HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009
College Development Plan Schedule Project Bids receivedJanuary 31, 2008 Project bid accepted & funding strategy adopted February 27, 2008 Notice of Award issuedFebruary 28, 2008 Contracts executedMarch 2008 Pre-Construction MeetingMarch 20, 2008 Notice to Proceed issuedApril 2, 2008 ConstructionApril 2008–Aug 2010
Child Development Lab Community Education Center Fitness & Recreation Center Receiving & Storage Building Student Commons Addition Instructional Commons North
Building Substantial Completion Receiving & Storage Bldg December 4, 2008 Child Development LabJanuary 16, 2009 Community Ed Center 1 st FloorAugust 3, 2009 Community Ed Center 2 nd FloorFebruary 19, 2010 SCB AdditionFebruary 1, 2010 Instructional Commons NorthDecember 18, 2009 Fitness & Recreation CenterMay 10, 2010 SCB RemodelAugust 2, 2010 Site Development – As needed to progress with building construction
Building Ready for Use Receiving & Storage BuildingDec 15, 2008 Child Development LabFeb 2, 2009 SCB Addition March 10, 2010 Community Education Center April 1, 2010 Instructional Commons NorthMay 15, 2010 Fitness and Recreation Center June 1, 2010 SCB Remodel August 24, 2010 Project CloseoutDec 31, 2010
Contracted Services Timeline Food Service and Bookstore Open Operations in New Space March 15, 2010