Criminal Justice System Modernization Project: DPW’s Infrastructure Projects 24 June 2015 1.

Slides:



Advertisements
Similar presentations
Regulation: Strategic Planning and Budgeting A Practical Perspective Tim Maverley. Head of Finance. Department of Justice and Law Reform.
Advertisements

1 Alignment to the Local Government Turn Around Strategy (LGTAS)
Briefing to the Portfolio Committee on Police, National Assembly PROPERTIES OCCUPIED BY ICD V227, Second Floor, Old Assembly Building Parliament, Cape.
Finance DEPARTMENT: FINANCE MPUMALANGA PROVINCIAL GOVERNMENT Presentation to Select Committee on Finance on Budget and Expenditure Outcomes for the period.
Municipal Infrastructure Grant Sport and Recreation 15 February 2005.
1 NATIONAL DEPARTMENT OF HEALTH PRESENTATION ON THE FFC RECOMMENDATIONS ON THE DIVISION OF REVENUE 2011/12 17 AUGUST 2010.
VP Quarterly Report on Strategies Q1 – 2015/16 VP: Carol Klassen – Knowledge & Technology Services Multi-year Plans: - IT/IM/Equipment Multi-year Plan.
Atlanta Public Schools Project Management Framework Proposed to the Atlanta Board of Education to Complete AdvancED/SACS “Required Actions” January 24,
Portfolio Committee on Police Briefing: 4 th Quarter Financial Report 2012/13 17 SEPTEMBER 2013.
Presented by Themba P Wakashe Director-General REPORT ON THE UNSPENT BUDGET 2009/10 TO STANDING COMMITTEE ON APPROPRIATIONS.
YOUNG PROFESSIONALS SEMINAR CIVIL ENGINEERING CHALLENGES Venue: CSIR International Convention Centre Gauteng Date: 22 November 2013 Presenter: Vikash.
SITA Presentation to Portfolio Committee on Police 29 October 2010.
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
EPWP PRESENTATION TO PORTFOLIO COMMITTEE. Principles informing IDT’s role Adding value to government development agenda Delivery of measurable sustainable.
DEPARTMENT OF LABOUR Expenditure – 30 JUNE MAIN DIVISIONS OF THE VOTE.
PRESENTATION: PORTFOLIO COMMITTEES ON CORRECTIONAL SERVICES AND HEALTH PROVISION OF HEALTH CARE WITHIN CORRECTIONAL CENTRES 1.
COMPLIANCE WITH THE SIGNING AND FILING OF PERFORMANCE AGREEMENTS BY HEADS OF DEPARTMENT BRIEFING TO THE PORTFOLIO COMMITTEE ON PUBLIC SERVICE AND ADMINISTRATION.
Select Committee on Appropriations Wednesday, 29 August 2012 Committee Room M46, Marks Building Presentation by Mr MG Seitisho LOCAL GOVERNMENT TURNAROUND.
1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June.
1 2009/10 DIVISION OF REVENUE BILL Presentation to Select Committee on Finance 24 February 2009.
1 Mpho Mathabathe: Researcher Portfolio Committee on Correctional Services Analysis of DCS Annual Report (2008/09)
Presentation to Portfolio Committee on Police on SAPS Communication Projects By: Mr Sithembiso Freeman Nomvalo
Portfolio Committee on Appropriations Quarter 1 Expenditure and Performance 24 August 2012 The Presidency Department of Performance Monitoring and Evaluation.
DEPARTMENT OF CULTURE, SPORT AND RECREATION MPUMALANGA PROVINCE COMMUNITY LIBRARY CONDITIONAL GRANT 2011/12 FINANCIAL YEAR 1.
Presentation to the Portfolio Committee on the Social Security Agency February 2005.
1 PROGRESS REPORT ON RECAPITALISATION FET COLLEGES DATE : 21 JUNE 2006.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
Technology Management Services (TMS) CJS/IJS/FSL/ICDMS 13 May 2015.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
Click to edit Master subtitle style 2/16/12 LEASE MANAGEMENT 2011/12 Financial year PRESENTATION TO THE PORTFOLIO COMMITTEE ON POLICE
Themba Wakashe Director - General Department of Arts and Culture 2009 / 10 DIVISION OF REVENUE BILL PRESENTATION TO SELECT COMMITTEE ON FINANCE NCOP 3.
Implementation of the Child Justice Act, 2008 (Act No. 75 of 2008) 23 February 2010.
THUBELISHA HOMES CLOSURE REPORT Presented to the Portfolio Committee on 8 July 2009.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
Briefing: 4 th Quarter Financial Report 2011/12 Vote 25: Police.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
ENROLMENT REPORT: FEBRUARY 2012 Portfolio Committee on Higher Education and Training 15 February 2012.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
1 Presented by Cathy Motsisi Chief Financial Officer Presentation of the Devolution of Property Rates and Taxes Grant to Provinces as at 30 June 2010.
Briefing: 1st Quarter Financial Report 2012/13 Vote 25: Police 1.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES SERVICE LEVEL AGREEMENT 02 June 2010.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
FREE STATE DEPARTMENT OF HEALTH Presentation on the Status of Conditional Grants Public Hearings on Conditional Grants 03 May 2006.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
Public Hearing: 3 rd Quarter Expenditure and budget Implementation Vote 24: Police 1.
BRIEFING TO THE PORTFOLIO COMMITTEE ON AUDITOR-GENERAL MATTERS 1.
Financial and Fiscal Commission
QUARTER 2 OF THE 2015/16 FINANCIAL YEAR
Technology Management Services (TMS)
PRESENTATION TO PORTFOLIO COMMITTEE ON PUBLIC WORKS Medium Term Budget Policy Statement 9 November 2005.
Trevor Balzer: Acting CFO Helgard Muller : CD Water Services
National Department of Health Presentation to the Standing Committee on Appropriations Public Hearings on the Adjustments Appropriation Bill 05 November.
PORTFOLIO COMMITTE PRESENTATION
PROGRESS REPORT ON IMPLEMENTATION OF THE PUBLIC FINANCE MANAGEMENT ACT
Infrastructure Delivery Management Toolkit:
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Select Committee on Finance Water Services Operating and Transfer Subsidy 10 May 2006 Department of Water Affairs and Forestry Jabulani Sindane : DG Trevor.
STRATEGY TO REDUCE CASE BACKLOGS TO THE PORTFOLIO COMMITTEE ON POLICE
Sport and Recreation Infrastructure Programme
DEPARTMENT OF EDUCATION NORTH WEST MID-TERM PROVINCIAL BUDGET REPORT
Progress report on the roll out of GIAMA
Rannoi Sedumo – CFO (Acting HOD) Gilberto Martins – DDG PW
PRESENTATION TO PORTFOLIO COMMITTEE ON DEFENCE AND MILITARY VETERANS ON THE STATUS OF THE DMV INFRASTRUCTURE 08 November 2017 Presented by Mr. M. OZINSKY.
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
National Department of Public Works Immovable Asset Management
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
OVERVIEW OF THE OCJ ANNUAL REPORT FOR THE 2016/17 FINANCIAL YEAR
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Presentation transcript:

Criminal Justice System Modernization Project: DPW’s Infrastructure Projects 24 June

CONTENT 1.Executive Summary 2.Relevant Projects to Criminal Justice System Modernization Programme 2.1 Installation of RI lane at Plattekloof and Arcadia Forensic Laboratories 2.2 Installation of Close Circuit Television (CCTV) 2.3 KwaZulu Natal: Provincial Head: Forensic Laboratory: Revamping of the Case Reception Area 2.4 Gauteng: Silverton: Forensic Science Laboratories (FSL): Chemistry: Refurbishment of Tshwane Lab into Offices 2.5 Gauteng: FSL: LP Neethling Building: Room 412B: Property Code: 45265: Renovations and Installations according to specification for laboratory 2.6 Limpopo: Local Criminal Record Centres (LCRC): Repair and Maintenance Programme: Upgrade and maintain of the following LCRCs  Giyani  Makhado  Kwa-Mhlanga  Secunda 3. Conclusion 2

EXECUTIVE SUMMARY The Department of Public Works (DPW) aims to promote Government objectives by providing and managing accommodation, land and infrastructure needs for user departments. The same role is critical in ensuring that the Criminal Justice System’s (CJS) Modernization Project achieves its objectives. The South African Police Service (SAPS) have identified Forensic Science Laboratories (FSLs) and Local Criminal Record Centres (LCRCs) as key facilities which the SAPS’ Technological Management Services (TMS) have earmarked for the CJS Modernization project. Therefore, the involvement of DPW in terms of delivery of infrastructure requirements is important and specific projects have been identified in this regard. This presentation will provide progress update of all these infrastructure related projects at FSLs and LCRCs and the action plan on projects that are still in progress. 3

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 1) Installation of RI lane at Plattekloof and Arcadia Forensic Science Laboratories Request: SAPS requested approval to execute the project at Plattekloof and Arcadia FSLs Progress Update: DPW granted approval to SAPS on 4 March 2014 to install the RI lanes. The approval was granted after the Mechanical and Electrical Engineers assessed and confirmed that SAPS can be allowed to do the installations. Action Plan None. 4

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 2) Installation of Close Circuit Television (CCTV) at 13 Police Stations Request: SAPS requested approval to execute the project. Progress Update: DPW granted approval to SAPS on 02 December 2014 to install the CCTV only at seven state owned police stations. The rest were leased police stations and approval are required from the landlords. The DPW Regional Offices are finalizing engagements with landlord which will result in addendum to existing lease contracts being effected. Action Plan DPW envisages to have addenda concluded with Landlords for the six following leased FSLs by the end of August 2015 to allow the required CCTV installations to take place; Amanzimtoti, 415 King Rest (Property Code ), Amanzimtoti, Nedbank Building (Property Code ), Pretoria, General Piet Joubert (Property Code 17), Pretoria, Sanlam Plaza (Bothongo Building-Property Code 130), Springs, Alpha Romeo Building (Property Code ) and Witbank, Jelicoe Place (Property Code ) 5

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 3) KwaZulu Natal: Provincial Head: Forensic Laboratory: Revamping of the Case Reception Area Request: SAPS requested approval to execute the project. Progress Update: The DPW Regional Offices are finalizing engagements with the Landlord which will result in addendum to existing lease contract being concluded. Action Plan  The envisaged date for the finalization of an addendum with the Landlord is the end of August 2015 to allow the required project on revamping of the Case Reception Area to be carried out. 6

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 4) Gauteng: Silverton: FSL: Chemistry: Refurbishment of Tshwane Lab into Offices Request: SAPS requested DPW to register the project for execution. Progress Update: The process of determining the actual scope and costs of the project is currently being finalized by Pretoria Regional Office for execution by DPW. As soon as the scope and costs for the project is determined, the Supply Chain Management (SCM) processes will be commenced with. Action Plan  Finalize the project scope by end of July  Provide the Project Execution Plan (PEP) for subsequent project activities by 10 August 2015  Ensure adherence to the timeframe as per the submitted PEP. 7

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 5) Gauteng: FSL: LP Neethling Building: Room 412B: Property Code: 45265: Renovations and Installations according to specification for laboratory Request: SAPS requested DPW to register the project for execution. Progress Update: DPW declined the request by SAPS to execute the project because it is of a capital works nature. This project has to be prioritized for inclusion into the Capital Works Implementation Programme for execution by DPW. Currently, there are 191 capital works projects that are funded for execution by DPW in this financial year (2015/16) and this project is not included amongst these. Action Plan  Pretoria Regional Office is finalizing scope of the project. Target date is 15 July  PEP for subsequent project activities will be ready by 31 July 2015  DPW will monitor and ensure adherence to agreed to timelines. 8

INFRASTRUCTURE PROJECTS: CJS MODERNIZATION PROGRAMME 6) Limpopo: LCRC: Repair and Maintenance Programme: Upgrade and maintain of four LCRCs Request: SAPS requested DPW to incorporate the upgrading and maintenance of four LCRCs in Polokwane to the existing RAMP project (043896). These were;  KwaMhlanga: Mpumalanga  Secunda: Mpumalanga  Giyani: Limpopo  Makhado: Limpopo Progress Update: DPW discontinued RAMP projects hence the four projects could not be incorporated to the existing project. All four projects were then registered as separate projects under WCS numbers & for execution by DPW Regional Offices in Mpumalanga and Limpopo. Action Plan  Project scope and cost estimate will be finalised by end July 2015  DPW will monitor and ensure adherence to agreed to deadline. 9

CONCLUSION The Department of Public Works is in communication with SAPS Facilities Management Division to determine the list of infrastructure projects on FSLs and LCRCs, other than the ones listed above, that are linked to CJS Modernization project. This process will assist in ensuring the Department makes serious improvements in planning and managing infrastructure projects linked to Criminal Justice System Modernization Programme. DPW is aware of how critical these projects are in the entire value chain of the Integrated Criminal Justice System’s value chain (i.e. starting from the reporting of a crime until it is fully dispensed of by the courts and then by DCS), and will ensure that Departmental resources are mobilized accordingly to ensure efficiency in delivering them. The Department will also leverage on services of the Joint Task Teams that have been established between DPW and user departments. 10

Thank you 11