GLAST LAT Project Technical/Cost/Schedule Review 06/30/05 4.1.9 - Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Advertisements

GLAST LAT Project Managers F2F Integration and Test 1 GLAST Large Area Telescope: Face to Face Managers Meeting LAT Integration & Test April.
GLAST LAT Project Online Peer Review – July 20, Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT ProjectISOC CDR, 4 August 2004 Document: LAT-PR-04500Section 3.31 GLAST Large Area Telescope: Instrument Science Operations Center CDR Section.
GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
1 GLAST Large Area Telescope Monthly Mission Review LAT Flight Software Status June 6, 2007 Jana Thayer Stanford Linear Accelerator Center Gamma-ray Large.
GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 Online 1 GLAST Large Area Telescope: I&T Integration Kickoff Meeting EGSE Hardware March 9th,
GLAST LAT ProjectOnline Peer Review – July 20, Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT Project Apr 1, 2005 E. do Couto e Silva 1/31 Overview of End to End Runs Eduardo do Couto e Silva April 1, 2005 ( not it is not a joke, we finally.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
1 GLAST Large Area Telescope Monthly Mission Review LAT Flight Software Status October 29, 2007 Jana Thayer Stanford Linear Accelerator Center Gamma-ray.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectISOC Peer Review - March 2, 2004 Document: LAT-PR Section 2.1 Requirements 1 Gamma-ray Large Area Space Telescope GLAST Large.
GLAST LAT ProjectMonthly Status Review – Sept. 1, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus1 Online Roadmap to the July 2004 Freeze Progress report for April 22, 2004 (to.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test J. Panetta 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope:
GLAST LAT ProjectOnline Peer Review – July 21, – Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT Project July 19, 2005 E. do Couto e Silva 1/17 Science Verification Analysis and Calibration GLAST Large Area Telescope Eduardo do Couto e Silva.
GLAST LAT Project Managers F2F 6/15/ Integration and Test 1 GLAST Large Area Telescope: Face to Face Managers Meeting LAT Integration & Test.
GLAST LAT Project Managers F2F 5/11/ Integration and Test 1 GLAST Large Area Telescope: Face to Face Managers Meeting LAT Integration & Test.
SVAC Instrument Analysis Meeting Aug 5, 2005 E. do Couto e Silva and Anders W. Borgland 1/7 SVAC 8 tower testing+ACD Anders and Eduardo.
GLAST LAT Project ISOC Peer Review - March 2, 2004 Document: LAT-PR Section 2.3 Verification and Validation 1 Gamma-ray Large Area Space Telescope.
GLAST LAT Project Technical/Cost/Schedule Review 03/31/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
111/3/2004 GLAST LAT ProjectLAT Engineering Meeting LAT Face to Face Manager’ Meeting Nov. 3, 2004 LAT Level Design Status LAT Face to Face Manager’ Meeting.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project ISOC Peer Review - March 2, 2004 Section Gamma-ray Large Area Space Telescope GLAST Large Area Telescope ISOC Peer Review 7.2.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT Project Technical/Cost/Schedule Review 09/01/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT ProjectTest Planning Meeting Aug 2, 2004 E. do Couto e Silva 1/6 SVAC EM2 Goals Develop distributions for E2E tests that involve comparison of.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT Project Technical/Cost/Schedule Review 05/24/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test L. Miller 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
Release & Deployment ITIL Version 3
GLAST Large Area Telescope:
GLAST LAT ProjectI&T&C Pre PDR, October 2, 2001 E. do Couto e Silva1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT Project LAT Instrument Analysis Workshop – Feb 27, 2006 Hiro Tajima, TKR Data Processing Overview 1 GLAST Large Area Telescope: TKR Data Processing.
GLAST LAT Project Technical/Cost/Schedule Review 04/26/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT ProjectI&T Face-to-Face Online Presentation – May 30, 2002 R. Claus1 I&T Online Status and Plans Ric Claus.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Suites (Backup) Stanford Linear Accelerator Center Gamma-ray Large Area Space Telescope.
GLAST LAT Project IA Workshop 4 July 14, 2005 E. do Couto e Silva 1/7 Introduction to the Instrument Analysis Workshop 4 Eduardo do Couto e Silva July.
GLAST LAT Project CU Beam Test Workshop 3/20/2006 C. Sgro’, L. Baldini, J. Bregeon1 Glast LAT Calibration Unit Beam Test Status Report on Online Monitor.
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review SVAC Elliott.
GLAST LAT Project SE Test Planning Dec 7, 2004 E. do Couto e Silva 1/27 Trigger and SVAC Tests During LAT integration Su Dong, Eduardo do Couto e Silva.
I&T&C Organization Chart
GLAST Large Area Telescope:
Mechanical Integration
Overview of Instrument Analysis Effort
LAT Test Results GLAST Large Area Telescope LAT Pre-Shipment Review
GLAST Large Area Telescope:
Overview Goal Study GEM variables in SVAC ntuple
Integration and Test Organization Chart
GLAST LAT System Engineering
GLAST Large Area Telescope: I&T Test Readiness Review
Introduction and Overview
Integration & Test Instrument Operations Coordination
SVAC Configuration Verification
Presentation transcript:

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 06/30/05 Elliott Bloom SU-SLAC Subsystem Manager Ken Fouts SU-SLAC Subsystem Engineering Manager Gamma-ray Large Area Space Telescope

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 2 Last Month's Accomplishments (1 of 3) Management –Tracking hardware shortages for LAT integration. –TKR Delivery –ELX Boxes –Procedure Status –69 of 70 submitted for sign-off or released IFCT –Completed 4 tower tests. –Completed I&T receiving tests on 3 TKR’s, 11 CAL’s and 3 TEM’s. –Completed assembly, checkout and installation of the grid cooler (aka the Chilla from Manila). –Completed installation of 2 additional towers for a total of 6 towers installed in the grid. –Completed alignment survey of 6 towers. –Preparations complete for 6 tower tests. –Completed shear plate and cable tray installation at four towers.

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 3 Last Month's Accomplishments (2 of 2) Online –LATTE Supported VSC software Python interface implementation Exploratory work in progress to demonstrate interaction with the VSC and its software interface released for ACD –Initiated by ACD-discovered bug –Bug fixes, Trigger GUI, GPIB support –Updated HippoDraw correcting memory leaks –Updated trigger GUI to address concerns raised in trigger meeting –Bug fix for incorrectly initialized TEM BUSY_LRS_MASK register (measures TEM deadtime) Housekeeping multi-pen strip-chart GUI V2.0 deployed to clean room for real-time monitoring. E-logbook Version released (minor bug fixes with corresponding tutorial and documentation updates)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 4 I&T Activities Grid Chiller Unit Installation Grid Cooling Six CAL/TEM’s Installed Six Towers in the Grid

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 5 I&T NCRs by Month Open/Closed Status Month NCR Opened Current Status As of June 29 th Previous Month NCR Summary 22 Open 45 Closed

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 6 Procedure Status 70 documents total 69 latest versions submitted for sign-off 67 are released

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 7 Procedure Status (1 of 1) – Management

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 8 Upcoming I&T Events –CAL/TEM Installation in Bay 5 (Complete) –CAL/TEM Installation in Bay 1 (Complete) –4 Tower Tests (Complete) –Receive TEM/TPS 3 and 4 (Complete) –Receive TKR 4 (Complete) –STR #14, 15 ECD 7/5 –SVAC data taking for 6 towers ECD 7/15

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 9 I&T Detail Schedule (1 of 3)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 10 I&T Detail Schedule (2 of 3)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 11 I&T Detail Schedule (3 of 3)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 12 I&T 6 Month Look Ahead (1 of 2)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 13 I&T 6 Month Look Ahead (2 of 2)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 14 SAS Interfaces SVAC is happy with CCB process –Thanks Richard Code release is getting more stable and reliable –Working with SAS to sharpen validation procedures –specially calibrations Pipeline issues are more infrequent –We expect to transition into a more robust architecture in a not so distant future –Ought to be tailored to the ISOC needs

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 15 Data Analysis Issues (up to 4 tower data) Hardware failures or problems –None so far !!! Kudos to the “royal we” Anomalies in offline distributions –Becoming less frequent and mostly due to –Incorrect configurations (mostly operational procedures) –Mistakes in the offline data analysis codes Understanding how the instrument works –Requires a much broader knowledge of –Integrated detector system functions and performance –LAT configuration (needs to be configuration controlled) –Details of complex offline software –How the analysis parameter space changes as we add more towers

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 16 Feedback to Operations: Procedures SVAC automated reports identified that GEM was not reporting trigger information properly for some of the 4 tower tests Action –stopped data taking to investigate root cause (Eduardo) Root cause –incorrect power up of system –found by Horwitz and confirmed by Huffer Recommendation to I&T –Improve procedures –Introduce online control plots during data taking

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 17 Understanding Performance: Deadtime Warren Implemented an offline variable to measure time without being affected by roll over of counter Measured deadtime in several configurations –Working to understand numbers

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 18 Do we have enough data yet? One tower Two towers –End-to-end cosmic ray data –To exercise trigger and data flow capabilities –SVAC cosmic ray data –To perform calibrations –To do performance studies that require large statistical sample Four towers to Sixteen towers (prior to ACD integration) –Only planned to collect SVAC data –May request some tests (most likely between 6 and 8 towers) to –Configure the instrument to take data with 2 Trigger Engines (simulate on-orbit operation) –Study nominal/high rates with TEM diagnostics OFF –Understand TKR one-shot behavior –Study TKR cable FIFO errors (caused by induced showers)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 19 Issues & Concerns ISSUES Availability of flight assembly hardware. –Shortages identified by I&T and being worked with Subsystems. Flight Cables –TKR –SIU & EPU CONCERNS Additional I&T manpower for Online, SVAC and IFCT. TPS rework and replacement, availability for future tower installations.

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 20 Cost/Schedule Reports for Presentation May 2005 Month End Integration & Test Gamma-ray Large Area Space Telescope

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 21 Level 3 Milestone Count

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 22 Level 3 Milestone List

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 23 Milestone Variance Explanation Schedule Impact –30 days due to late delivery of hardware Cost Impact –No cost impact Corrective Action –Evaluate system level test definition and durations. –Use 7/24 schedule as required for system level test to minimize test duration.

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 24 Cost Report

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 25 Cost Variance Explanation Why overrun/underrun? –Fly away instrumentation costs haven’t been recorded –Vacations What will be done to correct? –No action required

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 26 FTE Report (DOE/NASA-funded only)

GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 27 FTE Variance Explanation Why overrun/underrun? –Vacations What is the impact? –None –Potential future impact when hardware arrives. What will be done to correct? –Moving 1 FTE from ELX to I&T –Hire production control person.