TCLDA Design status Collimation Upgrade Specification Meeting 18-09-2015 L. GENTINI.

Slides:



Advertisements
Similar presentations
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
Advertisements

Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Injection Considerations for Scrubbing Run C. BRACCO, M.J. BARNES, W. BARTMANN, B. GODDARD, M. MEDDAHI, J. UYTHOVEN ACKNOWLEDGMENTS: M. DI CASTRO, M.DONZE,
Actuation and Alignment Challenges of LHC Collimators M. Garlaschè on behalf of the EN\MME collimation team 1 st PACMAN Workshop CERN, Geneva, Switzerland.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Vacuum, Surfaces & Coatings Group Technology Department Vacuum tests for CLIC module prototypes 6 November 2013 C. Garion2 Outline: Reminder: specification.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
1 DS Collimators at IR3: mechanical engineering and design LHC Collimation Upgrade Review Alessandro Bertarelli, Alessandro Dallocchio, Delio.
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
ELENA – Electron Cooler Vacuum design Benjamin Moles March 26 th 2015 on behalf of Electron Cooler team : Gerard Tranquille Jean Cenede Lars Soby Lars.
Collimation Meeting Tests on a Fully Assembled TCT Collimator in the HiRadMat Facility M. Cauchi, D. Deboy, on behalf of the Collimation Team.
Engineering Department ENEN Status of TCSP manufacturing Collimation Working Group (CWG) 24 June 2013 A. Dallocchio, A. Bertarelli, F. Carra, L. Gentini,
TCDI operation until LS2 LIU-SPS-to-LHC Transfer Line Protection Devices (TCDI) Review 1 Oliver Aberle 26/03/2014 O. Aberle (EN-STI-TCD)
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
HRM28-TCDI Updates June 24 th, 2015 Fausto Lorenzo Maciariello, F-X Nuiry, R. Ferriere, K. Karagiannis, M. Butcher, G. Vorraro, S. Le Fouest.
A. Bertarelli – R. Perret CERN TS – MME Group 1 CERN European Organization for Nuclear Research Mechanical Engineering and Thermo-mechanical.
Status of the activities on vacuum system C. Garion TBMWG, 20/06/2012.
41 st IUVSTA Workshop, Brdo pri Kranju, 21/06 – 24/06/2004 L. Schulz SLS Vacuum System Lothar Schulz Theo Bieri Nazareno Gaiffi Martin Steinacher.
HiRadMat Collimator Jaws HRMT23 03/07/2014EN/MME - E. Berthomé1.
A. Bertarelli CERN TS – MME Group 1 CERN European Organization for Nuclear Research Actuating system of the LHC Collimators (Phase 1) Main Features.
Agenda – Basics of cavity integration into CAST Introduction (M Davenport) Information exchange 2016 – Vacuum in cold bore – 2 cavities Cooling RF Cavities.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
Review of Mechanical Movement and Motorization for LHC Collimators The LHC Collimation project LHC Collimators for Phase 1 Alessandro Bertarelli.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
AFP-HPS /03/ D. D. INFN To/CERN PH UCM HPS240. Integration of Moving Beam Pipe and detector box. 1. Re-collection Layout of moving beam pipe.
Updated Design of TCLD whit reduced jaw length Collimation Upgrade Specification meeting L. GENTINI.
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
RAMI Paul Aden. RAMI Analysis Reliability Visual inspection during each shutdown Service schedule for necessary components Majority of components to have.
1 SLAC RC Status Report 19 July 2010 LHC Collimation Working Group Meeting Jeff Smith/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
Movable beam pipe and NNC Study & prototype development Manchester 14/12/20091D. FP meeting.
Two-beam module layout
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
F LESEIGNEUR / G OLIVIER LUND January 9th, ESS HIGH BETA CRYOMODULE ESS CRYOMODULE STATUS MEETING HIGH BETA CRYOMODULE LUND JANUARY 9TH, 2013 Unité.
LCWS11 WG4 Fully featured accelerating structure engineering design
Vacuum System P. Chiggiato TE-VSC
L. Gentini, A. Bertarelli, F. Carra
LARP Phase II Secondary Collimator RC1, ETC - Status 4/10/06
Proposal TDIS-TZM WP14 TDIS jaw validation testing
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Review on collimator movement with stepping motors
Challenges of vacuum chambers with adjustable gap for SC undulators
Components for the Machine-Interface Regions
Region between TAXN and D2 in HL-LHC IR1/5: Implications on Collimator Design Alessandro Bertarelli, L. Gentini (EN/MME) On behalf of the LHC.
EBTF Design Review Technical Meeting Group
TIDVG-4 TIDVG-4 Dump assembly, welding and installation Process sector BA1 February 2017 J. Humbert, (EN/MME) 06/02/2017 J. Humbert, EN-MME.
TCTW Collimator Design F. Carra1,2 A. Bertarelli, M. Garlasche, L
The 11T cryo-assembly: summary of design and integration aspects
Cryostat design Mechanical design: Thermal screens: Specifications:
Review on collimator movement with stepping motors
LARP Phase II Secondary Collimator RC1
TTC Hot Topic Common Questions
Phase II Collimators : design status
LARP Phase II Secondary Collimator RC-0 and RC-1
LHC Collimator – RF Contact Concept (180o wrap)
BGC Collaboration Meeting –
Presentation transcript:

TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI

Luca Gentini EN/MME 18/09/2015 2/10 Overview Design Jaws Actuation system Vacuum tank Lay-out Status

Luca Gentini EN/MME 18/09/2015 3/10 Actuation system Collimator “V” interconnection points. Collimator replacement without realignment Support assembly “V” interconnection points. Collimator replacement without realignment Collimator Actuation system

Luca Gentini EN/MME 18/09/2015 4/10 Completely new design never manufactured General -Active length 600 mm -Brazed cooling circuit -3x screwed tungsten blocs each jaw (30x20x200 mm) Or solid block in Glidcop? -Cantilever jaws Cooling system -1x Square pipes (9 mm edge, CuNi) -3x cooling pipes in the central cross-section Instrumentation -2x temperature probes (PT100) each jaw -2x Beam Position Monitor each jaw RF system -RF fingers + St. steel screens 600 mm

Luca Gentini EN/MME 18/09/2015 5/10 Tungsten blocs RF fingers RF screens St. Steel Bloc Support Glidcop Back stiffener Glidcop Tank axis Cooling pipes CuNi RF fingers

Luca Gentini EN/MME 18/09/2015 6/10 BPM Tapering slope: 10° RF screen St. Steel Tapering slope: 15° Screen RF contact CuBe C17410 Extremity RF contact CuBe C17410 RF contact CuBe C17410 Screen RF contact CuBe C17410

Luca Gentini EN/MME 18/09/2015 7/10 Completely new design never manufactured Movement -Two step motors each jaw  Jaw tilting -Stroke: -5  25 mm -Spring-back: in case of electrical short-cut the jaws must not go in beam direction Instrumentation -3x LVDT each jaw: 2x absolute movement, 1x relative movement (anti-collision) -3x switch assemblies each jaw : 2x absolute movement, 1x relative movement (anti-collision) Spring Roller screw Step motor Axis Movable table LVDT Switch

Luca Gentini EN/MME 18/09/2015 8/10 Completely new design never manufactured -Manufacturing process based on Ph.II tank. Electron Beam welded Stainless Steel. -No cooling system Fix RF fingers Flexible RF fingers NEW DESIGN OF THE EXTREMITIES To gain longitudinal space, the bellows after and before the collimator will be integrated into the tank transitions. Longitudinal stroke: +5; -15 mm Radial stroke: ±10 mm

Luca Gentini EN/MME 18/09/2015 9/10 Vacuum Equipment -2x D NEXTorr Pumps (integrated NEG Ion pump) -1x VVFMF DN 40 valve for mobile pumping -2x VGPB DN35 Penning pressure gauges -1x VGRB DN16 Pirani pressure gauge This lay-out agree with VSC group allows to solve previews integration conflicts VVFMF DN40 valve NEG Ion pump Penning gauge Pirani gauge BPM feedthrough

Luca Gentini EN/MME 18/09/ / D models Expected by DrawingsMaterial orderManufacturing date Collimator : JAWs, Tank, actuation system End Ready to go1 prototype: to be discussed 2 collimators: To be discussed Support End of Supports : to be discussed

Luca Gentini EN/MME 18/09/ /10