THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team LIU-2011November 25, 2011CERN.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Expected performance in the injectors at 25 ns without and with LINAC4 Giovanni Rumolo, Hannes Bartosik and Adrian Oeftiger Acknowledgements: G. Arduini,
1 Methods of Experimental Particle Physics Alexei Safonov Lecture #8.
Review of 2011 studies and priorities for 2012 LIU-SPS-BD.
Outcome from 2011 Chamonix workshop New structure of the SPSU Study Group E. Shaposhnikova /02/20111SPSU meeting.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Status of the PSB 2 GeV Upgrade and the RCS Study SGUI Meeting B. Mikulec, 07 July 2011.
Summary and outcome of the 1st LIU-HL-LHC brainstorming meeting (24 th June 2011) Mike Lamont This event is jointly organized by the HL-LHC and LIU projects.
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
1 Chamonix 2010 Summary of Session 7: Future Upgrade Scenarios for the Injector Complex P. Collier /BE (V. Mertens /TE) Chamonix Summary, 5th Feb 2010.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
HL-LHC Project Kick-off Meeting Friday 15 th April 2011 Sylvain Weisz DG-DI-DAT on the behalf of the A&T Sector Projects Support Office.
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
TS, Length of YETS EYETS LIU & CONS Project
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Linac4 Overview M. Vretenar, SLHC Meeting, Motivations 2.Layout 3.Main parameters 4.Schedule 5.Status.
HL-LHC/LIU Joint workshop Goal: Progressing towards an agreed set of 450 GeV beam parameters for High Luminosity operation in LHC after LS2 & LS3. Slides.
June 23, 2005R. Garoby Introduction SPL+PDAC example Elements of comparison Linacs / Synchrotrons LINAC-BASED PROTON DRIVER.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Update of achievable beam characteristics at injection in LHC H.Bartosik, C.Bracco, O.Brüning, C.Carli, K.Cornelis, H.Damerau, R.Garoby, S.Gilardoni, B.Goddard,
R.G. 7/09/20101 Options for neutrinos. R.G. 7/09/20102 Conventional beam from the SPS (1/3) Neutrinos using the SPS Nominal CNGS 732 km baseline from.
R. Garoby 3/03/2006PAF progress1 PAF Progress 3/03/2006 M. Benedikt, R. Garoby, F. Ruggiero, R. Ostojic, W. Scandale, E. Shaposhnikova, J. Wenninger 
0 1 Alternative Options in the Injectors – Preliminary Summary H. Damerau LIU-TM#8 18 October 2013 Many thanks for discussions and input to T. Argyropoulos,
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
STATUS OF THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team March 6, 2012CERN.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The Stripping Foil Test Stand in the Linac4 Transfer Line
THE LHC INJECTORS UPGRADE PROJECT - Organisation Malika Meddahi for Roland Garoby and the LIU Project Team.
Linac4 Status 1 M. Vretenar sLHC public event
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
Planning & Installation meeting New working group EDMS th October 2014LIU PLI meeting - J.Coupard1.
E.M, PS-OP shut-down lectures, 20/02/ u Requirements of the LHC on its injectors u What are the nominal & already achieved beams at PS exit? u How.
Some ideas for/from the SPS LIU-SPS team. Scrubbing (only) for ecloud in SPS? aC coating remains baseline..... –but scrubbing has many potential advantages.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
EU accelerator contributions to the IDS … R. Garoby ISS meeting RAL 28/04/2006.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Machine Progress Towards Higher Luminosity Frank Zimmermann CMS Upgrade Meeting FNAL, Chicago, 7 November 2011 (via EVO) Thanks to Martin Aleksa, Gianluigi.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
EVOLUTION OF BEAM CHARACTERISTICS DURING THE LIU PROJECT R. Garoby for the LIU Project Team March 7, 2012CERN.
Pushing the space charge limit in the CERN LHC injectors H. Bartosik for the CERN space charge team with contributions from S. Gilardoni, A. Huschauer,
Introduction R. Garoby LIU 2014April 11,  LIU summary  LIU Highlights in 2013  Outcome of the «Review of LHC and Injectors Upgrade Plans» (Oct.2013)
LIU-PSB Overview K. Hanke for the LIU-PSB Working Group K. Hanke, LIU-2011, 25 Nov 2011.
High Intensity Beams in Existing Accelerators for CN2PY: SPS studies, PS issues E. Shaposhnikova Laguna-LBNO General Meeting CERN, Acknowledgments:
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
Research progress and plan CERN-KEK Committee, 2nd meeting 07/Dec/07 Masamitsu AIBA CERN-Japan fellow, AB/BI.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LHC Injectors Upgrade Project 11/11/2010 R. Garoby.
LIU Day 2014 – M.Bodendorfer - LEIR model. LEIR model A plan for understanding/upgrading the LEIR performance limitations M.Bodendorfer BE/ABP & LEIR.
LIU-PS Beam Dynamics Working Group Introduction and objectives
ICE SECTION The coolest place to be! Elias Métral
LIU Workpackages 1 August 2014 Edms Id LIU-PM-PP-0030
Alternative/complementary Possibilities
Alternative/complementary Possibilities
Plans for ions in the injector complex D
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
LIU, ABP-CWG, PBC, miscellaneous
Update on the HiLumi/LIU parameters and performance ramp up after LS2
LIU project M. Meddahi LIU Project Team: G. Rumolo, J. Coupard, H. Damerau, A. Funken, S. Gilardoni, B. Goddard, K. Hanke, A. Lombardi, D. Manglunki, B.
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Generation of Higher Brightness Beams for LHC
SLHC-PP kick-off meeting, CERN 9 April 2008
Summary of session 9: "LHC Injectors Upgrade"
LHC Machine Advisory Committee, CERN 12th June 2008
Presentation transcript:

THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team LIU-2011November 25, 2011CERN

IntroductionIntroduction Project Management Anticipated Performance Goals Planning Summary

R.G. 3 LIU-2011– 25/11/2011 Goals & Means Mandate “The LHC Injectors Upgrade should plan for delivering reliably to the LHC the beams required for reaching the goals of the HL- LHC. This includes LINAC4, the PS booster, the PS, the SPS, as well as the heavy ion chain…” Implementation The LIU Project will:  Analyze the status of the injectors and the HL-LHC requirements,  Propose an upgrade path for the injectors, exploiting the work done by the Task Forces on the „PSB energy upgrade“ and „SPS upgrade“ and by the Working Group on the SPS upgrade,  Organize the upgrades (WBS with resources and planning) and take care of their implementation,  Take care of hardware and beam commissioning.

R.G. 4 LIU-2011– 25/11/2011 To increase performance (soon extended for heavy ions) Brightness   Increase injection energy in the PSB from 50 to 160 MeV, Linac4 (160 MeV H - ) to replace Linac2 (50 MeV H + )  Increase injection energy in the PS from 1.4 to 2 GeV, increasing the field in the PSB magnets, replacing power supply and changing transfer equipment  Upgrade the PSB, PS and SPS to make them capable to accelerate and manipulate a higher brightness beam (feedbacks, cures against electron clouds, hardware modifications to reduce impedance…) To increase reliability and lifetime (until ~2030!) (tightly interleaved with consolidation)  Upgrade/replace ageing equipment (power supplies, magnets, RF…)  Procure spares  Improve radioprotection measures (shielding, ventilation…) Basic Principles

R.G. 5 LIU-2011– 25/11/ Consolidation… Baseline Upgrade Actions Construction of LINAC4 PSB/PS/SPS Management Beam dynamics Magnets RF systems Power converters Beam instrumentation Beam intercepting devices Vacuum Injection system Ejection system and transfer line to PS/SPS/LHC Controls Electrical systems Cooling and ventilation Installation, transport and handling Civil Engineering Radioprotection Machine interlocks Alarms Access system Survey Commissioning Dismantling «Typical» list of Work Units Upgrades of PSB, PS and SPS All equipment and service groups are involved!

Introduction Project ManagementProject Management Anticipated Performance Goals Planning Summary

R.G. 7 LIU-2011– 25/11/2011 LIU Project Mandate (continued) … The project co-ordinator will have the responsibility for the project management (WBS, technical co-ordination and integration, manpower and budget agreement with the departments as well as budget and timescale control). They will report on a regular basis to the Director of Accelerators and Technology. The executive role for manpower and budget for the projects/studies remains with the technical groups in the departments. Source: Project Management case study – P. Bonnal, M. Meddahi LIU Project Planning and Costing

R.G. 8 LIU-2011– 25/11/2011 LIU-PSB coordination team K.Hanke – Activity leader B.Mikulec – Deputy V.Raginel – Scientific secretary /liu-project/liu-psb/ LIU- PS coordination team S.Gilardoni – Activity Leader H. Damerau– Deputy and Scientific secretary h/liu-project/liu-ps/ LIU-SPS coordination team B.Goddard E.Shaposhnikova – Deputy G.Rumulo – Scientific secretary liu-project/liu- sps/default.aspx LIU-Project Safety coordination L. Ponce Director of Accelerators and technology - Steve Myers LIU Project team Roland Garoby (Project Leader) - Malika Meddahi (Deputy) - Brennan Goddard (LIU-SPS machine coordinator) - Simone Gilardoni (LIU-PS machine coordinator) - Klaus Hanke (LIU-PSB machine coordinator) - Maurizio Vretenar (Linac4 Project Leader)- Laurette Ponce (Project Safety Officer)-Django Manglunki (LIU-Ion chain coordinator) Linac4 Project M.Vretenar project.web.c ern.ch/linac4- project/ LIU Administrative Support: Cécile Noels, Nadine Audrey. Project Support: Pierre Bonnal, Sylvain Weisz, Tadeusz Kurtyka - EVM coordinators: De Jonghe, Benoît Daudin Project Organization Breakdown Structure

R.G. 9 LIU-2011– 25/11/ by EDMS team and Project Support Office Templates and document handling and lifetime Quality Control Indico

R.G. 10 LIU-2011– 25/11/2011 Work Breakdown Structure

R.G. 11 LIU-2011– 25/11/2011 WORK IN PROGRESS WUs dictionary defined for all LIU machines - resources, schedule and deliverables Budget Control – (APT by J. De Jonghe, B. Daudin)

Introduction Project Management Anticipated Performance GoalsAnticipated Performance Goals Planning Summary

R.G. 13 LIU-2011– 25/11/2011 Basic assumptions  Beam parameters are given at injection in LHC: beam loss and blow-up inside the LHC are not accounted for.  All necessary improvements are implemented in the injectors (Linac4, PSB to PS transfer at 2 GeV, coupled bunch instabilities suppressed, e- cloud suppressed, hardware upgraded…)  Estimated beam degradation in the accelerator chain (based on observations in 2010): PS: 5 % beam loss, 5 % transverse blow-up SPS: 10 % beam loss, 5 % transverse blow-up.  RF gymnastics being kept, imperfections are unchanged: +-10 % fluctuation of all bunch parameters within a given PS bunch train. Traces of ghost/satellite bunches.

R.G. 14 LIU-2011– 25/11/2011 H/V transverse emittances [mm.mrad] Bunch intensity within constant longitudinal emittance [x10 11 p/b] Constant transverse density (Space charge) Nominal performance Today (2011) Beam parameters at LHC injection [50 ns] SPS single bunch limit HL-LHC requirement at 7 TeV Anticipated performance after LIU

R.G. 15 LIU-2011– 25/11/2011 H/V transverse emittances [mm.mrad] Bunch intensity within constant longitudinal emittance [x10 11 p/b] Constant transverse density (Space charge) Nominal performance Today (2011) Beam parameters at LHC injection [25 ns] HL-LHC requirement at 7 TeV SPS single bunch limit Anticipated performance after LIU

Introduction Project Management Anticipated Performance Goals PlanningPlanning Summary

R.G. 17 LIU-2011– 25/11/2011 Comments  LIU performance goals in terms of beam characteristics at injection in the LHC have to meet the needs of HL-LHC and to be feasible... Subject of active interactions between HL-LHC and LIU teams (2 nd joint «Brainstorming» session on January 24, 2012).  MDs until the end of 2012 will help refine the knowledge and understanding of the injectors and check the potential of upgrades.  End 2012/beginning 2013, the performance goals of the LIU project will be specified and the precise list of hardware modifications with their specifications will be issued.

R.G. 18 LIU-2011– 25/11/2011 Planning Linac4PS injector, PS and SPSBeam characteristics at LHC injection Continuation of construction… Beam studies § simulations Investigation of RCS option Hardware prototyping Test of new beam gymnastics Design § construction of equipment TDR 25 ns, p/b, ~3 mm.mrad 50 ns, p/b,  2 mm.mrad 2013 – 2014 (Long Shutdown 1) Linac4 beam commissioning Modifications and installation of some prototypes in PSB, PS and SPS Design § construction of equipment Progressive increase of Linac4 beam current Implementation of new PS beam gymnastics… PSB modification and connection to Linac4 during extentended winter shutdown If/when Linac4 connected: progressive increase of PSB brightness with benefits for PS and SPS. Equipment design § construction for PSB, PS and SPS Beam studies Possibly smaller emittance (25 ns) with new PS beam gymnastics… Limited gain from Linac4 proper (pending PSB, PS and SPS hardware upgrades) 2018 (Long Shutdown 2) Extensive installations in PSB, PS and SPS Hardware commissioning 2019 –2021 Beam commissioningAfter ~1 year of operation: beam characteristics for HL-LHC…

Introduction Project Management Anticipated Performance Goals Planning SummarySummary

R.G. 20 LIU-2011– 25/11/2011 Summary The goal of the LIU project is to make the LHC injector complex capable to reliably deliver the higher performance proton and ion beams required for High Luminosity in LHC until later than Performance for other users will at least be preserved and generally benefit (e.g. high intensity). More MDs will take place in 2012 to finalize the hardware modifications and their precise specifications. The implementation of hardware modifications will finish during LS2. All equipment and service groups are concerned!

Reference

R.G. 23 LIU-2011– 25/11/2011 Why is today’s beam better than nominal? Simple! No more blow-up along the accelerators cascade… PSB: Improved (achromatic) optics in the Linac2 to PSB transfer line since 2005 [ PS: Injection trajectories Working point along the whole cycle Transition PS to SPS: Transverse matching with better optics in TT2-TT10 WARNING: NO MARGIN LEFT!