PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.

Slides:



Advertisements
Similar presentations
12/12/ PHENIX WEEKLY PLANNING Dec. 12, 2013 Don Lynch.
Advertisements

PHENIX WEEKLY PLANNING 9/13/2007 Don Lynch. 9/13/2007 Weekly Planning Meeting 2007 PHENIX Shutdown April-June 2007: Complete run, De-mount HBD West, Begin.
PHENIX WEEKLY PLANNING 1/17/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
PHENIX WEEKLY PLANNING 9/6/2007 Don Lynch. 9/6/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upin progress.
PHENIX WEEKLY PLANNING 10/25/2007 Don Lynch. 10/25/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 11/1/2007 Don Lynch Daylight Savings Time ends Sunday Nov. 4 at 2:00 AM.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
5/9/ PHENIX WEEKLY PLANNING 5/9/2013 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/05/06 Don Lynch. 10/05/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
PHENIX WEEKLY PLANNING 5/24/2007 Don Lynch. 5/24/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6/07 Remove HBD.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
1/9/ PHENIX WEEKLY PLANNING Jan. 9, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 7/19/2007 Don Lynch. 7/19/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 8/9/2007 Don Lynch. 9/9/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
PHENIX WEEKLY PLANNING 12/20/2007 Don Lynch. 12/20/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 7/26/2007 Don Lynch. 7/26/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Presentation transcript:

PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch

10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec. Cooling Water upgrade(CA) (under EC)In progress10/12 (elsewhere in IR)In progress11/2 CM Move to Run position DoneDone MPC South InstallationDoneDone Borated PE neutron shield installationIn progress10/12 More decapacitor removalsDone?Done? Note: Final decision has been made to start run 8 cooldown on Nov. 1, 2007

10/11/2007 Weekly Planning Meeting3 ItemStartFinish EC Roll In10/1510/31 C-A fold scaffolding10/1510/15 Move MuID collars to IR10/1210/15 Remove Plates, cart & move Manlift10/1210/15 Roll in-to IR and North to run pos.10/1510/16 PHENIX techs reconnect water, elect., gas, fibers10/1610/19 Carpenters restore scaffolding, Re-install lift & ladder, re-connect gas sniffers10/1710/19 Mike Rau re-install lift wiring, Re-connectTOF blower 10/1610/19 Blue Sheet/Pink sheets10/2211/2 Run 8 Prep Schedule (cont’d)

10/11/2007 Weekly Planning Meeting4 ItemStartFinish DC East & West repairs (permits done)10/1110/26 Pre-run Commissioning10/110/31 Assemble shield wall10/2911/1 Shield wall roll in11/111/5 Start of Run 8 (Cooldown)11/111/1 HBD Pre survey at SBA-1 wkA-1 day HBD West Mechanical/Gas Reinstall12/3?12/17? HBD EAST Mechanical/Gas Reinstall ?????? HBD Electrical Reinstall?????? HBD installation survey10/1?12/22? Run 8 Prep Schedule (cont’d)

PHENIX Run 8 Electronics Preparation

10/11/2007Weekly Planning Meeting6 FCAL LED Pulser One NIM BIN per Arm. One NIM BIN per Arm. G-Link Breakout modules complete. G-Link Breakout modules complete. LED Driver modules complete. LED Driver modules complete. Test Pulser in 1008 Tech Shop with modebits? Test Pulser in 1008 Tech Shop with modebits? Currently making a LED Interface board. Currently making a LED Interface board. Try to have it all ready before J. Newby arrives. Try to have it all ready before J. Newby arrives.

10/11/2007Weekly Planning Meeting7

10/11/2007Weekly Planning Meeting8 LED Cable Interface Driver board outputs pulses on Lemo cables. Driver board outputs pulses on Lemo cables. Simple PC board will connect Lemo cables to FCAL ribbon cables through ballast resistors. Simple PC board will connect Lemo cables to FCAL ribbon cables through ballast resistors. 5 to 10 LEDs per channel. 5 to 10 LEDs per channel.

10/11/2007Weekly Planning Meeting9 FCAL Racks NIM bin goes here?

10/11/2007Weekly Planning Meeting10 HBD LeCroy HV Trip Sensor For protection of GEMs For protection of GEMs Trip Sensor board finished. Trip Sensor board finished. Relay board due next week and Sal will assemble six. Relay board due next week and Sal will assemble six. Panels needed for Relay Module. Panels needed for Relay Module.

10/11/2007Weekly Planning Meeting11 Some Other Things PC FEM testing (Anders). Sal found many physical problems on boards, some easy fixes. PC FEM testing (Anders). Sal found many physical problems on boards, some easy fixes. Ed Desmond working on GP Test Stand. Will be ported to Physics. Ed Desmond working on GP Test Stand. Will be ported to Physics. Reconnect fibers to EC after roll-in and test all EC systems. Reconnect fibers to EC after roll-in and test all EC systems. Need some odds and ends: more fibers for HBD? Need some odds and ends: more fibers for HBD?

10/11/2007 Weekly Planning Meeting12 Safety Systems/ UPS HSSD has been split IR from AH. IR is done. AH will be addressed during run. Alarms are the same for zone 3 (IR HSSD) but shutdown trip is permanently disabled/removed New system for AH is in planning. Working with C-A to assure we have the right number of spare parts for run Beginning to review blue sheet test procedure UPS We borrowed unit (15 KVA) from AGS (used with new batteries) will be energized on Monday/Tuesday and put online to phoncs computers. PO to be issued tomorrow for 30 KVA Mitsubishi unit. Should arrive ~ 1 month. Change over during the run hopefully before we begin taking physics data.

10/11/2007 Weekly Planning Meeting13 CM Ladder/Stair Shutdown Access PO pinned Waiting for delivery Purchasing SNAFU causes delay Delivery ~10/15

10/11/2007 Weekly Planning Meeting14 Station 1, 2, 3 access plan Work to begin on these items after prep for run 8 is finished

10/11/2007 Weekly Planning Meeting15 RPC Factory Issues Now-to-factory- operation schedule Factory Work Plan Detector assembly /test procedure Gas system operating procedure Electrical/electronics review Final walkthru What we can do now: Install and move in furniture, equipment, gas piping and leak tests, and test equipment operations What we can’t do now: Operate gas system (other than N2 leak tests), store, assemble and/or test detector modules and/or other components.

10/11/2007 Weekly Planning Meeting16 Mu Trigger Station 1 and 2 Upgrades Mockup boxes to be in place when the CM moves north MuTr Station 1 20 existing FEE’s Nothing new on this

10/11/2007 Weekly Planning Meeting17 Other Work Empty (except clean metal waste) and discard old container Neutron shielding test (4’ x 4’ x 2” borated polyethylene Shield support design in progress Install in October for Run 8 tests Shield to be fly cut to 1.25” thick, drilled and Tapped fo 3/8-

10/11/2007 Weekly Planning Meeting18 Safety, Security, Etc. : Tier 1 Inspection No new effforts Performance Appraisals- Get your achievements input and submitted by end of this week PPE update – Lab adopts PHENIX policy… Shoes, long pants required for work in IR and AH, short sleeves OK unless nature of work requires greater level of PPE

10/11/2007 Weekly Planning Meeting19 5 Year Plan 2007 HBD Repairs, DC (minor) repairs), MPC N&S upgrade,MuTr FEE upgrade prototype, infrastructure upgrades & repairs, misc. subsystem work 2008 MuTr FEE upgrades 1 octant 1&2 S, Cu absorber test, RPC3 S, infrastructure upgrades & repairs, misc. subsystem work 2009 Scaffolding in MMS and MMN, MuTr FEE N&S stn. 2 & 3, MuTr N&S stn. 2 & 3 repairs, RPC2 S&N, RPC3 N, Cu absorbers, infrastructure upgrades & repairs, misc. subsystem work 2010Remove HBD & RXNP, remove beampipe, DC West upgrade, VTX barrel, RPC1 N&S, MuTr FEE stn. 1 N&S, MuTr stn. 1 N&S repairs, infrastructure upgrades & repairs, misc. subsystem work 2011NCC S, FVTX, infrastructure upgrades & repairs, misc. subsystem work 2012NCC N, upgrades contingency & wishlist, infrastructure upgrades & repairs, misc. subsystem work * Years refer to the shutdown year and follow the run with the similar number (i.e. work in 2007 is to be done in the shutdown that follows run 7, and so on)

10/11/2007 Weekly Planning Meeting20 Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Where To Find PHENIX Technical Info