Comment on the LHCb upgrade cooling plan Paolo Petagna Meeting on CO 2 Cooling CERN 11 March 2015.

Slides:



Advertisements
Similar presentations
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Advertisements

Life at Two Lakes: Through the Seasons. Starting Questions You are going to be shown pictures from two lakes throughout the year. You are going to be.
DCal Meeting
LHC Crab Cavities - Phase 1 - Schedule 2008 Mini Workshop - reminder Activities & Planning Planning Remarks 1 LHC-CC09, 3rd Crab Cavity Workshop - Session.
P. Tropea for the PH-DT CO 2 team CO 2 CERN 11 March 2015 CO 2 cooling activities in PH-DT.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
3 Dec 2003Market Operations Standing Committee1 Market Rule and Change Management Consultation Process John MacKenzie / Darren Finkbeiner / Ella Kokotsis,
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
© 2010 Chevron A Day in the Life of a Project Manager Presented by Nancy Grossman, Project Manager Presented to Chabot College Engineering Class September.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
LHCb CO 2 cooling meeting Burkhard Schmidt – February 18,
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
Concept idea for the modular 2PACL system for the Atlas ITK 3 June 2015 Bart Verlaat 1.
IT-4082 Design, Supply, Installation and Commissioning of the ventilation of the BAF3 building Alexandre Broche EN-CV-PJ.
TRACI V3 Status & Delivery Plans UPDATE Paolo Petagna LHCb CO2 cooling meeting Apr 15 th, 2015.
Space, labs & testing equipment Paolo Petagna Meeting on CO 2 Cooling CERN 04 February 2015.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
LHCb upgrade cooling Paolo Petagna Meeting on CO 2 Cooling CERN 11 March 2015.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
APA CONTRACTS TO POST-2017 ALLOTTEES July 24 - Letter to all Allottees Inviting Comment August 10 - Allottee Response August 21 - Workshop August 28 –
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
CLIC - CDR Status (Volume 2) Hermann Schmickler, ILCW2010.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
LHCb-UT and Velo Upgrade Road to a system EDR in Q June 2015 Bart Verlaat 1.
UK Cansat Competition 2014 Teachers’ workshop. 1.How did we get here? 2.Workshop schedule and housekeeping 3.Competition guidelines – Reporting – “Launch”
EP-DT roadmap towards CO 2 cooling of "phase-2" detectors Paolo Petagna (CERN PH-DT)
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
CO 2 Cooling Plants for the LHCb upgrade LHCb infrastructure workshop February Burkhard Schmidt With input from Bart Verlaat, Paolo Petagna and Lukasz.
1M. Battistin M. Battistin CERN EN/CV/DC 9 th July 2009 CO2 kick-off NIKHEF - Cooling activities organization at CERN 9 th July 2009.
NA61/SHINE run schedule/plans:
Cryogenic Plant Controls – Cost and Schedule
DT-LHCb coordination meeting 18 April 2016
Deadline for Requisitions Payment Processing Date
Teleconference ACS – FREIA 17th October 2017
M. Battistin CERN EN/CV/DC 9th July 2009
Olof Bärring LCG-LHCC Review, 22nd September 2008
Teleconference ACS – FREIA 31st October 2017
LHCb & EYETS
MicroMegas Mechanical Meeting --- Cern April 2014
Mauro Morandin & Antoine Daël
Key Information Summary (KIS)
2K CB FDR Overview:  Agenda, Charge, Review Process
X-ray Pump-Probe Instrument
Experience with an IT Asset Management System
Potential Milestones A timeline to finish in one year
Welcome & Charge for the Meeting
Eurostat regional yearbook 2012 – new routines and time planning
Overall Project RAG Status:
Release 3 Scope & Proposed Plan
February 2007 Note: Source:.
Review plan of the nature reporting – update 6
LCLS-II Cryoplant Controls Workshop.
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
CO2 progress and issues on the control systems
East Hall under construction
2015 January February March April May June July August September
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Comment on the LHCb upgrade cooling plan Paolo Petagna Meeting on CO 2 Cooling CERN 11 March 2015

LHCb upgrade cooling | 11 March Timeline as presented at the Workshop (excerpts) Schedule driven by: –the LHC schedule, –the LHCb upgrade plan and –the availability of resources in PH-DT 2015: by summer: Concept P&ID 2015: by September: P&ID doc and first Functional Analysis 2015: October: Cooling EDR 2016: by September: Detailed 3D design of hardware 2016: October: Cooling PRR 2016: October: Launch production of Transfer Lines and Junction Box 2017: by end of EYETS (18 weeks): Install T.L. and J.B. 2017: Along the year: Plant construction 2018: by June: Install cooling systems in UXA 2018: by December: Commission the cooling systems “stand alone” 2019: July – December: Commission Velo and UT with cooling Design effort in 2015/2016 Construction 2017 Installation and start of commissioning in 2018 Complete F.A. Seen as critical! Hard deadline! X 2 Includes electrical cabinets + software

LHCb upgrade cooling | 11 March Comment The Timeline was discussed internally by the PH-DT CO2 team on March 11 th. It was felt that the proposed date of October 2016 for a single PRR might place on a critical path the production of the Transfer Lines, due for installation in Q1 2017, as well as the procurement of few specific components for the plant, known to have very long lead time for delivery. It is therefore suggested to split the 2017 reviewing process in two: 1.A preliminary review around May with a limited scope and the goal of unblocking the procurement procedures for the Transfer Lines and for some specific plant components clearly identified (e.g. the pump); 2.A final PRR in October when the complete design is presented (including the full 3D model of the hardware and the Functional Analysis). The approval of this second PRR will unblock the procurement of all plant components and the extraction from the 3D model of all the fabrication drawings.