RSRDC UNIT - KOTA
ORGANISATION CHART OF RSRDC - UNIT KOTA
Financial Work Load in Unit FINANCIAL WORK LOAD IN UNIT KOTA S. No. Name of Work Client Deptt. A& F Sanction Expendit ure till date Balance Work ARE – I Sh. Ashu kumar Garg 1 Construction of RTU Kota RTU, KOTA RTO, Kota RTO Const. B. wall Ummedganj. Kota Agr. Uni. Udaipur Police chowki Jagpura Police Deptt Transit Hostel range H. Q. Kota Police Deptt CFC at Kaithoon RUDA MOU Signed Academic block KUK, Kota Mou Under finalisation TOTAL
S. No. Name of Work Client Deptt. A& F Sanction Expendi ture till date Balance Work ARE II- Sh. Basant Kumar Gupta 1 Police Residential Qtrs. Kota Police Deptt ROB Morak LC No. 87 PWD Police Chowki at Indira Vihar Kota Police Deptt Police Chowki at Bajranj Nagar Kota Police Deptt Administrative block SIAM MOU Signed TOTAL TOTAL OF UNIT
RAJASTHAN TECHNICAL UNIVERSITY, KOTA Completion cost – lacs Foundation Stone laid by Hon’ble Chief Minister on Completed in June Important Works Completed during last 5 years
Important Works Completed during last 5 years KOTA UNIVERSITY, KOTA Completion cost – lacs Foundation Stone laid by Hon’ble Governer of Rajasthan on & Inaugurated by Hon’ble Education Minister on dated
Important Works Completed during last 5 years RFSL BUILDING,KOTA Completion cost – lacs Completed in year
POLICE HOUSING SCHEME No. of Quarters:76 Nos. (16 USQ+60 LSQ) Total Cost: Crores Location:Police line, Baran road, Kota Date of Start: Stipulated Date of Completion: Expenditure till Date: Likely Completion date: Bottlenecks if any:No. Note: Bar Chart of Important works may also be attached
Name of Work: ROB Morak L C No. 87 Total Cost:18.08 Crores Location:Near Morak Dabadeh R. Mandi Date of Start: Stipulated Date of Completion: Expenditure till Date: lacs Likely Completion date:Dec Bottlenecks if any:LA completed in Nov.2009 Revised drawing under approval from Railway
POLICE CHOWKI JAGPURA Total Cost:11.00 Lacs Location: Jagpura Date of Start: Stipulated Date of Completion: Expenditure till Date:3.35 Lacs Likely Completion date:Dec Bottlenecks if any:Delay in drawing finalisation.
BOUNDRY WALL OF UMMEDGANJ,KOTA Total Cost: Lacs Location: Ummedganj (Kaithoon road) Date of Start: Stipulated Date of Completion: Expenditure till Date: Lacs Likely Completion date:Jan.,2010 Bottlenecks if any:Delay due to seepage.
TRANSIT HOSTLE RANGE HEAD QTR KOTA Total Cost:30.00 Lacs Location: KOTA Date of Start: Stipulated Date of Completion: Expenditure till Date:1.02Lacs Likely Completion date:Feb.2010 Bottlenecks if any:No
Proposed New Works S. No. Name of Work Client Deptt. Mode Estimated Cost 1 Construction of academic block UOK,KOTA Actual plus 540 Lacs 2 Construction of CFC at KAITHOON RUDA,JAIP U Actual plus 100 Lacs 3 Construction of Administrative Building SIAM,KOTA Actual plus 100 Lacs