© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.

Slides:



Advertisements
Similar presentations
Evaluation Independent Monitoring Presented at: LPSC Staffs Technical Conference and ESIs Bidders Conference for the Fall 2006 Limited-Term RFP September.
Advertisements

AN INTRODUCTION TO THE MIDWEST ISO By Bill Malcolm Manager-State Regulatory Affairs Pierre, South Dakota June 9, 2006.
Rocky Mountain Area Transmission Study RMATS Economics Economic Comparisons Preliminary: Distribution of Gains and Losses RMATS Steering Committee July.
Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Ad Hoc West-wide Resource Assessment Team (WRAT) : Assessment of Western System Adequacy in the Short-term Jeff King Northwest Power Planning Council Presentation.
SPP’s 2013 Energy Consumption and Capacity 2 12% annual capacity margin requirement CapacityConsumption Total Capacity 66 GW Total Peak Demand 49 GW.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
1 The Midwest ISO At the Crossroads of America International Meeting of Very Large Power Grid Operators October 24 & 25, 2005 Beijing, China.
1.  Purpose  To present Staff’s Preliminary Findings on the 2012 Integrated Resource Plans of:  APS – Arizona Public Service Company  TEP – Tucson.
Congestion Management in a Market Environment 2 nd CIGRE / IEEE PES International Symposium San Antonio, Texas October 5, 2005 Kenneth W. Laughlin.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
1 Dale Osborn Midwest ISO February 27, Wisconsin Renewable Energy Summit Transmission Expansion Opportunities with Wind Energy.
Announcements Be reading Chapter 7
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable.
EE 369 POWER SYSTEM ANALYSIS
SPP.org 1. 2 Aggregate Transmission Service Study (ATSS)
National Renewable Energy Laboratory Innovation for Our Energy Future * NREL July 5, 2011 Tradeoffs and Synergies between CSP and PV at High Grid Penetration.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
Optimization for Operation of Power Systems with Performance Guarantee
Production Cost Model Fundamentals
Integration of Variable Generation Task Force Preliminary Conclusions and Actions.
Base Case Draft – For Comment Rocky Mountain States Sub-Regional Transmission Study December 9, 2003.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Black Sea Regional Transmission Planning Project By Predrag Mikša EKC - Electricity Coordinating Center Istanbul, March 2011.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Sixth Northwest Conservation & Electric Power Plan Draft Wholesale Power Price Forecasts Maury Galbraith Northwest Power and Conservation Council Generating.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Entergy AFC Stakeholder Meeting February 16, 2005 Houston, TX.
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Reliability Must-Run Analysis 2006 – th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.
Lecture 13 Newton-Raphson Power Flow Professor Tom Overbye Department of Electrical and Computer Engineering ECE 476 POWER SYSTEM ANALYSIS.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
ISO New England State of the Markets Report May April 2002 Robert Ethier, Ph.D. Manager, Market Monitoring and Mitigation ISO New England June 26,
Analysis of Demand Response Modeling in GridView Andy Satchwell and Sarah Smith Modeling Work Group December 21, 2015 The work described in this presentation.
1 Tests for Reasonable LMPs & Price Validation Tool Overview October 27, 2009 NATF.
1. Non-Dispatchable Resources and EIS Market Carrie Simpson May 30,
Announcements Homework 8 is 11.19, 11.21, 11.26, 11.27, due now
SPP.org 1. ICT Working Groups Current Activities Jody Holland Dowell Hudson Antoine Lucas Tim Phillips.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
ECE 476 Power System Analysis Lecture 13: Power Flow Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
ERCOT Public 1 Project Panel 1 Dan Woodfin Director, System Operations August 15, 2014.
January 14, 2016 PacifiCorp-CAISO-NVE EIM Initiative Overview.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
Minnesota Renewable Energy Integration and Transmission
Transmission Planning in ERCOT- Overview
Wind Management at MISO
Status Update for Reliability/Market Power Mitigation Assessment
ECEN 460 Power System Operation and Control
ISO New England System R&D Needs
ECEN 460 Power System Operation and Control
ECEN 460 Power System Operation and Control
PJM & Midwest ISO Market-to-Market Coordination (APEx Conference 2007)
Planning Tools Overview
Basin Electric SPP Market Update
ECEN 460 Power System Operation and Control
Planning Tools Overview
Acadiana Load Pocket Project
Strategic Plan and Economic Upgrade Process
Presentation transcript:

© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest Power Pool (SPP) February 16, 2011 ABB Inc., Electric System Consulting Dept. ERSC

© ABB Group August 23,2010 | Slide 2 Agenda  Study Overview  Study Status  Task List and Study Approach  Case List  Reference Case  Production Costing  Power Flow  Very Preliminary Results for Western Load Pocket  Production Costing  Power Flow Analysis  Next Steps

ERSC © ABB Group August 23,2010 | Slide 3 Study Status  Study assumption document submitted for review  Completed development of production costing and power flow models for 2013 Reference Case (RMR nomograms enforced)  Analysis started for Western Load Pocket

ERSC © ABB Group August 23,2010 | Slide 4 Task List Task 1 – Develop Data base and System Models Task 2 – Transmission Analyses with RMR Unit Task 3 – Transmission Analyses w/o RMR Unit & no Transmission Change Task 4 – Transmission Analyses w/o RMR Unit & Transmission Change Task 5 – Production Cost Simulation with RMR Unit Task 6 – Production Cost Simulation w/o RMR Unit & no related Transfer Limit Constraint Task 7 – Production Cost Simulation w/o RMR Unit & with Transmission Changes Task 8 – Economic Comparison of Benefits and Costs Task 9 – Collate results by Units, Plants and Groups. Task 10 – Congestion Analysis Task 11 – Fuel Price Elasticity Task 12 – Sensitivity Analysis Task 13 – Perform ATC Calculations Task 14 – Study Report Preparation, Discussion and Presentation Task 15 – Additional Transmission Upgrades required for Flexible Capacity (Optional)

ERSC © ABB Group August 23,2010 | Slide 5 Study Approach - Overview

ERSC © ABB Group August 23,2010 | Slide 6 Case List

ERSC © ABB Group August 23,2010 | Slide 7 Reference Case  Reference case provides a base for determining the impact of removing the RMR designations for the study units  RMR nomograms are enforced in the reference case  Modeling assumptions described in Study Assumptions Document

ERSC © ABB Group August 23,2010 | Slide 8 Reference Case (Production Costing)  Benchmarked with Entergy units, using following statistics for 2007, 2008, 2009: Annual energy production Annual service hours  RMR guidelines modeling was verified  Operating reserve modeling was verified  Entergy generation units data were checked

ERSC © ABB Group August 23,2010 | Slide 9 Reference Case (Power Flow)  Reference case represents system conditions at the Entergy system peak hour (Aug. 26, 3 pm)  Started from 2013 power flow case prepared by SPP-ICT  Synchronized Loads in the Power Flow and Production Costing at the peak hour  Synchronized dispatch of generating units within Entergy footprint based on Production Costing dispatch (SCED) at the peak hour  Also ensured interchange between Entergy footprint and Tier 1 matches Production Costing interchange  Entergy footprint totals at the peak hour:  Load + losses: 33,810 MW  Generation: 32,068 MW  Import from Tier 1: 1,742 MW

ERSC © ABB Group August 23,2010 | Slide 10 Reference Case (Power Flow)

ERSC © ABB Group August 23,2010 | Slide 11 Reference Case Results (Power Flow)  Ran power flow analysis on Reference Case to check steady-state performance in Entergy footprint for following conditions:  System intact  N-1 contingencies  G-1,N-1 contingencies (WOTAB and Amite South)  Results submitted to SPP  SPP reviewed results and provided Construction Plan projects and comments on results

ERSC © ABB Group August 23,2010 | Slide 12 Western Load Pocket Analysis  Following cases were simulated Case Name Definition West_0Same as reference case West_1Same as West_0 with no nomogram West_2Same as West_1 with no Western area transmission limits and no limits on 8 tie-lines between Western & WOTAB in production costing analysis West_3Same as West_0 with plant turned off West_4Same as West_3 with no Western area transmission limits and no limits on 8 tie-lines between Western & WOTAB in production costing analysis

ERSC © ABB Group August 23,2010 | Slide 13 Western Analysis (Contd.) Preliminary results For case West_1, it is found that:  Lewis Creek units are still being dispatched on the security constrained economic dispatch basis and also due to transmission constraints that limit the import of power into the WOTAB/Western load pocket.  Power flow analysis: When RMR designation was not used for Western units (Case West_1), generation dispatch is identical to that in the Reference Case (West_0 with RMR rule enforced) at the peak load hour. Hence, there was no need to repeat power flow for the West_1 Case.

ERSC © ABB Group August 23,2010 | Slide 14 Western Analysis (Contd.) Preliminary results  In Case West_2, reduction (appr. 40%) in the Lewis Creek plant annual energy (MWh) production was observed.  Power flow analysis showed degradation in steady-state performance (more overloads) compared to West_1 case, because the plant was dispatched at about 20% lower MW level (than in West_1 Case) during Entergy’s peak load hour.

ERSC © ABB Group August 23,2010 | Slide 15 Western Analysis (Contd.) Preliminary results  For West_3 Case, with Lewis Creek plant turned off, the annual production cost, in the Entergy footprint, increased.  Power flow analysis showed further degradation in steady-state performance (overloads) compared to West_2 case, including Voltage Collapse for certain double contingencies and several G1N1 contingencies. This is mainly due to erosion of reactive capability in Western Load pocket.  The results for West_4 Case were similar to West_3 Case.

ERSC © ABB Group August 23,2010 | Slide 16 Next Steps  Relieve all constraining flowgates  Increase WOTAB import limit  Power flow analysis will be run to check for transmission constraints associated with import of cheaper power into Western  Addition of transmission projects to increase load pocket import capability  Analysis (production costing and power flow): a) Is more economical generation available than assumed in the Production Costing model? b) If so, does that case require associated transmission fixes? - PV curves, OPF etc.

ERSC © ABB Group August 23,2010 | Slide 17 Q & A Thank you!