BPM Upgrade Projects Status & Technical Update Bob Webber DOE Review of Tevatron Operations March 2005.

Slides:



Advertisements
Similar presentations
Current Status of Virtual Accelerator at J-PARC 3 GeV Rapid Cycling Synchrotron H. Harada*, K. Shigaki (Hiroshima University in Japan), H. Hotchi, F. Noda,
Advertisements

FNAL Emittance Devices Flying Wires (FW) Sync Lite Ion Profile Monitors (IPM) aah,6/20/2000.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
Tevatron BPM Upgrade Project Manager Overview Stephen Wolbers Tev BPM Technology Choice Review December 16, 2003.
F Tevatron Software Digital Receiver Beam Line Tuner Vic Scarpine Instrumentation Instrumentation Meeting July 13, 2005.
Key Specifications for Tevatron BPM Hardware Architecture Choices Jim Steimel.
ATF2 Q-BPM System 19 Dec Fifth ATF2 Project Meeting J. May, D. McCormick, T. Smith (SLAC) S. Boogert (RH) B. Meller (Cornell) Y. Honda (KEK)
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Instrumentation Specifications July 26, 2001 S. Childress Page 1 NuMI Specifications for NuMI Primary Beam Instrumentation.
Craig Drennan Linac and Booster Beam Diagnostics Proton Source Workshop December 7 and 8, 2010.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
1 FermiLab Recycler Ring BPM Upgrade Based on Digital Receiver Technology R. Webber, J. Crisp, P. Prieto, D. Voy, C. Breigel, C. McClure, M. Mengel, S.
INTRODUCTION  RECYCLER BPM – Original system not adequate to measure beam position precisely. It is being upgraded to meet the required physics precision.
Tevatron BPM System Upgrade Technical Update Bob Webber Run II Luminosity Upgrade Review February 2004.
Horz V1 H1 H2 V2 Pbars in Recycler Ring Stripline Kickers Split Plate Pickups A-B Vertical Digital Damper Vert Recycler Transverse Damper System Similar.
Basic BPM Hardware Theory Jim Steimel. Wall Current Charge in a cylindrical perfectly conducting pipe produces an equal and opposite image charge at the.
Figure 2 gives an overview of the hardware components of the upgraded Main Injector BPM system. The figure shows 2 signal channels which produce one position.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
F Project X Overview Dave McGinnis October 12, 2007.
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
BPM Signal Processing: A Cartoon View Rob Kutschke Oct 13, 2003.
Initial Performance Results of the APS P0 (Transverse Bunch-to-Bunch) Feedback System N. DiMonte#, C.-Y. Yao, Argonne National Laboratory, Argonne, IL.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
The Main Injector Beam Position Monitor Front-End Software Luciano Piccoli, Stephen Foulkes, Margaret Votava and Charles Briegel Fermi National Accelerator.
Jean Slaughter –April 5, 2004 – all experimenters’ meeting Purposes of SDA Store to store monitoring of performance Long term trends Analysis of specific.
Overview: Primary Sensitivities Nov S. Childress Page 1 NuMI Overview: NuMI Primary Beamline Sensitivities NuMI requirements are for a very large.
The ATF Damping Ring BPM Upgrade Nathan Eddy, Eliana Gianfelice-Wendt Fermilab for the ATF Damping Ring BPM Team.
Proposal for LHC Microwave Schottky Pickups Ralph J. Pasquinelli 3/9/2005.
F Beam Line Tuners Vic Scarpine Instrumentation DoE Review Oct 28-31, 2002.
TeV BLM Review 4/19/041 Tevatron BLM Review - Schedule BLM Replacement Prototype schedule: Provide prototype digitizer cards, crate, readout path by ~
S. Pordes - to part of CD 09/10/031 Introduction to some Beams Division jargon in some order…see how far we get:
Beam Line BPM Filter Module Nathan Eddy May 31, 2005.
Multibunch beam stability in damping ring (Proposal of multibunch operation week in October) K. Kubo.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
18 December 2007 ATF Damping Ring BPM System Upgrade Joe Frisch, Justin May, Doug McCormick, Janice Nelson, Tonee Smith, Mark Woodley (SLAC) Charlie Briegel,
Fermilab February 17, 2003Recycler BPM Front-end1 Duane C. Voy
Beam stability in damping ring - for stable extracted beam for ATF K. Kubo.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Simultaneous Position Measurements of Protons and Anti-Protons in the Tevatron R. K. Kutschke †, J. Steimel, R.Webber, S. Wolbers, Fermilab*, Batavia,
Proton Planning – Major Projects, Schedule, Decisions, and Projections Eric Prebys FNAL Accelerator Division.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
Proton Source Improvement Workshop Cogging W. Pellico Dec 6&
TeV BPM Review 12/16/2003 Summary Status, Motivation, and Directions.
Craig Drennan Linac and Booster Beam Diagnostics Proton Source Workshop December 7 and 8, 2010.
RECYCLER REQUIREMENTS FOR THE RECYCLER RING & ASSOCIATED TRANSFER LINES BPMs Brajesh Choudhary for the MI Dept.
Specifications of Tevatron BPM Upgrade Jim Steimel.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Craig Drennan Linac and 400 MeV BPMs January 7, 2011.
9/2/2003Tev BPM requirements1 Tevatron BPM and BLM requirements Mike Martens.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Beam time structures 1 At any particular instance of time there will be only one kind of beam in the MI. It will be either protons or anti-protons. The.
12/16/03Tev BPM requirements1 Tevatron BPM requirements Mike Martens.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Projects, Tools and Engineering Patricia McBride Computing Division Fermilab March 17, 2004.
BPM Signal Processing: A Cartoon View Rob Kutschke Oct 13, 2003.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
Tevatron Beam Position Monitor Upgrade Stephen Wolbers (for the Tevatron BPM Upgrade Project) PAC05, Knoxville, TN May 16-20, 2005.
F Project X: Recycler 8.9 GeV/c Extraction D. Johnson, E. Prebys, M. Martens, J. Johnstone Fermilab Accelerator Advisory Committee August 8, 2007 D. Johnson.
S. Smith LCLS Facility Advisory October 12, Beam Position Monitors Facility Advisory Committee October 12, 2006.
A Survey of TBT Capabilities of the Upgraded TeV BPMs Rob Kutschke, CD/EXP Tevatron Department Meeting February 18, 2005 Beams-doc-1583-v2.
A Survey of the Capabilities of the Upgraded TeV BPMs Rob Kutschke, CD/EXP Run II Meeting March 24, 2005 Beams-doc-1752-v2.
SDA- Shot Data Analysis Jean Slaughter DOE Review July 21, 2003.
Beam Current Monitoring with ICT and BPM Electronics
Presentation transcript:

BPM Upgrade Projects Status & Technical Update Bob Webber DOE Review of Tevatron Operations March 2005

BPM Projects - DoE Tevatron Operations Review - March Webber2 Recent and Active BPM Projects  Recycler Ring  Completed and operational since early 2004  NuMI Beam Line  Completed and operational since first NuMI extracted beam  This system reported meaningful beam position data on first pulse !!!  Tevatron Ring ( ) (9/2/03 – 5/17/05) ($1081K labor, $1764K m&s)  Installed and operational for routine proton measurements in ~25% of the ring; functioning compatibly with remaining old systems  Completion of installation scheduled by end of May 2005  Antiproton Transfer Lines ( ) (3/26/04 – 7/25/05) ($91K labor, $284K m&s) (details in Elvin Harms’ Rapid Transfer Talk earlier this breakout)  In final design stage, manpower assigned, ~80% procurements done  Will employ NuMI/Recycler software and Tevatron EchoTek boards  Completion expected by ~August ’05  Main Injector Ring ( ) (1/3/05 – 6/1/06) ($324K labor, $900K m&s)  Requirements being reviewed  Awaits manpower currently devoted to Tevatron and Transfer Line projects  All systems are built around a common commercial (Echotek) digital receiver board

BPM Projects - DoE Tevatron Operations Review - March Webber3 Tev BPM - General Status  Cooperative activity between Computing and Accelerator Divisions, CD has provided ~80% of total project effort  Essentially all hardware is in hand, including spares  Considerable planning and care allow adiabatic installation without adversely impacting Tevatron operations  It is a big deal to seamlessly replace a large operational system without disrupting Collider operation and luminousity production  7 of 27 systems are installed and routinely operational for proton measurements (functional replacement for old systems)  Antiproton position measurements have been demonstrated but not yet routinely operational  Installation pace is presently limited ~equally by:  Opportunity -- we don’t install during a Collider store  Debugging –- operational problems must be solved as they are discovered

BPM Projects - DoE Tevatron Operations Review - March Webber4 TeV BPM - Software  ~85% of required VME front-end software functionality has been implemented and debugged  Data is packaged, either in VME front-end or in ACNET BPMLIB library code, to “look like” data from the old BPM system so as to minimize modifications to legacy console applications  Software switch permits transparent operation with mixture of old and new BPM systems in field  Critical legacy console applications are working with new BPM data after little or no modification  Some new applications are being developed to take advantage of the system’s new capabilities  SDA is being updated to use the new BPM data as each new crate is installed

BPM Projects - DoE Tevatron Operations Review - March Webber5 TeV BPM - Colored Pictures! A3 House Installation BPM Integrity Check

BPM Projects - DoE Tevatron Operations Review - March Webber6 TeV BPM – 36 Bunch Closed Orbit Resolution Upper Limits 20 minutes of closed orbit data for A3 BPMs 400 microns full vertical scale all plots Histograms of same data and RMS variation from the mean

BPM Projects - DoE Tevatron Operations Review - March Webber7 TeV BPM – 36 Bunch Closed Orbit Resolution Correlation plot of closed orbit data from two BPMs on opposite sides of ring estimate resolution to be ~5 microns

BPM Projects - DoE Tevatron Operations Review - March Webber8 Tev BPM – Single Proton Bunch TBT Measurements TBT resolution is better than 50 microns RMS

BPM Projects - DoE Tevatron Operations Review - March Webber9 TeV BPM - Antiproton Measurement “Plan A”  Establish cross-talk (imperfect pickup directionality) coefficients a, b, c and d and compute corrected antiproton signals according to:  Now working to establish unique coefficients for each BPM and cope with operational maintenance of time varying values  There is a “Plan B” … BPM ApAp ProtonsPbars A pbar B pbar BpBp

BPM Projects - DoE Tevatron Operations Review - March Webber10 TeV BPM – Antiproton Measurements Proton sum signal Proton position Pbar positionPbar sum signal Pbar sum signal during proton loading (ideally zero) Proton loading Pbar loading Ramp

BPM Projects - DoE Tevatron Operations Review - March Webber11 TeV BPM - What’s Left  Solve currently known bugs  Intermittent first turn/injection turn-by-turn (phase/timing problem)  Complete hardware installation  Implement and test additional required functionality  Robustness of Pbar measurements  “Safe” mode (timing robust first turn measurements)  Calibration-scaling-offset database  Produce as-built drawings and documentation  MOU -> operations  Project closeout

BPM Projects - DoE Tevatron Operations Review - March Webber12 Transfer Line BPM  First system required to observe both 53MHz and 2.5MHz beam structures  Major impact on design and required dynamic range of analog circuitry upstream of digital receiver boards  Precursor to MI BPM system with similar requirement  Operational scenarios are complicated due to different beam structures down parts of beam lines at different times  Recycler/NuMI front-end software that is suited mode switching and cycle dependent data buffers will be used  Design of analog circuit is in final prototype stage  All major procurements except analog boards are complete  VME front-end software is ready and waiting  Prototype/development system now installed at F23  Schedule calls for completion mid to late summer 2005 – integration will be subject to operational constraints

BPM Projects - DoE Tevatron Operations Review - March Webber13 Main Injector BPM Project  This project will follow on the heels of the currently Tevatron and Transfer Line BPMs  Scope  Replace signal processing electronics and front-end data acquisition systems for ~208 beam position monitors located around the Main Injector and in six buildings  Objectives  Eliminate obsolete Multibus II hardware and ACNET communications protocol  Accommodate measurement of beam in 2.5MHz RF buckets  Provide improved measurement resolution  Beams Document #471, dated February 2003, specifies system requirements and is now under review by Main Injector Department

BPM Projects - DoE Tevatron Operations Review - March Webber14 Main Injector BPM - Similarities to Tevatron BPM  General system design and implementation  Beam information to be obtained and types of measurements, i.e. first turn, closed orbit, and turn-by-turn  Anticipated hardware, except more complicated analog circuitry upstream of digitizer  Scope of DAQ, on-line, and off-line software, although different in detail

BPM Projects - DoE Tevatron Operations Review - March Webber15 Main Injector BPM - Differences from Tev -- All in the Details  Main Injector operating cycles are more varied in type than in Tevatron and dynamically interwoven in time  Both 2.5MHz and 53MHz signal frequencies must be processed (in different Nyquist bands)  Measurement data for multiple operating cycle types is to be stored separately in parallel front-end data buffers  Both protons and antiprotons must be measured, but  Do not circulate simultaneously (but fine timing is different)  Pickups are not directional not separate p/pbar cables protons and pbars require different fine timing  Measurement of user selectable segment (batch) of the circulating beam is required

BPM Projects - DoE Tevatron Operations Review - March Webber16 Main Injector BPM - Anticipated Implementation  Analog front-end electronics will leverage heavily off Transfer Line BPM project (common requirement to deal with 2.5MHz and 53MHz signal frequencies)  VME and VXWORKS front-end DAQ systems as other new systems  Tevatron style EchoTek digital receiver boards  Tevatron style digitizer clock and timing boards  Front-end software probably dependent on what group implements the system (different in detail from both Tevatron and Recycler)

BPM Projects - DoE Tevatron Operations Review - March Webber17 Main Injector BPM - How Project Likely Plays Out  Little dedicated effort up to now other than clarification and refinement of requirements  MI department occupied with NuMI commissioning  BPM people occupied with the other new BPM systems  Analog front-end design will flow from Transfer Line project  Most people who provided engineering, software, and technical support for NuMI BPM will focus on Transfer Line project through ~May ’05  Software support from Tevatron project might become available in ~June ’05  Commodity procurements can begin any time (EchoTek boards already procured and in hand)  A development system initially with either Tevatron or Recycler software should be installed in MI by June 2005  Computing Division will likely play a major role in the project

BPM Projects - DoE Tevatron Operations Review - March Webber18 BPM Projects - Summary  We are mid-stream in the effort of re-building all major BPM systems in the accelerator complex except Linac and Booster  Results from completed systems in Recycler and NuMI and partially installed systems in Tevatron show excellent performance and operational credibility and utility  Considerable effort remains to:  Complete Tevatron system  Overcome analog signal challenges for Transfer Lines and Main Injector  Meet the diverse and dynamic functional requirements demanded in Main Injector

BPM Projects - DoE Tevatron Operations Review - March Webber19 BACKUP SLIDES  #1577 B3 resolutions  1571 coupling  1581 pbars  #1752 for Rob’s most recent very good talk

BPM Projects - DoE Tevatron Operations Review - March Webber20 Antiproton Measurements  Present ratio of proton to antiproton intensities combined with directivity of stripline pick-up produces residual proton signals at the antiproton port about 50% the amplitude of antiproton signals  When antiproton intensities increase they will begin to “contaminate” the proton signals also  We opt to not pursue p/pbar separation by precise timing Typical signal from pbar end of BPM for present bunch intensities 80 nsec/tic Pbar bunch signal Undesired Proton bunch signal

BPM Projects - DoE Tevatron Operations Review - March Webber21  Separate p/pbar signals with relaxed timing requiring precision and maintenance of ~50 nsec rather than ~5 nsec  Observe only “isolated” proton or antiproton bunches at ends of 12-bunch trains  No pbar bunches observable One pbar bunch observable  Five bunches observable Two bunches observable Antiproton “Plan B”

BPM Projects - DoE Tevatron Operations Review - March Webber22 Coverage of Ring in Antiproton “Plan B”  Locations with at least one clear pbar bunch (at least 400 nsec from nearest proton bunch) at various times in cycle  x axis is feet around ring from B0, each point is BPM location  y axis is clearance >21 is “clear”

BPM Projects - DoE Tevatron Operations Review - March Webber23 HA15 and VA14 P/Pbar Positions “Plan B” Changing Separators Horizontal Pbar Horizontal Proton Vertical Proton Vertical Pbar Position Scales 2mm/box

BPM Projects - DoE Tevatron Operations Review - March Webber24 Horizontal A15 Helix Change and Pbar Loss “Plan B”

BPM Projects - DoE Tevatron Operations Review - March Webber25 Block Diagram Cartoon of Signal Path  Note that proton and pbar signal paths from same half of BPM are directly connected together by the stripline --- reflections from one will feed directly into the signal of the other attenuator53MHz BPF Eight Channel VME Digital Receiver Proton Inside attenuator53MHz BPF attenuator53MHz BPF Proton Outside Pbar Outside attenuator53MHz BPF Pbar Inside VME CPU ACNET Diagnostic and Calibrate Signals

BPM Projects - DoE Tevatron Operations Review - March Webber26 Main Injector BPM - Possible Roles for Computing Division  Total effort level would be between that provided for Recycler and Tevatron BPM Projects Less engineering design effort than in Tevatron project  Administrative project management  Analog circuit board layout and fabrication based on AD designs  Support for procurement, incoming component inspections and testing, production testing, equipment tracking, etc.  Supply Tevatron BPM style timing boards  DAQ, on-line, and off-line software components after successful completion of Tevatron system  Installation manpower  To serve all these roles, CD effort estimated as on the scale of 60 FTE months  Learning curve (AD language, machine operational issues, ACNET) has already been largely traveled by CD personnel on Tevatron project  Details will be different

BPM Projects - DoE Tevatron Operations Review - March Webber27 BPM Accuracy/Resolution Specs This is Table 2 from Requirements document. Table gives the most stringent requirements on the system; for certain types of operation these requirements are relaxed. Note: resolutions are stated as 3 sigma. Key Specifications (Protons): Measurement Range:  15mm Absolute Position Accuracy: < 1.0 mm Long Term Position Stability: < 0.02 mm Best Orbit Position Resolution: < 0.02mm (0.3 sec averaging) Position Linearity: < 1.5% Relative Position Accuracy: < 5% Intensity Stability: < 2% Key Specifications (Pbars)_: Measurement Range:  15mm Absolute Position Accuracy: < 1.0 mm Long Term Position Stability: < 0.02 mm Best Orbit Position Resolution: < 0.05mm (0.3 sec averaging) Position Linearity: < 1.5% Relative Position Accuracy: < 5% Intensity Stability: < 2%

BPM Projects - DoE Tevatron Operations Review - March Webber28 Demonstrated Beam Measurements  Recycler-type BPM front-end is set up for development and tests in TeV House A1  Connects to both Proton and Pbar signals of one horizontal BPM and one vertical BPM  Interfaced to ACNET with small subset of ultimate required functionality  Closed orbit and turn-by-turn measurement performance have been demonstrated  In use to assess narrowband frequency domain p/pbar signal de-convolution  Will soon demonstrate “wide” time separation of Protons and Pbars (utilize isolated bunches at the ends of the otherwise over-lapping 12-bunch trains); ~50 rather than ~5 nsec timing

BPM Projects - DoE Tevatron Operations Review - March Webber29 Proton Positions in Load of Store #3172: Old vs New Old: rms error ~140 um for uncoalesced beam, ~70 um for coalesced beam, and 0.6 mm “step” between the two New: rms error ~25 um for uncoalesced beam, <9 um for coalesced beam, no “step” between the two

BPM Projects - DoE Tevatron Operations Review - March Webber30 Closed Orbit Resolution During Proton Loading Green: Vertical 100 microns/div showing ~10 micron resolution and orbit changes due to leakage fields in ramping injection Lambertson magnet Red: Beam Intensity showing proton bunches loading Yellow: Time in Supercycle

BPM Projects - DoE Tevatron Operations Review - March Webber31 Upper Limit of Closed Orbit Resolution Average of standard deviations for twelve five-minute intervals First one-hour intervalSecond one-hour interval ± mm ± mm Two one-hour periods of 1 KHz bandwidth proton position measurement data, 17 hours apart, in store #3148. (data-logged at 1 Hz) 50 microns / vertical division Demonstrates upper limit resolution of 9 microns rms in 1 Khz (any real beam motion not excluded) to meet spec of 7 micron 1 sigma in ~10Hz

BPM Projects - DoE Tevatron Operations Review - March Webber32 Injection Turn-By-Turn --- Un-coalesced Protons Vertical A14Horizontal A15 vertical axis units are millimeters in all plots vertical tune horizontal tune

BPM Projects - DoE Tevatron Operations Review - March Webber33 Turn-by-Turn Long After Injection Single Coalesced Bunch Vertical A14Horizontal A15 vertical axis units are millimeters in all plots Horizontal transverse motion due to persistent synchrotron oscillation

BPM Projects - DoE Tevatron Operations Review - March Webber34 Upper Limits on TBT Resolution --- Vertical A14 If remove betatron and synchrotron motion by zeroing 17 frequency line amplitudes around betatron frequencies and one at synchrotron frequency, leaving untouched 494 of the original 512 frequencies, TBT resolution is found to be 15 microns Standard deviation of raw data is 34 microns

BPM Projects - DoE Tevatron Operations Review - March Webber35 Same Coalesced Proton Bunch Given Big Vertical Kick Vertical A14Horizontal A15 vertical tune horizontal tune vertical tune

BPM Projects - DoE Tevatron Operations Review - March Webber36 Antiproton “Plan A”  Model BPM as an 8-port network at processing frequency  Measure network transfer functions with beam, e.g. ratio of proton signal on pbar end to proton signal on proton end  Measure signals then correct according to pre-determined transfer function before computing positions  Measurements in process to determine achievable accuracy Linear System P Upper In P Lower In Pbar Upper In P Upper Scope InRefl InRefl InRefl InRefl Pbar Upper Scope P Lower Scope Pbar Lower Scope BPM ApAp ProtonsPbars A pbar B pbar BpBp