St. Cloud High School Phased Comprehensive Construction Project April 28,
Design – Phase 1 Early Work Demo Building 3 Building 4 Building 5 Misc Modular Building 15 Building 6 3, April 28,
Design – Phase 1 New Buildings New Building 3 Story Classroom + Media Central Plant New Gym 7 New Cafeteria 9 Remodel Outdoor Dining 28 Admin 22 3 Story Classroom + Media Remodel Admin 22 Dining New Cafe. 9 Demo Building 10 Gym 7 Central Plant Remodel Admin 28 Demo Bldg. Build 10 April 28,
Design – Phase 2 Work New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 12,13 Classroom New 2 Story Classroom 8 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational Classroom April 28,
Final Master Plan Design Classroom ,000 SF Existing Class ,190 SF Vocational ,800 SF Existing Lab ,474 SF Gym ,800 SF Total Gross SF 279,341 Admin ,917 SF Auditorium - 2 Music 35,360 SF Dining / Kitchen ,800 SF Classroom ,000 SF April 28,
Project Curriculum Classroom ,000 SF Existing Class ,190 SF Vocational ,800 SF Existing Lab ,474 SF Gym ,800 SF Total Gross SF 279,341 Admin ,917 SF Auditorium - 2 Music 35,360 SF Dining / Kitchen ,800 SF Classroom ,000 SF April 28,
Project Curriculum April 28,
Design Images Auditorium, North Elevation April 28,
Design 3 story Classroom & Media Center, East Elevation April 28,
Design Cafeteria/ Kitchen + Phase 3 Classroom Building, West Elevation April 28,
3, Schedule – Phase 1 Early Work + Site work Demo Building 3 Building 4 Building 5 Misc Modular Building 15 Building 6 Schedule Early Works May, 2009 Aug, 2010 Site / Civil Work & Underground Infrastructure Wet Retention Ponds April 28,
Schedule – Phase One New Buildings New Building 3 Story Classroom + Media Central Plant New Gym 7 New Cafeteria 9 Remodel Outdoor Dining 28 Admin 22 3 Story Classroom + Media Remodel Admin 22 Dining New Cafe. 9 Demo Building 10 Gym 7 Central Plant Remodel Admin 28 Demo Bldg. Build 10 EWP Phase 1 June, 2009 Schedule Aug, 2010 April 28,
Schedule – Phase 2 New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule April 28,
Schedule – Phase 2, Student Access New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule STUDENT ACCESS April 28,
Schedule – Phase 2, Student Access New Building New Performing- Arts 2 New Vocational 5 New 2 Story 8 Demo Building 1,2,7,8, 9,11,12,13,14 Remodel 21 Science 25 Classroom Demo Dining Food 2 Demo 1 New Performing Arts 2 Arts 2 Remodel Admin 22 Dining Cafeteria 9 Demo 12,13,14 Classroom New 2 Story Classroom 8 Demo 7,8,9,11 From Previous Phase 3 Gym 7 Central Plant Science 21 New Vocational 5 EWP Phase 1 Phase 2 June, 2010 Aug, 2011 Schedule April 28, STUDENT ACCESS
Schedule – Completed Master plan Classroom ,000 SF Existing Class ,190 SF Vocational ,800 SF Existing Lab ,474 SF Gym ,800 SF Admin ,917 SF Auditorium - 2 Music 35,360 SF Dining/Kitchen ,800 SF Classroom ,000 SF EWP Phase 1 Phase 2 Aug, 2011 Schedule May, 2009 April 28,