14 May 2009Hans Postema - CERN CMS Upgrade Workshop Tracker Phase I upgrades 14 May 2009 1.

Slides:



Advertisements
Similar presentations
24 April 2009Hans Postema - CERN Tracker Upgrade meeting CO2 cooling tests and progress.
Advertisements

1 Ann Van Lysebetten CO 2 cooling experience in the LHCb Vertex Locator Vertex 2007 Lake Placid 24/09/2007.
24 June 2010 Immanuel Gfall (HEPHY Vienna) CO 2 Cooling for PXD/SVD IDM Meeting.
Cooling Update (May 2011) Tim. Overview From last time – Estimate Power Loads Active components Extraneous heat sources – Develop methodology for exploring.
CO2 cooling pressure drop measurements R. Bates, R. French, G. Viehhauser, S. McMahon.
CO 2 return pressure drop budget and pipes from PP2 to tracker Georg Viehhauser.
CMS FPIX Cooling Prototype Phase One Estimate and Conceptual Design R. L. Schmitt 10/28/2009.
Overview of basic issues.   The design of the (Outer) Tracker Upgrade for phase 2 has been ongoing for more than 4 years  So far the (implicit) assumption.
Wim de Boer, Univ. Karlsruhe 1Jan.2009 Design considerations for a CMS CO2 cooling system CMS specials: 50 kW cooling system at C (see below) Difficulties:
CMS CO2 Test Stand Specifications and Installation Status Erik Voirin Fermilab PPD - Process Engineering Group CMS CO2 Cooling Test Stand1.
CMS Pixels upgrade CO 2 cooling transfer lines Introduction to the two projects P.Tropea 5 Dec 2012.
WA104 Cryogenics Design Status David Montanari / Johan Bremer May 21, 2015 Rev. 1.
Cooling R&D at RWTH Aachen Lutz Feld, Michael Wlochal (RWTH Aachen University) CEC Meeting, CERN Lutz Feld, Michael Wlochal (RWTH Aachen University)
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
26 May 2010Hans Postema - CERN Status and plan for the development and construction of CO2 Cooling System for Pixel Upgrade 1.
J. Direito - M. Battistin – 28 th May 2010EN/CV/DC J. Direito, M. Battistin (EN/CV/DC) 28 th May 2010 Detector Cooling Project III Thermosiphon Workshop.
Full Scale Thermosyphon Design Parameters and Technical Description Jose Botelho Direito EN/CV/DC 19 November, th Thermosyphon Workshop.
1 Outer Barrel, Phase 2 Mech Review 26 Aug 2013, indico: Antti Onnela, CERN Tracker Phase 2 Mechanics Review, 26 August 2013 Status of the Outer.
CO 2 Cooling: Overview over CMS activities Jennifer Merz RWTH Aachen University, 1. Physikalisches Institut B May CEC General Meeting, Karlsruhe.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
Cooling System Solutions
CO2 cooling in CMS General overview 30 July 20101Hans Postema - CERN.
Jan. 28, 2014W. Bertl, PSI BPIX Cooling Status W. Bertl, PSI.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
Phase 1 FPix Cooling Tube Testing Erik Voirin, C.M. Lei, Harry Cheung, Stefan Gruenendahl (FNAL) Kirk Arndt, Qiuguang Liu (Purdue) Phase 1 FPIX cooling.
Limits of CO 2 Cooling A clear explanation that anyone can understand (the goal) Hans Postema & Joao Noite PH-CMX-DS1.
Reviewers report of the LHCb C0 2 cooling EDR EDR date: 3 rd of December January
Pixel upgrade test structure: CO 2 cooling test results and simulations Nick Lumb IPN-Lyon MEC Meeting, 10/02/2010.
CO2 Cooling For the CMS Pixel detector 11 November 20081Hans Postema & Antti Onnela.
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Design of the thermosiphon Test Facilities Thermosiphon Cooling Review A. MORAUX PH Dpt / DT Group CERN SEPTEMBER.
LHCb-UT and Velo Upgrade Road to a system EDR in Q June 2015 Bart Verlaat 1.
Aachen Status Report: CO 2 Cooling for the CMS Tracker at SLHC Lutz Feld, Waclaw Karpinski, Jennifer Merz and Michael Wlochal RWTH Aachen University, 1.
Status of the Marco chiller and Marco capacity analyses Bart Verlaat, Lukas Zwalinski, Maciej Osterga, Jan Godlewski MPI Munich,1 March.
Tracker Upgrade Mechanical/Thermal Engineering 3 June meeting theme: Modules and Structures News on Phase 1 BPIX Upgrade Mechanics & Modules, R. Horisberger.
KIT – University of the State of Baden-Wuerttemberg and National Research Center of the Helmholtz Association Institut für Experimentelle Kernphysik
High Granularity Calorimeter Workshop Ideas for cooling of a high granularity calorimeter Nick Lumb, IPN-Lyon 02/02/2015.
7 February 2012 Annekathrin Frankenberger (HEPHY Vienna) Open CO 2 Cooling System at the beam test Belle II SVD-PXD Meeting.
H.-G. Moser, PXD Workshop, Valencia, January 2016 IBBelle for VXD 1 Use one unit first Assemble on a platform which fits in a 20’ container No redundancy.
CERN Cryolab CO 2 cooling for pixel detectors Investigation of heat transfer Christopher Franke, Torsten Köttig, Jihao Wu, Friedrich Haug TE-CRG-CI.
Pixel Cooling Upgrade (2013) 1 December 20081Hans Postema - CERN.
Stave thermal analysis Cooling connections CO2 warm Test
2016/12/6 Yasuhiro R&D status of a gas-compressor based 2-phase CO2 cooling system for FPCCD vertex detector 2016/12/6 Yasuhiro Sugimoto.
For the CMS Pixel detector
Status of Cooling Development in Karlsruhe
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Safety approval of the installed copper cooling pipes
Detector Cooling Project WP2 CO2 activities status report
For the CMS Pixel detector
Performance of a CO2 System with Four Parallel Pipes
Forum on Tracking Detector Mechanics - Bonn, May 2016
Pixel cooling specifications
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Aachen Status Report: CO2 Cooling for the CMS Tracker
Pixel upgrade CO2 cooling plants – 3D modelling
Aachen Status Report: CO2 Cooling for the CMS Tracker at SLHC
Progress at the large scale CO2 system,
Re-circulating CO2 Test System
Pixel CO2 Cooling Status
Detector Technology Group
Recirculating CO2 System
Progress at the large scale CO2 system,
Progress in the development of the CO2 cooling system
Members of project: Christian Brosch Andreas Maier Tamara Bubeck
Status Report on Fermilab CO2 cooling activities
CO2 Cooling IPNL Nick Lumb, 28/01/09.
Tests on a dummy facet of PIX upgrade using CO2 cooling
Aachen Status Report: CO2 Cooling for the CMS Tracker
Second Meeting of the Material Budget & Engineering Working Group
Status and Prospects of Tracker Services Hans Postema (CERN)
For the CMS Pixel detector
Presentation transcript:

14 May 2009Hans Postema - CERN CMS Upgrade Workshop Tracker Phase I upgrades 14 May

CO2 cooling Distributed effort in many different places Lot of progress everywhere Study and engineering are advancing Some installations are built Some installations are running Some preliminary results 14 May 20092Hans Postema - CERN

Participating places (1) Aachen – Lutz Feld, Michael Wlochal Lyon – Nick Lumb, Didier Contardo Karlsruhe – Wim de Boer et al. Fermilab – Simon Kwan, Richard Schmitt, Terry Tope, Kirk Arndt 14 May 20093Hans Postema - CERN

Participating places (2) CERN Cryolab – Friedrich Haug, Jihao Wu, Torsten Koettig, Christopher Franke University Esslingen – Walter Czarnetzki, Stefan Roesler CERN DT group – Joao Noite, Antti Onnela, Paolo Petagna 14 May 20094Hans Postema - CERN

Participating places (3) PSI – Roland Horisberger, Stefan Koenig CERN CMS – Duccio Abbaneo, Paola Tropea, Hans Postema 14 May 20095Hans Postema - CERN

System overview Thin and light pipe inside the detector Pipe connecting techniques Existing pipe-work inside CMS detector Cooling station –Pump, heat exchangers, components Interface to cooling plant in USC Control system Other items Hans Postema - CERN14 May 20096

Lyon test setup System operated from CO2 bottle 5.5 m tube ID=1.4 mm Simulates Pixel barrel tube Hans Postema - CERN14 May 20097

Set-up in Lyon Hans Postema - CERN14 May 20098

5.5 m tube in the freezer Hans Postema - CERN14 May 20099

Last results Lyon Hans Postema - CERN14 May

CERN Cryolab setup Hans Postema - CERN14 May

CERN Cryolab setup Hans Postema - CERN14 May

CERN-DT setup System operated from CO2 bottle 5.5 m tube ID=1.4 mm Simulates Pixel barrel tube Hans Postema - CERN14 May

Detector Cooling Tube Requests The preferred cooling liquid temperature during operation is around -12°C, which corresponds to a pressure of 25 Bar. The Pixel Barrel cooling tube is specified as ID=1.5 mm, wall thickness 50 microns. Layer 1 of the Pixel detector dissipates 144 W over a cooling pipe length of 5.5 m. 14 May Hans Postema - CERN

CO 2 Cooling Test Setup Data Acquisition System Test Zone CO2 Test Rack 14 May Hans Postema - CERN

Temperature Sensors Placement PT100 Temperature Sensors Detector Tube ID = 1.4 mm Insulation 14 May Hans Postema - CERN

Test Zone 14 May Hans Postema - CERN

Data Aquisition System 14 May Hans Postema - CERN

Temperature vs Lenght Power = 144 W Mass Flow = 1 g/s ΔT ≈ 3.7°C ΔP ≈ 2.5 Bar 14 May Hans Postema - CERN

CO 2 Cooling Test Next Steps Tube testing using diferent conditions of: Mass Flow Power Pressure Tube Geometry 14 May Hans Postema - CERN

dT at - 9 C Hans Postema - CERN14 May Power=145W Mass Flow=1g/s Pressure=27 Bar ΔT=2.6°C ΔP=1.9 Bar

dT at – 21 C Hans Postema - CERN14 May Power=144W Mass Flow= 1g/s Pressure= 19 Bar ΔT=5.4°C ΔP=2.9 Bar

Existing cooling pipes The currently installed cooling pipes are virtually impossible to replace People ask: “Is this really the case” Please have a look at the following slides 2314 May 2009Hans Postema - CERN

YB0 – fully cabled 24Hans Postema - CERN14 May 2009

YB0 - numbers Tracker cooling pipes below all the cables HB: 180 cables, 180 optical fiber cables EB: 1600 cables, 180 optical fiber cables Tracker: 3000 cables, 640 Optical fiber cables 9 month plus, installation time Removing and reinstalling ~10 year old EB cables is inviting trouble 2514 May 2009Hans Postema - CERN

Re-use of installed pipes The currently installed pipes are OD=14 and OD=16 mm copper pipes with a wall of 1 mm Cannot be used for 2 phase CO2 cooling without special precaution But can be used when the system design takes care that pressures remain below a limit Avoiding 100+ bar pressures is also advantageous for detector design 2614 May 2009Hans Postema - CERN

Storage tank The system contains a cooled storage tank When system is inoperative, all liquid is condensed in the tank, all warm components are filled with gas (Standard for cryogenic systems) A very similar system is used for the CDF COT flange cooling, same concept, different fluid, different temperature. See next slide 2714 May 2009Hans Postema - CERN

CDF – COT endplate cooling Courtesy Richard Schmitt FNAL 2814 May 2009Hans Postema - CERN

Operation modes Normal operation, system cooled by commercial chiller, CO2 temperatures between 0 and -20 C, pressures 35 to 20 bar Strong request for detector operation with coolant at +15 C (50 bar). This to avoid condensation during the installation and testing phase. For this a safety valve setting at 57 bar, corresponding to +20 C seems acceptable May 2009Hans Postema - CERN

Meeting with CERN safety Meeting with Benoit Delille on 5/12/2008 Using French safety code CODAP-2000 Stress limit during operation: UTS/4 Stress limit during test: UTS/2.6 Thus pressure test at 1.43x max. operating pressure 3014 May 2009Hans Postema - CERN

Questions from safety Questions by CERN-safety concerning safety factors during operation and during test, certificates of installed materials and quality control of the brazed connection have been answered and documented May 2009Hans Postema - CERN

Summary With this system design, max coolant temp at 15 degrees C and safety valve at 57 bar, the currently installed copper tubes can be approved by CERN safety We shall build one equivalent circuit for destructive testing by CERN safety We will pressure test the installed copper tubes with gas at 1.25x57=71 bar 3214 May 2009Hans Postema - CERN

System aspects 1 Aachen is building a re-circulating system. Experience with pump, heat exchanger and other components will be useful for all CO2 systems Hans Postema - CERN14 May

heat removal design considerations o load: 500 W maximum o CO 2 temperature at detector: -45°C … +20°C o precise temperature control o precise flow measurement o continuous operation o safe operation (100 bar max.) chiller temperature  vapour pressure  evaporation temperature Re-Circulating CO 2 Cooling Test System 14 May 2009Hans Postema - CERN pump sub-cooled liquid 4 -> 5: detector load QQ 3 3 Pressure Enthalpy QQ Chiller 2 Chiller 1 flow meter

Implementation of Re-Circulating CO 2 Cooling Test System 14 May 2009Hans Postema - CERN35 Components Chiller 1: Huber Unistat 815 (1.2 Chiller 2: Huber CC-505 Expansion Vessel: Swagelok 304LHDF4-1Gal Levelmeter: Rechner Sensors KFS PEEK-VA-3/4“ Heat Exchangers: SWEP B16DWx8/1P-SC-U Pump: GATHER 1MX-X/12-11/X-SS/S/Q/K200/HDT/DS2D50 Flow Meter: Rheonik RHM015-T2-P1-SM0-M0-G1-N Piping, fittings etc.: Swagelok Frame: ITEM Temperature Probes: various

System aspects 2 Fermilab is looking into system aspects, investigating into pump and heat exchangers. Calulations by Terry Tope determining pressure drops due to sharp bends in detector pipes. Hans Postema - CERN14 May

14 May 2009Hans Postema - CERN 37 CO 2 CO 2 System CO 2We would like to build a prototype CO 2 cooling system at Fermilab CO 2Goals: for testing the completely assembled pixel half-cylinder (3 half-disks) and gaining operation experience of a CO 2 cooling system; design and experience may be expandable and valuable to the final system at P5 or useful for Track/trigger layer R&D at Fermilab Design spec: be able to operate detector at ~18C to -10C; total heat load ~ 1 kW; chiller can cool down to -40C (design with safety margin)

System aspects 3 Karlsruhe is providing TEC cooling plant for system test purposes, acquired LEWA pump and a HEX. Planning on building a large scale test setup in a joint effort together with DT and Cryolab Hans Postema - CERN14 May

Conclusions Distributed effort over many different places. All critical aspects receive attention. Maintaining the excellent and open communication that we have today, is the most crucial ingredient for success. Hans Postema - CERN14 May