Long-Baseline Neutrino Facility LBNF Integration - Interfaces, Config Mgmt and Requirements Jeffrey Dolph LBNF/DUNE DOE/SC CD-1 Refresh Review July 14-16,

Slides:



Advertisements
Similar presentations
1 PROJECT MANAGEMENT ROLE OF KEY PERSONNEL Bernd Madauss International Space University Strasbourg February, 2011
Advertisements

Project Scope Management
Project Change Management
Chapter 3: The Project Management Process Groups
Development plan and quality plan for your Project
© VESP International Pty Limited To Contents Slide CLICK to advance slides/ bullet points within slides Integrated Master Planner An Overview.
Fermilab Neutrino Beamline to DUSEL Mike Martens Fermilab PAC November 3, 2009.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Long-Baseline Neutrino Facility LBNF Summary of FSCF Final Design Parameters Meeting at SURF, 10 Aug 2015 Elaine McCluskey, LBNF Project Manager EFIG 19.
Managing Engineering Design - Infrastructure. Presentation Overview 1.Tools and Techniques 2.Design and Documentation 3.Estimating and Scheduling.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Certificate IV in Project Management Qualification Code BSB41507 Unit.
© Mahindra Satyam 2009 Configuration Management QMS Training.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Logistics Workshop Summary Mike Headley August 19, 2015.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Project Scope Management Information Technology Project Management, Fifth Edition Note: some slides have been removed from the author’s original presentation.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Develop Project Charter
12/2/04Module 2D1 The NCSX Engineering Web – An Overview Part IV Engineering Management & Systems Engineering and Other.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
JWST PRDS Project Mangement Case Study Jesse Doggett Project Engineer, ITEB/OED.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
DUNE-LBNF Configuration Management Jeff Dolph, LBNF interim Systems Engineer BNL.
Long-Baseline Neutrino Facility LBNF Engineering Data Management System Jeff Dolph EFIG meeting August 5, 2015.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
State of Georgia Release Management Training
September 10, FY 2003 Plans Bob Simmons. September 10, Introduction Overview of Project and Engineering Plans Project Plans Engineering Plans.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Conventional Facilities for the Far Detector Options Assumptions and Cost Estimates T. Lundin April 25, 2012 LBNE Reconfiguration Workshop - 25, 26 - April-2012.
6/6/ SOFTWARE LIFE CYCLE OVERVIEW Professor Ron Kenett Tel Aviv University School of Engineering.
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Project 29 September 2015.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
News from LBNF C. J. Mossey, LBNF Project Director DUNE Collaboration Meeting - South Dakota School of Mines and Technology 19 May 2016.
Long-Baseline Neutrino Facility LBNF Far Site Conventional Facilities (FSCF) Scope and Interface Overview Tracy Lundin as borrowed from Headley & Willhite.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Engineering Documentation
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Long-Baseline Neutrino Facility LBNF LBNF/DUNE Status N. S. Lockyer
Long-Baseline Neutrino Facility LBNF Update: LBNF EVMS Implementation for CD-3a Elaine McCluskey, LBNF Project Manager Bob O’Sullivan, Project Controls.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
Long-Baseline Neutrino Facility LBNF LBNC: Far Site Update and Planning Mike Headley LBNF Far Site Facilities Project Manager January 11, 2016.
DUNE-UK Mark Thomson University of Cambridge DUNE-UK Meeting, UCL May 15, 2015.
Challenges to get LBNF ready for Far Detector installation ASAP Elaine McCluskey ELBNF Proto-Collaboration Meeting 22 Jan 2015.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
LBNF 1 LBNF/DUNE – Construction Summary. LBNF Far Site Facilities Scope and Requirements LNG Membrane cryostat is an European technology. CERN has now.
CERN Steve Kettell DUNE Collaboration Meeting January 12, 2016.
1 DOE Independent Project Review Critical Decision-3a Long-Baseline Neutrino Facility/ Deep Underground Neutrino Experiment (LBNF/DUNE) Project DOE Executive.
IEFIG update Joe Lykken | iEFIG Chair ELBNF IB phone meeting | 6 March 2015.
Long-Baseline Neutrino Facility LBNF Elaine McCluskey, LBNF Project Manager Fermilab PAC Meeting 23 June 2015.
Camera PDR/CD1 Planning 19 September 2008
Accelerator Readiness Review October 31, 2006
Software Project Configuration Management
Managing the Project Lifecycle
Risk Identification HL-LHC Detector Upgrades Project
Software Configuration Management
News and brief overview of Beamline plans for the next few months
Hyper-V Cloud Proof of Concept Kickoff Meeting <Customer Name>
Details supporting the increase
Configuration Management
Conventional Facilities
Executive Project Kickoff
Project Kick-off <Customer Name> <Project Name>
CF Scope, Management & Organization
Presentation transcript:

Long-Baseline Neutrino Facility LBNF Integration - Interfaces, Config Mgmt and Requirements Jeffrey Dolph LBNF/DUNE DOE/SC CD-1 Refresh Review July 14-16, 2015

LBNF Who am I? What have I done? Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements2 Jeff Dolph, Principal Engineer at BNL Physics Dept. Registered Professional Engineer - Mechanical Professional Experience: 3 years – LBNE Systems Engineer 2 years – Chief Engineer, LBNE Water Cherenkov Far Detector 25 years – Mechanical Engineer - integration of major mechanical and structural modifications:  Boeing Company  Northrop Grumman  Consulting Engineer 747 Special Freighter US Marine Corps radar system

LBNF Outline Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements3 Integration Team Interface Development and Management Configuration Management and Change Control Other Important Integration Tasks  Requirements Development  Value Engineering and Trade Studies

LBNF Integration – Project Engineers and Systems Engineer Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements4 Integration to assure complete design can be delivered within subprojects is the responsibility of the subproject Project Engineers  Beamline: Salman Tariq  Near Detector: Jan Boissevain  Far Detector: Russ Rucinski, Terry Shaw  FSCF: Josh Willhite  NSCF: Tom Hamernik  Cryogenic Infrastructure: Barry Norris Between Subprojects, this role is covered by the Systems Engineer with help from the Project Engineers & their teams  Covers requirements, risk, interfaces, QA, configuration control  This talk addresses interfaces, configuration control & requirements

LBNF Interfaces between LBNF & DUNE and within Subprojects Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements5 Interfaces are managed between major WBS elements using a matrix linked to Interface Control Documents (ICD)  ICDs define the interfaces and any parameters associated with them.  ICDs signed by relevant managers on both sides  ~150 ICDs expected to be developed across LBNF/DUNE Far Site and Near Site Matrix contains schedule for completion of interface definition Expect to complete by end of this year Highest priority is FSCF since that is critical path and needed for CD- 3a this fall, to be completed by Sept. 3 Interfaces are discussed in weekly subproject meetings that involve team members from associated subprojects  Example: NSCF engineers attend most Beamline meetings to assure Beamline CF is being designed to meet Beamline requirements

LBNF ICD Matrices Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements6 5 matrices cover all LBNF to DUNE interfaces  DUNE FD (internal)  DUNE ND (internal)  LBNF-DUNE Near Site (Beamline – ND – CF – Fermilab)  Near Site – Far Site (alignment)  LBNF-DUNE Far Site LBNF-DUNE Far Site interface documents are found on the Project Planning Documents review site linked in this matrix Project Planning Documentsmatrix

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements7 ICD Matrix example – Far Site Design/Construction LBNF-DUNE Far Site Interface Matrix Note: Each cell will contain a hyperlinked ICD after the completion date. Far Site Entity Design/Construction CF, Far Site - Surface CF, Far Site - Shafts & Drifts CF, Far Site - Caverns Far Detector Design Far Detector Construction Cryostat Design Cryostat Construction Cryogenics Ar System-Design Cryogenics Ar System-Construction Cryogenics N System-Design Cryogenics N System-Construction Cryogenic Fluids SURF CF, Far Site - Surface CF, Far Site - Shafts & Drifts 3-Sep-15 CF, Far Site - Caverns 3-Sep-15 Far Detector Design 24-Jul Far Detector Construction 24-Jul Cryostat Design 24-Jul Sep-15 Cryostat Construction 24-Jul Sep-15 Cryogenics Ar System-Design 24-Jul Sep Sep-15 Cryogenics Ar System-Construction 24-Jul Sep Jul-15 3-Sep-15 Cryogenics N System-Design 24-Jul Sep Sep Sep-15 Cryogenics N System-Construction 24-Jul Sep Jul-15 3-Sep Sep-15 Cryogenic Fluids 24-Jul-15 3-Sep-15 SURF 3-Sep Jul-15 indicates highest priority indicates draft itemization only

LBNF ICD Development Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements8 Capture all technical and programmatic interfaces between stakeholders  Numerous technical meetings with Project Engineers, Scientists, Managers to list interface items and “provider” if evident  Draft ICD from input  Review drafts with stakeholders with an eye toward determining “provider” for each item Seek stakeholder’s agreement and finalize

LBNF Experiment - Facility Interface Group (EFIG) Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements9 Addresses high-level interfaces between DUNE and LBNF Charged with assessing formal Change Requests in which one Project affects the other & making recommendations for changes EFIG initiated Far Site underground modular reconfiguration  4 equal-size free-standing cryostats for detectors  Same cryostat for both single & dual-phase detectors  4 equal-size caverns  Central utility cavern  Considered competing schedule and funding programmatic requirements EFIG recommended recent change to larger target hall to include this scope, cost, and schedule in CD-1 Refresh

LBNF Configuration Management - in development Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements10 Change to any controlled documentation  Requirements  Deliverable(s) and/or ICD(s)  Engineering drawing and/or specification  Selected project plans such as PMP Change Request (CR) will be initiated in joint CR database Engineering documentation managed in Fermilab Teamcenter engineering document database Project documentation managed in project’s document database DocDB  Electronic BOEs, all project plans, other relevant documents  Provides for versioning and approvals

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements11 Change Control – LBNF/DUNE Integrated Process Separate processes that will be managed through each Project Converge when change affects both Projects Not required until CD-2, but will start process for FSCF at CD-3a Change thresholds based on impact to technical scope, cost and/or schedule and in accordance to Configuration Management Plan and DOE PPEP Configuration Management PlanDOE PPEP

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements12 LBNF/DUNE Requirements Science objectives flow down to science and engineering requirementsscience and engineering requirements

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements13 LBNF/DUNE Requirements High level programmatic requirements flow down to the deliverables’ programmatic requirements

LBNF Summary Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements14 Robust Integration approach for LBNF/DUNE  Interfaces - being defined within and between subprojects  Configuration Management with Change Control – in development  High level requirements developed and managed Configuration Management to be implemented now to CD-3a for Far Site Facilities design and for LBNF Far Site - DUNE interfaces Engineering team in place to manage systems across and between subprojects

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements15 Backup

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements16 Ensuring all scope is covered through interface management Partners define work scope of intended Deliverable(s) by defining limits re: Interfaces Work scope of each Deliverable (one WBS item per Deliverable for non-DOE) Deliverables, ICD’s and Interface Matrices evolve with Partnership Development Compile Deliverables Lists for full scope of LBNF and DUNE Analyze Deliverables Lists and ICD’s for gaps and overlaps looking for missed or duplicated scope Negotiated adjustments to Deliverable scope and interfaces Partners can generate Statements of Work (SOW) from Deliverables Lists and ICDs and incorporate into agreements

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements17 Configuration Management Data Flow Deliverables’ Data Interface Control Documents (ICD) Deliverables Data List Interface Matrices LBNF/DUNE Config. Mgr. (SE acting) Change Control Data Management Systems LBNF/DUNE Science & Engineering Configuration Status Accounting Configuration Verification Process of creating defined-scope deliverables starts here

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements18 Interfaces Between Partners to Start Far Site Construction (Excavation) Far Site interface requirements already developed for kick-off with A&E, are under revision to the new configuration Scope Interface Review to be held soon with scientists, engineers and managers having interfaces to Far Site Conventional Facilities (CF) LBNF Far Site CF design and construction has priority, CD-3a before CD-2 for all of LBNF/DUNE:  Some level of “baseline” of the interfacing deliverables within: LBNF Near Site – Beamline and CF (Far Detector alignment) LBNF Far Site facility (ES&H, SURF throughout the schedule, utilities…) DUNE Far Detector (ES&H, schedule, utilities, installation…) LBNF Cryostats (ES&H, schedule, space via FD interface, construction..) LBNF Cryogenics Systems (ES&H, schedule, surface, shaft, caverns…)  After CD-3a changes affecting LBNF Far Site CF will be under Change Control

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements19 Configuration Management Development Planning for CD-2 needs to begin now and develop with Partnership development Each Deliverable to be a Configuration Item (CI), have a Work Breakdown Structure (WBS) ID, and dictionary definition Level 4 CI’s roll up into Level 3 End Items and so on up to the (4) End Items described earlier (4) integrated deliverables lists, formally called Configuration Items Data Lists(CIDL) all have associated ICD’s 1.DUNE Near Site 2.DUNE Far Site 3.LBNF Near Site 4.LBNF Far Site = LBNF/DUNE scope

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements20 LBNF/DUNE – Configuration Management - Data Management Systems LBNF/DUNE Science and Engineering Requirements available to all (read only), controlled by Systems Engineer (SE), approval by DUNE and LBNF CI data is controlled by Owner/Partner in their Data Management System –Current CI engineering – CF or electro-mechanical CAD models and drawings with PDF’s –Specifications, including Suppliers’ specifications (verified to meet requirements) –Copies of current CIDL and ICD’s (access via web, described later) –Copies of Change Control data (access via web) LBNF/DUNE Project Offices: –Each CI must have a unique TeamCenter (TC) Design Item ID, named appropriately –Each End Item must have a unique TC Design Item (Assembly of CI’s), named appropriately –CIDL, controlled by SE, contains list of controlled documentation that fully describe each CI (deliverable)

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements21 LBNF/DUNE – Configuration Management - Data Management Systems Partners upload current engineering and specifications with ID of Change Control items completed, to its TeamCenter Design Item on a regular schedule (TBD) and at data-freeze milestones for reviews Note: Fermilab performs this for A/E SE designated Configuration Manager (CM) converts and assembles CAD models in TC/NX into current Near Site and Far Site configurations In a regularly schedule process CM performs: –Configuration verification –Configuration status accounting –Updates CIDL’s and ICD’s –Reports results to SE, PM and TC

LBNF Jeff Dolph | Integration - Interfaces, Config Mgmt and Requirements22 Value Engineering & Trade Studies Value Engineering is a continuous process Will be performed for FSCF final design with A/E before CD-3a Value engineering & trade studies have already produced major design decisions:  Beamline on embankment vs. underground  Waste rock handling  Major Far Site underground reconfiguration February-March 2015