Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 paul drumm; ; FAC-PR MICE Project Status Funding Agency Committee 19 th September 2005.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
UK Costs Beam & Infrastructure Coils Tracking Detector.
CMPB Alain Blondel 14 April STATUS OF MICE.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Layout and Installation MICE Collaboration Meeting, RAL, October 27-29, 2004 Elwyn Baynham, Tom Bradshaw, Paul Drumm, Matthew Hills, Yury Ivanyushenkov,
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM32 25 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
MICE Demonstration of Ionisation Cooling Colin Whyte University of Strathclyde On behalf of the MICE collaboration 1RF Review 9th-10th Sept. 2015, Abingdon.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement Ionisation Cooling Test.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Comments on the February DOE Review
Muon Ionisation Cooling Experiment Overview
MICE CM28 Engineering Session Summary (On behalf of Wing)
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE Project in the US: Completion of Efforts
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014

Content Assumptions Document Decision of direction for Cooling Demonstration 2

Assumptions Document Scope –Try to capture and understand who is responsible for what – and agree to those statements Funding, institutes and international contributions – The UK funding agency will continue to fund STFC and University groups – Proposal 2015/16 – The DoE will continue to fund the US construction team – No specific call out for the Non-UK / US collaborators – needs to be added – UK will deliver and be responsible for MICE infrastructure and construction-project management; The hydrogen system and associated extraction and safety systems; The focus-coil module and associated power supplies and cooling equipment; and The MICE Muon Beam including the MICE target, the decay solenoid an the conventional magnets along with the associated power-supply, cooling and the storage equipment. RF Amplification system –US will deliver and be responsible for RF cavities and associated vacuum chambers, vacuum equipment; Partial return yokes for Step IV and cooling demo. Spectrometer Solenoid magnets Cherenkov detector systems Additional lithium hydride absorbers – University of Geneva will deliver and remain responsible for the EMR and DAQ system – INFN will deliver and remain responsible for the TOF and KL detectors 3

Assumptions Document Safety – The MICE Project Engineer will hold the full delegated responsibility for safety in all areas, activities and project periods through to completion of the MICE project holding the title of Group Leader In Matters Of Safety (GLIMOS); Spares – Spares for each sub-system is the responsibility of that subsystem and will be delivered before operations Maintenance – Maintenance of the compressor and cold heads will be borne by the common fund – Maintenance of the hall infrastructure, eg Air Conditioning, will be borne by MICE-UK – Not called out needs to be added – Maintenance of Vacuum systems will be borne by the common fund Gasses and Cryogens – During construction and commissioning periods the cost of gasses will be borne by MICE-UK – During construction and commissioning periods the cost of cryogens will be borne by the sub system groups. – During operations the cost of gasses and cryogens will be borne by the common fund. Vacuum – MICE-UK will provide the manifold system for the experiment and provide the support during operations Construction – All lifting operations will only be carried out by approved crane operators 4

Assumptions Document Operations – ISIS Cover–approximately 6 FTE will be funded for by the MICE-UK project budget with a fraction of the current Common Fund levy already set aside for project / operational support staff –Detector System–each detector to supply expert operators during operational periods. The effort supplied will be sufficient to allow 24 hour running of the experiment; –Magnet System–each magnet system to supply expert operators during operational periods. The effort supplied will be sufficient to allow 24 hour running of the experiment. 5

Cooling Demonstration Important for the engineering teams to have a direction and end goal for the Cooling demonstration A decision on the arrangement for the cooling demonstration has a large impact on the engineering required Single cavities and the ends or double cavity at the centre The layout of the magnets and absorbers has an impact on Floor plate arrangement Waveguides for RF PRY support structures PRY Walls – penetrations for the waveguides Vacuum envelope Power and instrumentation services South mezzanine – support legs may need changing for example X-ray shielding (may not be needed any more) Clean room space for cavity build-up Transportation frames / devices 6