MKD dust related actions Viliam Senaj Technical Coordination Meeting 27/01/2015.

Slides:



Advertisements
Similar presentations
Inspection & Preventive maintenance of breakers
Advertisements

Delayed Coker Unit Savings Best Practice. Delayed Coker Heater Tube Skin Temperatures. Delayed Cooker Units have heaters with tube skin thermocouples.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
MKDV switch faults November V. Mertens L. Ducimetière with H. Bartosik, G. Bellotto, C. Boucly, P. Burkel, E. Carlier, D. Comte, S. Huon,
Rule Based Systems Michael J. Watts
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 28 July 2003 Sam Burke UCSB HEP Group.
David Nelson STAVE Test Electronics July 21, ATLAS STAVE Test Results Version 1 David Nelson July 21, 2008.
LHC Beam Dumping system
TS2-SPS & TS1-LHC. TS2-SPS (On Monday 15th of June for 24hrs) SPS – HW: Replacement of HV Switch PFN 7 MKP (Impact 65420) SW: « Smooth » upgrade in accordance.
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 21 July 2003 Sam Burke UCSB HEP Group.
FHCT SEB cross-section measurements at H4IRRAD and with cosmic rays and its influence to LHC abort system reliability Viliam Senaj RadWG meeting 04/10/2011.
Exponential Notation Significant Figures
MKD stack upgrade MKD generator meeting Viliam Senaj 23/06/2015.
Test of the high voltage strength of Pelletron’s gas insulation (18-Dec-2008) Recycler Meeting January 21, 2009 A. Shemyakin.
LBDS commissioning – MKD tests Viliam Senaj, 11/12/2013.
Solid-state based 60 kV 15 kA switch for the SPS vertical beam dumping kicker magnet L. Ducimetière, P. Faure, V. Senaj.
Learning, our way Examples of bad installation. CONTENT Installation related examples Installation related examples Application related examples Application.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
This presentation will cover your LCD screen with several solid colors, one at a time. This makes it fairly easy to see stuck (always on or off) pixels.
Product Programming Switches Echoflex’s products are a combination of unique transmitters and controllers/receivers that need to be learned to each other.
Proposed LHC beam dumping kicker generator modifications for LS2 TE-TM Meeting Viliam Senaj 07/07/2015.
Setting up the Ricoh C305 Press F5 to start the Presentation
LIBD on LBDSmeeting Viliam Senaj 04/02/2014. MKB test MKB vacuum level satisfactory for beginning of HV test: – B1: between 3.1x10 -7 and 5.7x10 -7 (new.
Vertical deflection system: * The function of the deflection system provides an amplified signal of the proper level to derive the vertical deflection.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
7/2/2003Ivan Hruska,Francisca Calheiros1 Radiation test of components for LV power supply design  Test done in PSI verification and selection.
1 HER Arc RF seals M. Sullivan MAC Review Oct , 2006 Status of HER Arc RF Seals M. Sullivan For the PEP-II team Machine Advisory Committee Review.
TF5 – Status report on thermal propagation EVS-GTR 9 th IWG meeting Changchun, China 2015/9/17.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
MKD Reliability run Viliam Senaj TCM meeting 18/11/2014.
LG, 15 March 2007 ATB work for 2007 run1  Repair of ‘guillotine valves’  Repair converter (just after T4 TAX – quite radioactive !)  Invert order of.
Beam Line BPM Filter Module Nathan Eddy May 31, 2005.
Sketching Basic Kicker System Parameters W. Bartmann, T. Fowler, B. Goddard, T. Kramer.
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
LHC Beam Dumping System Experience from reliability run and Re-commissioning procedures MPP Nicolas Magnin – TE/ABT/EC.
TECHNICAL ANALYSIS. PRICE PATTERNS A typical price cycle has three trends: up, sideways, and down. The sideways trend is essentially a horizontal or.
Replacement of Obsolete/Old Hardware L. Ducimetière SPS Consolidation Review Luc Sermeus, Mike Barnes, Viliam Senaj, Thomas Kramer, Luis Feliciano, Vasco.
System Restore BCIS 3680 & BCIS Better Safe than Sorry  Before installing programs used in this course (NetBeans, MySQL, etc.), it’s highly recommended.
SBDS – MKDV/H: The new MKDV Generator and additional Magnet for BA5 installation V. Senaj, L. Ducimetière November 20 th 2015.
Technology Department 7 May 2015A.Adraktas1 MKD 3D field calculations A. Adraktas Acknowledgments: V. Senaj MKD meeting, 7 May 2015.
Technology Department 2 April 2015A.Adraktas1 MKD 3D field calculations A. Adraktas Acknowledgments: V. Senaj MKD meeting, 2 April 2015.
Thesis: Introduction Study for a failsafe trigger generation system for the Large Hadron Collider beam dump kicker magnets prepared by Martin Rampl.
ORBUMP Power Supply... 16x3 SCR’s Pulse Forming Network (PFN) - looks like a very slow transmission line. Flat top ~ (10 usec)*(number of cells). Reduced.
FHCT SEB cross-section measurements at H4IRRAD and consequences for MKD reliability Viliam Senaj LIBD meeting 24/01/2012.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
PAST STATE  The high intensity of the solar radiation through the roof increases the warming-up in the hall over 30 °C = 86 °F  The high internal temperature.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
LBDS YETS activity report Viliam Senaj MKD meeting, 19/01/2016.
MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014.
Module Loading Task Force Meeting October 21, 2004
Proposition of MKD & MKBH modification with the goal to reduce maximum voltage (and risk of erratic) Viliam Senaj, 05/05/2017.
LHC beam dump 7.56 TeV operation
Fast High Current Thyristor SEB test
LHC Beam Dumping System Reliability Run Summary
MKD/MKB Review Meeting Scope and Definition
Aachen Status Report: CO2 Cooling for the CMS Tracker
Viliam Senaj MKD meeting 23/05/2017
Overview of LBDS related tasks
FCC hh dump kicker - switch topologies and impact on beam
Noise analysis of the 1m3 DHCal test beam
LPI Moscow, K. Zhukov, MEPhI-LPI Moscow, V. Kantserov
Heating of ALFA detectors
Appliance Repair A to Z
How To Fix A Jam Error When Paper Is Not Stuck In Xerox Printer
Aachen Status Report: CO2 Cooling for the CMS Tracker
10/12/2019.
Presentation transcript:

MKD dust related actions Viliam Senaj Technical Coordination Meeting 27/01/2015

Erratic of 2 nd family on MKD A/B2 on 18/01 at 6.5 TeV Presence of some amount of dust inside generators MKD confirmed (B1: B+N; B2: A+B+N+O) Cleaning – delicate Incorrect cleaning - worse Done during WE /01/2015: – Conditioning up to 6.8 TeV – OK – 1 ES up to 7.1 TeV – OK Plan: – TeV (cycle test) – If problem again on A/B2 – replacement – If problem on more generators – cleaning of all of them – Otherwise waiting with cleaning till confirmation of possibility to cover the perforation (overheating?) to obtain “dust proof MKD rack” Cleaning strategy

Dust proofing the MKD Reliability run in 2008 – with side panels non-perforated Perforated panels installed at the beginning of 2009 (cooling reason?) Temperature stabilisation (Peltier module) added to the GTO stack compartment during the same period Self triggering started in July 2009 To avoid dust penetration – blinding of perforation Test of temperature rise inside “Main capacitor compartment” with perforation blinded – ongoing in 867 Certain temperature rise expected with some influence to a pulse current value: main capacitor temperature dependence ~ ppm/K; +10 deg ~ % of Imax1 Temperature rise so far observed (after 3h at 2 TeV) ~ + 3 deg ~ % on Imax1 (in reality no visible change of magnet current)