A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
A. Hervé - 13 august 2007 ILC-IRENG Meeting of Working Group A: 13 Aug 07 Proposal for an Experimental Area With only One Large Shaft A. Hervé/CERN.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Conventional Facilities and Siting Global Design Effort Safety Requirements for IR Conventional Facilities and Siting Group Safety Requirements for IR.
Construction and Installation of the CLIC Experimental Area
19/10/2010 GS-SEM J Osborne N Baddams A Kosmicki EN-CV M Nonis EN-MEF M Gastal PH-CMX A Gaddi H Gerwig A Herve N Siegrist DGS-SC.
CLIC MDI Working Group QD0 external reference structure A. Gaddi, H. Gerwig, H. Hervé, N. Siegrist, F. Ramos.
1 FD Support and Pacman for GLDc 27 Aug Yasuhiro Sugimoto KEK.
Tracking Integration Challenges Y. meeting 2013/9/25.
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
1. Civil Engineering works for Linear Colliders* : -Brief introduction on the overall machine layout (just for CLIC at this stage) -Experimental Area.
Global Design Effort - CFS SiD Collaboration Meeting - SLAC 1 VERTICAL ACCESS ILC IR LAYOUT for SiD and ILD CONVENTIONAL FACILITIES AND SITING.
October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
MEA Machine and Experiment Assembly 1 Norbert Meyners, MEA Engineering Forum at CERN 12.Okt Thoughts about LDC Hall and Assembly (Work is not finished.
4366-ILD-T-Platform-and-environment.ppt A. Hervé Seoul workshop 17 February 2009 Concept of Platform and Environment A. Hervé / ILD-Webex meeting.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Global Design Effort Critical Interaction Region Issues, Report from the IR engineering workshop Andrei Seryi, SLAC October 24, 2007.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
CLIC Experimental Area Layout Design Considerations & ARUP Study A. Gaddi, H. Gerwig, M. Herdzina, H. Hervé, N. Siegrist, F. D. Ramos.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
Date Event Global Design Effort 1 Platform Moved on Hillman Rollers, Deformations John W. Amann ILC – Mechanical Engineering 9/12/07 IREng07.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
A. Hervé - 17 Sept ILC-IRENG IRENG07 Workshop: 17 Sept. 07 Various Possibilities for disposition of Experimental Area A. Hervé/CERN.
3/20/11 ALCPG11 Global Design Effort 1 CFS Detector Hall Considerations Tom Lackowski.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
March 22, –  Design Concept & Hall Layout  Access Tunnel  Top heading Tunnel  Displacement of detector hall by push-pull operation.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
Global Design Effort Working Groups A & C Parallel Session Summary IRENG07 A. Herve, T. Markiewicz, T. Sanuki, Y. Sugimoto V. Kuchler, A. Enomoto, J. Osborne.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
CES Studies at CERN for the Interaction Region : -Summary of Linear Collider IR meeting at CERN held on 16 February Design Brief for external design.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Philip Burrows SiD Monthly Phone Meeting, 4/10/071 IR Issues from IRENG07 Philip Burrows John Adams Institute Oxford University.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
Implication of gamma-gamma on 14mr tunnels discussion (questions for discussion with WG-C and WG-A) Valery Telnov Budker INP IRENG07, Sept.19, 2007, SLAC.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
Octobre LAL Orsay Report from the IRENG07 workshop at SLAC W. Lohmann, DESY from Septembre 17 – 21, ~ 100 participants - plenary and parallel sessions.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
CLIC Handling Engineering Update
CLIC Civil Engineering Update
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
CLIC / ILC Collaboration for CFS works
Interaction Region Alternative Layouts
Design Concept Update – Platform Moved on Hillman Rollers
Detector hall in mountain regions
CMS Gantry for Detector Lowering
Detector hall in mountain regions
RDR Baseline Layouts for Interaction Region
Presentation transcript:

A. Hervé - 17 Oct CLIC-Workshop CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

A. Hervé - 17 Oct CLIC-Workshop Contents Hypotheses for ILC Workshop in September –Deep site, push-pull, surface assembly… Various dispositions of Experimental Area –Two Large Shafts directly over UX –Two Large Shafts offset wrt. UX Possible Underground-Hall Parameters Conclusions for ILC (and CLIC…)

A. Hervé - 17 Oct CLIC-Workshop Hypotheses for ILC workshop in September Difficult to equip ILC with two independent IRs, but need two indpendent experiments Choice of Push-Pull scheme to exchange experiments frequently, say every month or so Exchange must be done quickly, say in small week.

A. Hervé - 17 Oct CLIC-Workshop Hypotheses for ILC workshop in September These goals are ambitious. It was concluded that they can be met, but this cannot be for free. Part of the saving from doing away with a second IR will have to be invested to provide a well-engineered, efficient and safe push-pull system.

A. Hervé - 17 Oct CLIC-Workshop Hypotheses for ILC workshop in September Chosen site is a ‘Deep Site’, say 100 m deep or so. ‘Surface Assembly’ scheme followed by ‘Heavy-Lifting’ à la CMS is used. The ‘Larger Detector’ will drive the requirements (GLDc is used as example here). If the other one is a ‘Smaller Detector’, it will benefit from improved facilitities.

A. Hervé - 17 Oct CLIC-Workshop Moving platform is a safe solution… To move quickly and safely a 12’000-ton (or so) large composite object is not easy and a dedicated platform would do the trick. It provides a well-defined interface from which all parties can design with different time scales (Civil Engineering needs to go in construction earlier than experiments). The platform would allow the detector to be commissioned in the garage position and moved in a nearly working state towards IP..

A. Hervé - 17 Oct CLIC-Workshop And a clear interface for organization Collaboration could be responsible for opening, maintening, closing, and operating its experiment above the platform ILC machine could be responsible for moving the platform carrying a detector to the beam position, and from it to the garage positions. Mainly beam line protruding inside the detector would need to be re-connected (and re-aligned), in a common effort.

A. Hervé - 17 Oct CLIC-Workshop A concrete platform will be stiff enough…. Example: A 2’500-ton load on the CMS cover : 20 m between supports and only 3 mm sag…

A. Hervé - 17 Oct CLIC-Workshop ILC Sliding Platform Design Concept Concept developed by J. Amann, A. Hervé and H. Gerwig Platform details: 20x15x2m 5m wide trenches for cable chain and roller access. Steel reinforced concrete

A. Hervé - 17 Oct CLIC-Workshop ILC Sliding Platform Design Concept Uses 1.5kT roller module with 1kT hydraulic jacks. Design must be optimized to distribute load evenly over roller module. Feet support platform when stationary. Could provide isolation from vibration Space for access to rollers/jacks.

A. Hervé - 17 Oct CLIC-Workshop SX5 20m shaft to expt cavern 12m shaft to service cavern Oct 2000 Pressure from Civil Engineering Schedule will be as important for ILC than for CMS, (maybe also for CLIC… ) Choice of Full Surface Assembly for schedule reasons

Elements are fully cabled to local racks. All services, gas and water cooling pipes are there. Subdetectors are fully commissioned. Once below they can be connected to the umbilical cables going to the counting rooms through the cable chains. Another advantage of Surface Assembly ‘à la CMS’ is that Elements fully are fully commissioned before being lowered

A. Hervé - 17 Oct CLIC-Workshop IRENG07 Workshop: 17 Sept. 07 Experimental Area Two Large Shafts RDR Design

Side pressurized Egress tunnels connected to stairs/lifts Common to all designs Started design with two large shafts directly above UX-Hall Strong interference in Logistics and Safety between Shafts and Detector Areas This design has been put aside looking for better solutions Safety and logistics problems during ALL handling operations Difficult to position lifts and stairs

A. Hervé - 17 Oct CLIC-Workshop IRENG07 Workshop: 17 Sept. 07 Experimental Area Two Large Offset Shafts

A. Hervé - 17 Oct CLIC-Workshop Shafts are moved outside the main cavern The two shafts are positioned outside the footprint of the main underground hall to do away with interferences (in safety logistic and schedule) between loading/unloading areas and working areas. This solution has been used for 3 of the 4 LEP experiments, Aleph, Delphi, Opal. It needs horizontal transfer of loads but this is well adapted to the full surface assembly scheme when the number and weight of elements to transfer in UX is limited.

A. Hervé - 17 Oct CLIC-Workshop Two shafts with lift/stairs services 80-t crane access from surface 9m shaft for machine service Two Large Shafts outside the Footprint

A. Hervé - 17 Oct CLIC-Workshop Stairs & Lift +services Potential risk of structural weakness on this side

A. Hervé - 17 Oct CLIC-Workshop IRENG07 Workshop: 17 Sept. 07 Experimental Area Two Large Shafts Offset Diagonally wrt IP

Two Large Shafts in Diagonal to reduce structural weakness on the side of the two shafts

A. Hervé - 17 Oct CLIC-Workshop

A. Hervé - 17 Oct CLIC-Workshop For the Experiments in the Underground Hall there is no difference

A. Hervé - 17 Oct CLIC-Workshop Platform

Elements could be lowered at an angle and rotated in the Transfer Tunnel

A. Hervé - 17 Oct CLIC-Workshop For two experiments, it is too crowded with only one SX hall Because during Phase I, shaft areas have to be reserved for CE Civil Engineering turf during phase I

A. Hervé - 17 Oct CLIC-Workshop One solution is to separate the two Surface Halls If needed gantry can be shared

A. Hervé - 17 Oct CLIC-Workshop However, the simplest solution for logistics is to have two parallel halls The gantry can still be shared if needed

A. Hervé - 17 Oct CLIC-Workshop This is a view of phase I, when civil engineering uses the shafts

A. Hervé - 17 Oct CLIC-Workshop And a view of phase II

A. Hervé - 17 Oct CLIC-Workshop And a view of phase II during Heavy Lifting operations

A. Hervé - 17 Oct CLIC-Workshop IRENG07 Workshop: 17 Sept. 07 Experimental Area Underground Hall Parameters for Two Large Shaft Solution

Possible Hall Parameters - Length around 90 m Space reserved for shielding wall 8 m working corridor, could be from 0 to 100% on any one side of experiment in 2-m increments, using ‘working platforms’ to fill the gaps Space for ancillaries recovered from curved end-wall Maximum stroke 28m

A. Hervé - 17 Oct CLIC-Workshop Transfer tunnel 31 m 5.6m 9m Possible Hall Parameter - Width Transfer Tunnel allows easy extraction of ‘Tracking Device’

1 31 m 11 m 9 m Possible Hall Parameter - Width Depends of Crane Reach and Pacman Region 2 28 m GLDc Two 40-t cranes with asymmetric crabs This bottom space is ‘free’ because of the invert Top used by ventilation ducts

The interface between the experiment, the last part of the machine and the movable shielding (pacman) is a complex region that needs an integrated effort Example of GLDc at ILC

Example of GLDc at ILC, Opening Scenarios govern the choice of hall parameters

A. Hervé - 17 Oct CLIC-Workshop IRENG07 Workshop: 17 Sept. 07 Conclusions

A. Hervé - 17 Oct CLIC-Workshop Conclusions-I Various experimental area dispositions have been looked at for ILC, assuming that: -A deep site is used -Assembly on the surface and heavy lifting ‘à la CMS’ are used -At least one large detector is installed on a platform and push-pull scheme is used

A. Hervé - 17 Oct CLIC-Workshop Conclusions-II -The platform can move on heavy-duty rollers as it has to go in one direction only -The preferred solution for moving the detector elements is to use air-pads as complex paths are likely to be required -These air pads can be used in the ‘sublifting’ mode for maintenance operations guaranteeing no relative vertical movements (H. Gerwig)

A. Hervé - 17 Oct CLIC-Workshop Conclusions-III If surfaced assembly is used, two large shafts positioned directly above the underground hall are not the preferred solution -If two large shafts are used it seems better to position them diagonally wrt IP, outside the footprint of the underground hall -Stairs, lift and services can be installed in these large offset shafts

A. Hervé - 17 Oct CLIC-Workshop Conclusions-IV The length of the underground hall could be around 90 m for the two-large-offset-shaft solution -The width depends of the way the pacman region is designed and which crane coverage is acceptable -These parameters, like the best disposition of the experimental area, are ‘detector dependent’.

A. Hervé - 17 Oct CLIC-Workshop Conclusions-V Most of this reasoning is certainly applicable to CLIC IR, however there will be differences, for example the amount of services and the radiation environment outside the detectors. It would be useful to form early enough a study group, working closely with a proto-collaboration and a typical CLIC detector, to orient correctly the civil engineering studies for the CLIC IR and experimental hall(s), (and also other studies for CLIC detectors…)