1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
Status of the Power Core Configuration Based on Modular Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Construction of Wendelstein 7-X Max-Planck-Institut für Plasmaphysik
NCSX May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1 ACC Review Of Modular Coil Manufacturing Facility Station No. 5 [VPI] the NCSX Manufacturing.
NCSX NCSX CDR May 21-23, 2002 Larry Dudek Slide 1 Facility Systems (WBS 62-65) L. Dudek, G. Gettelfinger, M. Kalish.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
SLA – Oct. 07 BDS-KOM1 Installation Overview Acknowledgment: F. Peters, M. Munro, J. Kim G. Aarons, C. Corvin, P. Rodriguez Fred Asiri/SLAC.
NCSX 1 NCSX Engineering Overview Wayne Reiersen NCSX Engineering Manager On behalf of the NCSX Team.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
January 4, 2007 RHIC II Project Internal Cost Review Gary McIntyre RHIC Ring Modifications January 4, 2007 Project Overview.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
NSTX NSTX Center Stack Upgrade Ensure fatigue resistant Welds: minimum # of locations shown, could be more. Various Weld Reinforcements & Hardware Replacement.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006 Page 1 Maintenance and Building Conceptual Approach L. Waganer and R. Peipert The Boeing Company 4 October.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain for Walter Sondheim, P-25, Los Alamos February 11, 2005, at Los Alamos National Laboratory Conventional.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
SC Project Review of NCSX, April 8-10, 2008 Plant Design Integration, General Arrangement Drawings E. D. Perry.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Installation of the T600 at Fermilab CSN2, September 22,
DRAFT Cost and schedule, staffing, metrology utilization 10 AM October 12, 2006 Mike Viola Field Period Assembly Manager.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
Neutrino 1 Assembly Process. Neutrino 2 Assembly Process Step 1: Basement I beams positionned and fixed on the ground. Flatness checked.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Installation of the T600 at Fermilab Fermilab, February 15,
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
Installation of the T600 at Fermilab
Hailo US Tower Equipment Manufacturer
Construction Documents
MICE Partial Return Yoke Mechanical Design
INSTALLATION SEQUENCE
Far Detector Activities Late 2017 – Early 2018
Suryoday Technologies ISO 9001:2015 Co.
L&V Manpower Development Prepared by: HR department Mar, 2013
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Polarized 3He target installation
Presentation transcript:

1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001

J.H. Chrzanowski2 WBS 700 Machine Assembly WBS 710 “Planning and Oversight” WBS 720 “On Site Pre-Assembly Activities” WBS 730 “Test Cell & Basement Assembly Activities” WBS 740 “Measurement Systems”

J.H. Chrzanowski3 WBS 700 Machine Assembly WBS 710 “Planning and Oversight” –Includes costs associated with planning and overseeing the assembly of the Vacuum Vessel /Coil Field Periods, plus the final assembly of the NCSX machine in the C-site Test Cell. –Responsible for coordinating all NCSX Test Cell activities including those Pre-assembly activities in the TFTR Test Cell

J.H. Chrzanowski4 WBS 700 Machine Assembly WBS 710 “Planning and Oversight” Developing plan for assembly of machine components Integration between WBS elements involving assembly issues Initiating and maintaining General Arrangement Drawing of Test Cell Designing tooling required for component assembly Design and fabrication of machine platform

J.H. Chrzanowski5 WBS 700 Machine Assembly Tooling Design and Material Procurements –Special assembly and lifting fixtures and tooling $100.0 k ~ $125.0 k (w/25% G&A) –General procurements ( miscellaneous items required for assembly- safety, tools, disposable items, etc.) $ 20.0 k ~ $ $25.0 k (w/25% G&A) –Platform Materials $35.0 k ~ $ 44.0 k (w/25% G&A)

J.H. Chrzanowski6 WBS 700 Machine Assembly Labor Requirements: –Construction Manager (1726 mhrs) –Engineering support (2857 mhrs) –Construction Safety Representative ( 1726 mhrs) –Industrial Hygiene (863 mhrs) –Quality Control (863 mhrs) –Cadd Designer (1295 mhrs) –Technician/ Monthly Support: (2386 mhrs) –Material & Supplies: $155.0 k ~ $194.0 k (w G&A) –Estimated Cost: $1,360 k

J.H. Chrzanowski7 WBS 700 Machine Assembly WBS 720 “On Site Pre-Assembly Activities” –This WBS section includes the costs associated with the receipt, assembly, alignment and vacuum leak testing of the (3) field periods

J.H. Chrzanowski8 WBS 700 Machine Assembly NCSX Pre-Assy. Area

J.H. Chrzanowski9 WBS 700 Machine Assembly WBS 720 “On Site Pre-Assembly Activities” –The assembly of the VV/Coil Modules will occur in the abandoned TFTR Test Cell located at D-site Area Preparation: $57.6 k (720 mhrs technician and monthly support) –Sufficient floor space and crane capacity available (110 Ton capacity) –Manpower dependent- Multiple segments could be assembled simultaneously

J.H. Chrzanowski10 WBS 700 Machine Assembly Assumptions –The vacuum vessel will be delivered to the TFTR Test Cell in three sections –The TF coils and Modular coils will be delivered to the TFTR Test Cell as separate components

J.H. Chrzanowski11 WBS 700 Machine Assembly TF Coil Systems –Receive, inspect and test TF and Modular coils $23.1 k (288 mhrs Tech. & Monthly Support) –Assemble all of the TF/Modular coils together for fit up and alignment Components may have to be match reamed Alignment equipment will be required (laser or “Faro” measuring arm required) –$147.2 k (1840 mhrs) approx. 2.5 months

J.H. Chrzanowski12 WBS 700 Machine Assembly Assemble Field Period Components –Assemble each of the three Field Periods TF coils/Modular coils/vacuum vessel and Trim coils Slide TF/ Module coil assemblies onto the vacuum vessel and align/fasten coil structures together Hang Vacuum vessel from Coil support structure MIG weld port extensions to the vacuum vessel –(22) extensions per field period

J.H. Chrzanowski13 WBS 700 Machine Assembly Assemble Field Period Components-continued –Vacuum leak Field Period segment –Install Trim coils inside of the vacuum vessel –PFC’s to be installed after final assembly of all three periods in the NCSX Test Cell (welded scenario) –Transport “Field Period” to the NCSX Test Cell –Cost per field period assembly $ k –Approximately 16 weeks per assembly

J.H. Chrzanowski14 WBS 700 Machine Assembly WBS 73 “Test Cell & Basement Assembly” –This WBS section includes the assembly of all the NCSX Torus components in the Test Cell including: All support structure Vacuum vessel & coil systems Cryostat Test Cell Platform (inc. lighting, fire detection, suppression system under platform)

J.H. Chrzanowski15 WBS 700 Machine Assembly Machine components will be assembled in the PLT/PBX Test Cell 25 Ton Overhead Crane will be used to assemble components

J.H. Chrzanowski16 WBS 700 Machine Assembly Remove walls during assembly NCSX TEST CELL

J.H. Chrzanowski17 WBS 700 Machine Assembly –Activities not included in this WBS : Bus runs to the coils (WBS 400) Cryo-line connections (WBS 600) Bakeout system installation & connections (WBS 600) Water system connections (WBS 600) Neutral Beam Installations (WBS 200) External Diagnostic Installations (WBS 300) Shield wall modification & installation (WBS 600) Vacuum pump system (WBS 200) External Diagnostics (WBS 300)

J.H. Chrzanowski18 WBS 700 Machine Assembly –Activities not included in this WBS : GPP Activities Lighting Upgrade Test Cell Roof upgrade ?? Dew Point Control needs repair C-site Cooling Tower Upgrade Upgrade Central Chilled Water Plant

J.H. Chrzanowski19 WBS 700 Machine Assembly Machine Assembly Sequence –Install/align machine support columns –Install lower support rings –Install lower cryostat floor –Position lower PF-3 & 4 coils in support Rings –Pump down & Leak Check Vacuum Vessel

J.H. Chrzanowski20 WBS 700 Machine Assembly Install 1 st. Field Period Install 2 nd. Field Period Install 3 rd. Field Period

J.H. Chrzanowski21 WBS 700 Machine Assembly Install Vacuum pump system –(WBS 200) Pump down & Leak check Vacuum vessel Complete installation Bakeout connections (WBS 600)

J.H. Chrzanowski22 WBS 700 Machine Assembly Raise into position Lower PF 3 & 4 Install Upper PF-3 & 4 Install PF-1 & 2 Solenoid PF4 PF3

J.H. Chrzanowski23 WBS 700 Machine Assembly Machine Assembly Sequence- continued –Installation of PFC’s and Internal Diagnostics –Weld support hardware and plumbing Approximately 2 months x 3 men –Assemble tile subassemblies (outside VV) Approximately 2 months x 2 men –Install Internal PFC’s & Diagnostics Approximately 4 months x 4 men Estimated Cost $300.0k

J.H. Chrzanowski24 WBS 700 Machine Assembly Machine Assembly Sequence- continued –Install Bus connections to coil systems (WBS 400) –Connect Cryostat and water lines (WBS 600) –Install Platform around machine –Install external diagnostics (WBS 300)

J.H. Chrzanowski25 WBS 700 Machine Assembly Install Cryostat walls and ceiling –Install collars and boots around feedthru’s

J.H. Chrzanowski26 WBS 700 Machine Assembly

J.H. Chrzanowski27 WBS 700 Machine Assembly

J.H. Chrzanowski28 WBS 700 Machine Assembly Estimated cost excluding WBS 740 –$ 2,875.0 k

J.H. Chrzanowski29 WBS 70 Machine Assembly Rates Used For Estimating –Engineering -mechanical & electrical (EM) $ per hour –Senior lab (SM)/Technicians (TB) and Cad Designers(DM) $80.00 per hour –Material & Supplies Cost plus 25% G&A No contingency included in estimates