1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs.

Slides:



Advertisements
Similar presentations
The Challenge to Install 1,300 New Water Meters. Scope Install electromagnetic meters (mostly) + telemetry + solar power ~700 sites in Upper Murray Valley.
Advertisements

SCO 3 Crewing Optimization As-Is Processes January 9, 2006
1 RIC 2009 Construction Inspection Program Glenn M. Tracy, Director Division of Construction Inspection and Operational Programs March 11, 2009.
Project Selection Overview By Tim Washington September 14 th, 2011.
DOE OFFICE OF INDIAN ENERGY Step 4: Project Implementation 1.
NREP 2009 Emergency Preparedness and the New Reactor Licensing Process: An Update on Where We Are Now Dan Barss Division of Preparedness & Response Office.
Contractor Safety Management
> NRC Regulatory Information Conference March 12, 2009 AREVA NP Inc. 2 AREVA Perspectives on the Containment Sump Design and Downstream Effects for U.S.
INSAG DEVELOPMENT OF A DOCUMENT ON HIGH LEVEL SAFETY RECOMMENDATIONS FOR NUCLEAR POWER Milestone Issues: Group C. Nuclear Safety. A. Alonso (INSAG Member)
Licensing Options for the First US Demonstration Fusion Power Plant S. Abdel-Khalik ARIES Meeting, San Diego (February 3, 2008) G. W. Woodruff School of.
Define ● Deliver ● Sustain Sundar Chellamani Technical Director SysComm Project Management Ltd.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.7 Commissioning Geoff Vaughan University of Central.
Managing Risk to Reduce Construction Claims (And Improve Project Success) Presented by Laurie Dennis, PE, CVS-Life, FSAVE.
© 2008 Prentice Hall11-1 Introduction to Project Management Chapter 11 Managing Project Execution Information Systems Project Management: A Process and.
Project Execution.
Product Lifecycle Management Cost of Quality Pasi Kaipainen, Mika Huhta.
Release & Deployment ITIL Version 3
MPMP Power Supply 1 Nuclear Power Update for The Society of American Military Engineers September 15, 2010.
Effective Methods for Software and Systems Integration
Unit Introduction and Overview
Complete and Integrated Lifecycle Management. Challenges 1.
MethodGXP The Solution for the Confusion.
Copyright 2005 Welcome to The Great Lakes TL 9000 SIG TL 9000 Requirements Release 3.0 to Release 4.0 Differences Bob Clancy Vice President, BIZPHYX,
1 “Lessons Learned - Construction of the National Enrichment Facility” Stephen Cowne Director, Quality & Regulatory Affairs Louisiana Energy Services (LES)
The New Reactor Program Process, Progress, and Plans (And a Peek Over the Horizon) December 2, 2009 David B. Matthews, Director Division of New Reactor.
Quality Assurance Program National Enrichment Facility Warren Dorman September 19, National Energy and Environmental Conference.
1 The U.S. NRC’s Reactor Certification and Licensing Process – Meeting the Challenge? Commissioner Peter B. Lyons U.S. Nuclear Regulatory Commission 15.
1 Attributes of a Successful Nuclear Construction Project – A Regulator’s Perspective Victor M. McCree Deputy Regional Administrator for Operations U.S.
1 © 2012 Westinghouse Electric Company LLC. All Rights Reserved.Westinghouse Proprietary Class 3 The Incorporation of the Utilities Input into the Design.
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
1 Information Handover at UniStar Lessons Learned Presented By: Bob Renuart UniStar.
Configuration Management in New Reactor Construction Tom Kozak, NRO/DCIP/CAEB
1 RIC 2009 Construction Inspection Program Glenn M. Tracy, Director Division of Construction Inspection and Operational Programs March 11, 2009.
1 RIC 2009 Construction Inspection Program Loren R. Plisco Region II March 11, 2009.
New Nuclear Generation Ellen Ruff President, Duke Energy Carolinas.
PAGE 1 New Plant - CM Configuration Management For The Next Generation Of Nuclear Facilities Joseph Burack Consulting Engineer Configuration Management.
Project Licensing Status Jim Kinsey Director, Regulatory Affairs NGNP Project.
New Reactor Construction Inspection
Configuration Management of Post-Fukushima Regulations CMBG June 2013 David Gambrell Director, Severe Accident Management Southern Nuclear.
New Reactors: Licensing Basis and Configuration Mgmt Challenges June 22, 2010 David B. Matthews Director Division of New Reactor Licensing Office of New.
ANSI-NIST Nuclear Energy Standards Coordination Collaborative David Matthews, Director, Division of New Reactor Licensing Larry Burkhart, Chief, AP1000.
New Reactor Licensing R. William Borchardt Director, Office of New Reactors US NRC February 19, 2008.
A Mid-Process Review Marilyn C. Kray Vice President, Exelon Generation President, NuStart Energy Development Regulatory Information Conference March 10,
NPP Vendors Perspectives TM/WS Infrastructure Development 9-12 February 2010 Breakout session – Group 4.
RIC 2009 Construction Inspection Program: Industry Perspectives Russ Bell Director, New Plant Licensing March 11, 2009.
1 RIC 2009 NRO New Reactor Design Reviews and Engineering Jennifer Dixon-Herrity USNRC/NRO/DE March 11, 2009.
1 RIC 2009 Design Acceptance Criteria: Searching for Acceptance Andrea Sterdis Tennessee Valley Authority March 11, 2009.
RIC 2009 Human Factors DAC/ITAAC Reviews Michael Junge USNRC/NRO/DCIP March 11, 2009.
LECTURE 5 Nangwonvuma M/ Byansi D. Components, interfaces and integration Infrastructure, Middleware and Platforms Techniques – Data warehouses, extending.
PRIIA 305 Technical Subcommittee Systems Engineering Processes for Passenger Equipment Acquisition and Life Cycle Support Presented at: NGEC Executive.
Installation and Commisioning SE view point Romuald Duperrier ESS SE manager.
Prof. Shrikant M. Harle.  The Project Life Cycle refers to a logical sequence of activities to accomplish the project’s goals or objectives.  Regardless.
Principal Investigator ESTCP Selection Meeting
Product Lifecycle Management
Commissioning & Startup
Knowledge-centric Plant Information Model
Principal Investigator ESTCP Selection Meeting
Flooding Walkdown Guidance
Mitigation of Beyond Design Basis Events (MBDBE) Rule Implementation
NRC Cyber Security Regulatory Overview
Introduction to Software Testing
Vogtle 3&4 Configuration Management
Regulatory Oversight of HOF in Finland
Considerations on the Reference Plant Concept
Anna Bradford, Deputy Director Division of New Reactor Licensing
Principal Investigator ESTCP Selection Meeting
PSS verification and validation
NGEC Executive Board Meeting
Principal Investigator ESTCP Selection Meeting
Presentation transcript:

1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

2 Discussion Topics UniStar Current Status of the EPR USEPR Owners Group EPR Fleet Experience Feedback ITAAC (Inspections, Tests, Analyses Acceptance Criteria)

 Like-minded owners  Shared resources  Shared generic development costs  Standardized fleet  AREVA’s U.S. EPR technology UniStar: Generic DDE Licensing (DCD, COLAs) Equipment procurement Construction best practices Operating procedures Simulator and training development Communications programs Cost Optimization:

4 UniStar Business Model Principles Standardization –Use FL-3 design criteria for control room, MMI and TG/BOP design –Use EDF planning, construction, startup and operating experience and procedures –Maximize the use of real time OL-3 and FL-3 lessons learned –Create processes to maintain fleet standardization in all project phases Risk Mitigation –Levelize the most controllable portions of overnight capital costs (paper and procurement) –Risk management improves as fleet size grows Flexibility –Provide the tools and procedures needed by owners in licensing, EPC and operations of the Fleet –Operate U.S. EPRs as a standardized fleet, through the entire plant lifecycle

5 UniStar Project Timelines COL Issued COD Construction begins Calvert Cliffs3 - MD Nine Mile Point - NY Callaway - MO Bell Bend - PANew Project

Current Status of the EPR

7 EPR in Finland: Olkiluoto 3

MAY 2006 MAY 2007 MAY 2008

EPR TM in China Artist rendering of Taishan site with four EPRs January 2009 – Taishan construction site

10 New EPRs Penly 3 Status –Electricite de France and GDF Suez welcomed the announcement of a second French EPR, to be built in partnership at the Penly nuclear power plant site on the Channel. Potential additional EPR in France (3 total by 2020)

11 EPR Owners Group Each EPR project belongs to a worldwide community What affects one of us will impact all of us We need an organization and a means to communicate

12 EDF to UniStar FA3/OL3 Lessons Learned Transfer Process

13 How ITAAC Fits Into Commissioning Tests Integrated Test Program Pre-operational Tests (includes ITAAC) Initial Fuel Load and Pre-critical Tests Initial Criticality and Low Power Physics Tests Power Ascension Tests Other Tests Performance Tests Demonstration Tests Initial Surveillance Tests Component/Equipment Tests Systems Tests ITAAC* SSC Inspections, Tests and Analysis Non-SSC Inspections, Tests and Analysis Required prior to Fuel Load * Inspection, Test, Analysis, Acceptance Criteria

14 Current ITAAC Challenges There are currently ITAAC which will require detailed plans for execution, scheduling, documentation, and NRC notification = collaborative effort NRC review and approval of ITAAC in the DCD is not yet complete and will likely result in comments. Configuration Management of completed/inspected ITAAC is yet to be developed. ITAAC delays during construction and/or testing could impact the fuel load schedule, and Commercial Operation Date.

15 Objectives of an ITAAC Program: The ITAAC process should take advantage of current processes/programs (i.e., QA Program, Pre-Op Test Program) “Book of ITAAC” –Detailed description and definitions for each ITAAC –Execution Plan including methodology & closure criteria –Sequence and Schedule –Ensure the Schedule is shared with the NRC so independent verification and validation is ensured

16 Objectives of an ITAAC Program: ITAAC results should not result in unexpected NRC findings. ITAAC inspections hopefully will not impact the construction schedule. ITAAC information and Project Schedule should be provided to the NRC in a proactive manner to avoid impacts on schedule. Owners should have a close working relationship with the NRC in order to establish and implement the ITAAC process. Experience from the industry will be shared – NRUG concept