710 $/ea no. of 16.5" ports 2ea cost for 16.5" ports $3,420 large square flange cover, ss$4,000 o-ring seals for diamond flange and square flange$2,530 subtotal, ports $17,400 Fabricate and install lateral support$8,000$/ea number of supports 2ea subtotal for support $16,000 Total, each nbi port duct extension $104,800 no. of nbi duct extensions 3 total, 3 extensions$314,400 None of the above includes an interface to the cryostat.

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 8 Schedule & Staffing Schedule Staffing P. L. Goranson – 80% during Title I & II design. Gary Lovett – 100% during Title I & II.

SC Project Review of NCSX, April 8-10, 2008 P. L. Goranson - page 9 Schedule and Cost Risk Mitigation Uncertainty of the Estimate HighMediumLow Uncertainty Range (%) Design MaturityX -10%/+15% Design ComplexityX Other Comments: