GLAST LAT ProjectPDU TRR, July, 2005 4.1.7 DAQ & FSWV4 1 GLAST Large Area Telescope: Presented by P. Young SLAC (650) 926-4257.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectMonthly Review, Aug-1, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
Advertisements

GLAST LAT ProjectSIU MRR DAQ & FSWV1 1 GLAST Large Area Telescope: G. Haller SLAC (650) Gamma-ray Large Area Space.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 Online 1 GLAST Large Area Telescope: I&T Integration Kickoff Meeting EGSE Hardware March 9th,
GLAST LAT ProjectOnline Peer Review – July 20, Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectTEM/TPS TRR, Jan 7, DAQ & FSWV3 1 GLAST Large Area Telescope: Presented by G. Haller SLAC (650)
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
Tower Electronics Module and Tower Power Supply EM Tower Electronics Module (TEM) before coating/staking TEM & TPS assembly Close to 60 TEM & TPS assemblies.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
GLAST LAT ProjectACD CDR, January 7 & 8, 2003 Section 10 Integration and Test 1 GLAST Large Area Telescope: ACD Integration & Test Jim La/ACD I&T Lead.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT Project Quarterly Review, Aug. 14, 2001 Gunther Haller1 GLAST Large Area Telescope: Electronics, DAQ & Flight Software Gunther Haller Stanford.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT Project4.1.7 July 17, 03 LAT Meeting G. Haller V41 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S LAT.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectF-to-F, June 15, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
ISOC Peer Review - March 2, 2004 Section GLAST Large Area Telescope ISOC Peer Review Test Bed Terry Schalk GLAST Flight Software
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST Large Area Telescope ISIS Post Acceptance Test Review 28 January 2005 ISIS Completion Status Jana Thayer Stanford Linear Accelerator Center
GLAST LAT ProjectF-to-F, March, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
GLAST LAT ProjectTower Power Supply Review Sept 22, 2003 Gunther HallerPart 1, Version 3 1 GLAST Large Area Telescope: Electronics, Data Acquisition &
GLAST LAT ProjectPDU/GASU MRR, February 3, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, G. Haller SLAC xxxx LAT Quality Engineer
GLAST LAT ProjectGASU TRR, July, DAQ & FSWV1 1 GLAST Large Area Telescope: Presented by G. Haller SLAC (650)
GLAST LAT Project PDU/GASU MRR 4 February 2005 PART 2 / 1 GLAST Large Area Telescope: B. Estey, Production SLAC (650)
GLAST Large Area Telescope:
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 6.0 Subsystem Verif. Test Plan 1 GLAST Large Area.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review EMI/EMC Presentation 9 of 12 1 GLAST Large Area Telescope Pre-Environmental Test Review EMI/EMC.
GLAST LAT ProjectEGSE Peer Design Review, August 17, S. WilliamsEGSE Overview Electrical Ground Support Equipment Overview Scott Williams Stanford.
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: Pre-Environmental Test.
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT Project4.1.7 G. Haller V11 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Monthly Status Gunther.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: LAT Pre-Ship Review Performance.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Suites (Backup) Stanford Linear Accelerator Center Gamma-ray Large Area Space Telescope.
GLAST LAT Project4.1.7 G. Haller V2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S April Status Gunther.
GLAST LAT ProjectMonthly Review, June 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Environment Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center.
GLAST LAT ProjectTEM/TPS MRR, September 16, DAQ & FSWV1 1 GLAST Large Area Telescope: Gunther Haller SLAC (650)
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
GLAST LAT ProjectPeer Review & CDR Preparation Document: LAT-PR Preparation Schedule Subsystems Peer Reviews –ACD January 7-8, 2003 –CALMarch.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 D. Nelson 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
GLAST LAT ProjectSLAC Internal Review, April 16-18, 2002 LAT-PR Electronics and Flight Software WBS GLAST Large Area Telescope: Electronics,
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST Large Area Telescope:
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Peer Review Agenda (Suggested).
Electrical Ground Support Equipment Verification Test Support
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
Integration and Test Organization Chart
GLAST Large Area Telescope:
GLAST Large Area Telescope
Integration and Test Organization Chart
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 1 GLAST Large Area Telescope: Presented by P. Young SLAC (650) Gamma-ray Large Area Space Telescope PDU TRR

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 2 Contents Introduction –Overview –Significant Changes since CDR –Objectives –Status Requirements/Verification EGSE and Test-Procedures Verification Test Plan and Flow –At Assembly Vendor Test-plan and Flow Facility Man-Power Quality Assurance Vibration –At SLAC Test-plan and Flow Thermal Vacuum Test Mass Property EMI/EMC (at sub-contractor) Man-Power Quality Assurance Equipment Calibration/Safety Risk Assessment Schedule Status of Procedures Issues and Concerns

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 3 LAT Electronics 3 Event-Processor Units (EPU) (2 + 1 spare) –Event processing CPU –LAT Communication Board –SIB Spacecraft Interface Units (SIU)* –Storage Interface Board (SIB): Spacecraft interface, control & telemetry –LAT control CPU –LAT Communication Board (LCB): LAT command and data interface 16 Tower Electronics Modules & Tower Power Supplies * Primary & Secondary Units shown in one chassis Power-Distribution Unit (PDU)* –Spacecraft interface, power –LAT power distribution –LAT health monitoring Global-Trigger/ACD-EM/Signal-Distribution Unit* TKR CAL TKR Front-End Electronics (MCM) ACD Front-End Electronics (FREE) CAL Front-End Electronics (AFEE)

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 4 EGSE PDU Mounted on LAT GASU PDU

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 5 Flight PDU Primary and Redundant PDU DAQ Module in same enclosure, separated by metal

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 6 One enclosure houses primary and redundant Power Distribution DAQ Circuit Card Assembly –Separated by aluminum wall Receives primary and redundant 28V DAQ feed from spacecraft Common mode filter Selects whether to use primary or redundant feed for a selected DAQ board via control signals from SIU Receives LAT command link from primary and redundant SIU into on-board ACTEL FPGA (via LVDS converter IO) On/off control of power to each of the loads: 16 TEM/TPS, 3 EPU’s, via configuration registers Readback of configuration registers to SIU Includes under-voltage, over-current protection and inrush current limiting for each output feed Digitization of 28 primary and 28 redundant RTD and 97 primary and 97 redundant thermistor sensor values –Block redundancy: all primary sensors are connected to primary PDU, all redundant sensors are connected to redundant PDU –Digitization in response to “digitize” command –Readback of results after fixed minimum latency PDU 3.3V-supply voltage level and thermistor interface to spacecraft Power Distribution Module

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 7 Changes since LAT CDR Modification of FPGA code –Code was rewritten by Eric Siskind –Code was reviewed by GSFC reviewer (Dr Rod) Some resistor/capacitor values have changed to optimize monitoring ranges Details of monitoring circuit have changed Redesigned load-switch circuit –To incorporate under-voltage protection Added in case space-craft converters enters current-limiting mode with subsequent drop in output voltage –To incorporate over-current protection Avoids damage to MOSFET switches –Changed resistor values to optimize in-rush current level Worst Case Analysis updated to incorporate changes Thermal Analysis from CDR/Delta-CDR remained since changes don’t impact thermal performance

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 8 Objectives Demonstrate that hardware, software, procedures, and support equipment are prepared to support system environmental test Demonstrate that planned and completed testing meets performance and interface requirements Identify and understand all the risks and limitations TRR is not intended to –Review PDU design –Review flight readiness –Buy-off hardware or software RFA’s should only be of sufficient concern to stop test –Prior to start of an given test, any applicable TRR RFAs must be closed

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 9 Test Entrance / Exit Criteria Entrance –All required paperwork released and in place Procedures, drawings, etc –Test configuration verified and approved –Essential personnel in place –Pre-test PDU functional successfully passed Exit –As-run procedures completed –Correct and accurate application of test environment –Test data acquired and archived –No damage to PDU –PDU performance within specification limits –Post-test PDU functional successful

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 10 Status First PDU (to be proto-flight tested) –Assembled –Pre-conformal coat PDU with enclosure-internal EGSE harness tested, tests to verify that ACTEL performs over temperature performed (was prerequisite to programming FPGA’s for second PDU box) –Conformal coated, integrated in enclosure with flight harness –Final PDU to be delivered to SLAC week of July 18, 2005 Second PDU (to be flight acceptance tested) –Will be spare or primary flight PDU, depending on schedule –Board went thru reflow surface-mount assembly step –ACTEL FPGA’s were programmed and are being assembled on boards –Remaining are staking, integration of boards into enclosure, integration of EGSE harness, testing at SLAC, conformal coating, integration of flight harness, testing

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 11 Tests To-Date PDU engineering modules were extensively tested –As EGSE in DAQ/I&T Testbed includes PDU for > 1 year I&T uses EGSE PDU during integration of towers in LAT for several months Main difference to flight PDU: under-voltage/over- current circuit was not implemented on EGSE PDU’s supplied to I&T and testbed –One flight board was assembled with mostly flight parts and tested –Additional PDU tests Informal thermal test -40C to 55C Informal EMI test on EGSE station sent to Lockheed for thermal test

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 12 Requirements LAT-SS Specifications, Level 4 LAT Dataflow System LAT-SS Specifications, Level 3 T&DF Subsystem Specification LAT-SS Specifications, Level 3 Power Supply System LAT-SS Specifications, Level 4 Power Supply System LAT-SS Specifications, Level 5 PDU Specification LAT-TD LAT Inter-Module Communications LAT-TD PDU ICD Specification & Conceptual Design LAT-TD PDU, Programming ICD LAT-SS LAT Environmental Specification LAT-SS PDU lists requirements LAT-TD contains Verification Matrix which gives approach to verify each requirement –Lists verification method used

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 13 System Performance Level 3 and level 4 DAQ and TRG and power-system requirements are met with a combination of DAQ modules (TEM/TPS, GASU, SIU, PDU, etc), since the DAQ and trigger and power system is comprised of several sub-system module types –Level 5 PDU requirements which are verified are derived from Level 3 and Level 4 DAQ and Trigger and Power system specifications (as noted in the L5 requirements doc) –Level 5 requirement doc includes derived requirement addressing Functionality/performance Power Mass/C.G. EMI/EMC Environmental incl temperature and vibration

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 14 Verification Status Engineering Module PDU –EM completed full functional test program with exception of thermal-vacuum, EMI/EMC, mass, and C.G. –Demonstrated compliance with specifications

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 15 EGSE and Test-Procedures EGSE for Functional/Performance Tests –Test-Stand documented in LAT-DS Test-Procedures –LAT-TD Electrical Interface Continuity and Isolation Test procedure Power-off impedance tests of I/O –LAT-TD Stray-Voltage-Test Procedure Power-on voltage test of I/O –LAT-TD Comprehensive Test Procedure Functionality and Performance test

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 16 EGSE Test-Configuration LAT-TD

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 17 Verification Level – Module Detail Breakout of verification at PDU Module Level Tests to be conducted after successful TRR (order may change depending on availability of resourced (TV/EMI) EICIT & SVT Functional test Vibration (Wyle) Functional test Thermal cycle Functional test Mass properties including CG Thermal vacuum (in-situ testing) EMI/EMC (at CKC-lab for proto-flight, at SLAC for flight acceptance) Functional test Review Deliver to I&T –DAQ (out-going) / I&T (incoming) test combined

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 18 Verification Test-Stand –Supplied by SLAC –Operated by SLAC engineers Vibration facility at Wyle –LAT-TD Vibration test-procedure –SLAC engineers present for vibration tests Thermal Cycle in thermal chamber in SLAC clean-room

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 19 TC and Vibration Requirements Figure 1. Vibration Levels, Duration, and Spectra

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 20 Mass Property Mass properties checked at SLAC –Procedure to be written (performed at SLAC Metrology) –Expected: (ref LAT-TD-00564) Total 9.8 kg Allocation 12% above = 11 kg –C.G. to be measured for the proto-flight unit only

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 21 Thermal Vacuum Test Thermal Vacuum facility in Building 33 at SLAC –Thermal Vacuum Chamber Operating Procedure LAT-TD –PDU Thermal Vacuum Test-Procedure LAT-TD –First PDU tested to proto-flight specifications (same Temperatures as qualification, but 4 TV cycles versus 12 cycles)

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 22 Proto-Flight and Flight Acceptance Thermal Vacuum Test See PDU Thermal Vacuum Test-Procedure LAT-TD At < 10-5 Torr X 4

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 23 EMI/EMC Test Proto-Flight = Qualification Test (Conductive & Radiative) –Sub-contracted to CK Labs –Statement of Work: LAT-PS CE102, CECN, CS102, CSCM, CS06, RE101, RE102, RS101, RS103 –Detailed EMI/EMC procedure provided by CKC lab (TP doc, to be released?) –SLAC engineers present at vendor for tests –Vendor supplies test-report –LAT QA at SLAC present for tests Flight Acceptance Test (Conductive) –Performed at SLAC –LAT-TD Only CE102, CS102 –SLAC supplies test-report –LAT QA at SLAC present for tests

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 24 Manpower & Quality Assurance Test man-power –PDU: Patrick Young –Test Support: J. Ludvik –Thermal Cycle and TV support: R. Williams, P. Hart –TV shift support: 2 contractors –EMI support: D. Nelson –Vibration support: D. Tarkington Quality assurance: Joe Cullinan –QA representative (Y.C. Liew) present during tests, review of test-procedure and results –Required changes to documentation are red-lined and included in new revisions –NCR are created for non-conformance (e.g. exceeding of min/max test limits) and submitted for disposition

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 25 Problem Failure Report/ Configuration Management Problem Failure Reporting –Via standard SLAC LAT Non-Conformance Reporting (NCR) System NCR is entered Reviewed/accepted/resolved –LAT engineering –LAT QC Already exercised during pre-conformal coat PDU assembly Configuration Management –Via standard LATDOC system

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 26 Planned Tests Function/Performance Tests (LAT-TD-01744) –Verifies all requirements in LAT-SS except below Thermal Vacuum Tests –Verifies performance/function over temperature Mass/C.G. –Verifies/measures mass and C.G. Vibrations test –Verifies vibration performance requirements EMI/EMC –Verifies EMI/EMC performance Note to margin testing –External Voltage margin testing is performed at all stages (28V +/-1V) –Internal Voltage margin testing (3.3V/2.5V) is only performed at pre- conformal coat stage while using internal EGSE harness –No internal voltage margin testing once flight harness is used. Respective tests in TD are omitted at that stage as will be documented in work- order –Frequency margin tested pre-conformal coat as well as on final PDU –Temperature testing performed during TV testing

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 27 Equipment Calibration Electrical Functional Test Equipment –EGSE Test-Stand documented at glast.slac.stanford.edu/Elec_DAQ/EGSE/I&TPDU/TESTSTAND_ 1164/teststand1164docs.htm EMI/EMC Test Equipment –Quantitative measurement equipment (sensors, antennas, etc) calibrated to NIST standards –Calibration performed annually All item are (will be) within calibration at time of testing Vibration Test Equipment –Accelerometers calibrated against a standard accelerometer traceable to NIST –Signal conditioners calibrated annually TVAC Equipment –Thermocouples calibrated against standard temperature; calibrated prior to test –Thermocouple reader calibrated very 2 years

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 28 Sub-System Safety EGSE –Safe-to-mate –Configuration control –Calibration verification –Functionality verification with “golden” EGSE PDU prior to test with flight hardware MGSE –No custom MGSE Environment –Temperature controlled in all test-facilities –Cleanliness actively controlled in clean-room; hardware bagged and purged when required Training –ESD training completed –Clean room training completed

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 29 Risk Assessment Schedule –Pressure to deliver flight hardware could force less than complete characterization and analysis of modules, could result in replicating a problem in the second module Performance –None known Software to support TV test is still in development

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 30 Test-Schedule Estimated as follows, order subject to EMI/TV availability First PDU –7/25: functional test –7/28: vibration test –7/29: functional test –8/1: TC –8/2: functional test –8/3: EMI start –8/17: EMI end –8/18: mass, c.g. property –8/9: TV start –8/29: TV end 2 nd PDU –Lags first PDU by about 8 weeks

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 31 Status of Main Test Procedures All procedures must be released before respective test Procedures to be released –Mass/CG procedure to be written/released –EMI vendor procedure to be released –CPT and TV modified, revisions are in review –Vibration procedure released?

GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 32 Issue & Concerns Schedule –Tight Vibration test –Concern that harness/connectors pass vibration tests (should be ok, but is concern)