9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage https://edms.cern.ch/document/593278/

Slides:



Advertisements
Similar presentations
Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Advertisements

SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
M.N Minard SPD cabling overview SPD cable chain & tray SPD cable chain & tray Motorisation PS/SPD Motorisation PS/SPD Work on PS Work on PS.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Walls crates cables gas chambers electronics CERN adb.
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
14 February 2006A.Ciocio - ID Week1 SCT Services Procurement & Installation Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing MTF Workpackage.
Upgrade news and Proposed interventions during YETS for the Muon Barrel Alignment Szillási Zoltán, Béni Noémi (ATOMKI ) This project is supported by Hungarian.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M. Gilchriese - April 2001 Disk Sector Status. M. Gilchriese - April Technical Status Three prototypes to current dimensions(8-sector disks) except.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
TE/MPE/EE J. Mourao T/MPE/EE 23 December 2012 LHC Machine Redundant Power supply (DQLPUR) & interface Module (DQLIM) assembling during LS1.
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
Status of NA62 straw electronics Webs Covers Services Readout.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary.
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
V. Bobillier1 Cable installation status.
31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Comments on Engineering talk by A. Catinaccio at Inner Tracker Engineering Meeting CERN ) Fixed length barrel layout drawing by C. Bault (Strawman.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
A few points that need discussion today (Gerard) UH needs golden front boards (2?), golden HVB (1), and HV cabling to PS with the correct connectors. IU.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Mauro Citterio - Mi meeting
Service channels between Tracker and PP1
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
Chamber Design and Integration RE3/1 and RE4/1
Nearly the end of a long story...
LS1 status 24/03/2014.
CNGS horn / reflector in 2005: The story of the glass ring insulator
CSC Electronics Installation and Commissioning CSCE I&C
Presentation transcript:

9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage

9 May 2006A.Ciocio - SCTSG2 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of doubles harnesses completed (last week) –2125 double harnesses (4250 cables) Installation –All racks in US side + 2 USA racks were installed last year by TC teams (Russian) –Installation resumed at the end of March with a new TC team (French) –Very slow startup –Completion of USA side was expected by the end of May –Unlikely even with 2 teams (2 shifts) and with participation of Russian teams Connector in situ (CPE) –All cables (except for a few) in US15 completed on March 10 –Most racks are tested –Very good yield –2 techs returned on April 18 and currently working on one USA rack –Complete US side and continue racks in USA15 when full team will be back Racks on Level 6 US side

9 May 2006A.Ciocio - SCTSG3 PP PP3 units needed –173 are spares –139 empty shield cases –Standard subracks of 30 units –Mini subracks (of 5 units) –Special subracks (PP3 + empty cases) Layout of each rack can be found at: Much of the installation done but lots of work to complete all racks: –Most of subracks installed –Some subracks sitting by racks to be installed –Small fraction of cables partially plugged in –Rework for damages (due to installation) Parts missing: –4 standard subracks –3 special subracks –2 mini subracks –Outer shells –80 PP3 units Schedule still unknown but promised soon – NEED last parts ASAP

9 May 2006A.Ciocio - SCTSG4 Type II-III by Sector S5 S3S7 S1S9 S15S11 S13 US PP3 racks USA PP3 racks 384 Barrel 494 EC 384 Barrel 494 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC Level 7 Level 6 Level 2 Level 8 Level 5 & 2 Level 1 & 2

9 May 2006A.Ciocio - SCTSG5 SCT Services Sequence Sector 5 (top) and Sector 13 (bottom) –heater cables, and DCS cables (completed) Sector 9 - Installation completed on May 1 –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (EC) Sector 3 - Installation started May 2 – two weeks to complete –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sector 1 next – can start this week to allow parallel team work –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (Barrel) Sector 7 – Lengths measured – Length will be sent to company this week –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sectors 11, 15 – Double harnesses length sent to company to fabricate – SCT cables (336 Barrel, 247 EC) – Fibre cables (9 EC,18 Barrel) Installation sequence in a sector is: –Tubes, fibres, heater cables, SCT cables, (Muon chambers), –TRT cables, pixel cables

9 May 2006A.Ciocio - SCTSG6 Type II/III & PP1 – Production INEO/Thurmelec are making type II-III cables in 2 steps: 1.double length harnesses as they receive information about the lengths type II cable and type III spliced type II FCI/JST connectors on both ends of double harness 2.Single length cables with FCT connector (PP3) are produced when length finalized with test cable measurement from cryostat to PP3 racks sector by sector Delivery rate reached the promised: 400 cables/week We are ahead with cable preparation! So far good quality No fatal defect found on some cables (the color coat is gone is some section/pattern but kapton insulation OK) PPB1 – clamps, clips, cable tray covers were late, not used yet during installation –Clamp mounting finalized today –Clip under revision PPF1 – most parts available –Found the best way to crimp group of drain wires in a ferrule and catch the ferrule with the grub screws into clamp’s holes

9 May 2006A.Ciocio - SCTSG7 Type II/III cables – Installation About 1000 cables installed ½ bundle /day/side/team 48 cables/day but can reach 100 in the future Problem with testing related to the grounding in cryostat (OK) Mechanical problems to fit layers of 6 cables between clamp holder pins (all cables installed have been retrofit) Clamp installation Barrel today EC final Details given in April SCTSG

9 May 2006A.Ciocio - SCTSG8 SCT Readout Cables - Status All 18 (SCT readout) cables for end-cap in sector 9 installed and tested, all OK (this was the first sector with SCT fibre cables). 18 barrel cables installed in sector 3 during last two weeks (9 on side A and 9 on side C). These were the first SCT barrel readout cables installed. Barrel cables are quite fragile due to a 3 meter long strip-back of the cable cladding at the end of the cables. No serious problems were encountered during the installation. The cables need to be tested, probably with the help of people coming from Oxford. 9 end-cap cables in sector 3 will be installed in the next phase, perhaps this week (6 cables on side A and 3 cables on side C). Sector 1 should be installed afterwards. There are 18 end-cap cables and no barrel cable.

9 May 2006A.Ciocio - SCTSG9 FSI delivery cables and tubes 38 cables The first FSI delivery cable cut and prepared for the installation in sector 3. The length of the cable taken from the EDH table. After the first cable is installed, 8 more cables will be cut, labeled and installed (i.e. all cables for sector 3). The lengths to cut will be determined from the first cable. The first FSI tube is going to be bent, cut and installed this week by the technicians. The drawings of the tubes are not precise and needed some modifications to respect the real situation on the cryostat flange

9 May 2006A.Ciocio - SCTSG10 SCT DCS Cables 128 type II and 40 type IV All cables for the barrel are in the pit and ready for installation Sector 13: 24 cables are installed and tested Sector 5: 24 cables are installed and tested 3 cables in sector 5 were damaged during installation (caught on sharp edge of cable tray) – repaired 20 cables to be installed in sector 3 are ready but installation should occur soon Installation of SCT DCS cables interleaved with ID DCS cables

9 May 2006A.Ciocio - SCTSG11 Installation & Testing Activities Type IV (2 people + Petr + Prague) –Acceptance test –Test in rack after installation –Test of cut cables after connector in situ work –Plug-in cables into PS crates – test with feedtrough Type II-III Preparation (5 people + Vlastik + Kuo Ming) –Acceptance test (partial) –Visual inspection –Folding the shield and cut it the right amount, fix it –Organize boxes with right cables to send following installation sequence Type II-III Installation(2 people: Lars & Neil part time + Jacek) –Mount dPPB1 and dPPF1 –For Barrel: Squeezing the cables to fit between pin and clamp holder Plug-in of the delicate JST/FCI connectors to dPPB1 Placing the clamp (now), placing the clip (later) –For Endcap: crimp group of drain wires in a ferrule and catch the ferrule with the grub screws into clamp’s holes Plug in the dPPF1 Type II-III Testing (Alexandre + 1 person) PP3 (Scott was here for 2 months – need 2 people now) –Burn-in of units –Assembly into subracks –Installation into racks of subracks –Plug-in the cables to PP3 Final test of whole chain (2 people)

9 May 2006A.Ciocio - SCTSG12 Issues PP3 –Damaged In the pit left by racks –Damaged In the racks after installation/plug-in of type IV by French team –Parts to finish assembly and installation too late Connector damage –In US15 they are left too long on the floor –Other cables installation interference Tester –Different flavor that work with different configuration of cable chain –Multiple laptops failure (ok now) –Several software updates to cope with different configurations (over last few months) –Getting parts in time Spares installation –2 spare type ii-iii EC cables installed but too short – need splicing extension Defective dPPF1 –Faulty cable was actually due to a bad channel on dPPF1 (that was marked color dots but it was used anyway) Type III installation & testing –Difficult conditions for testing because sequence of cables installed doesn’t match order in PP3 rack, cables are set aside and plug-in has to happen for all cables when rack completed –Extra length to reroute on additional trays –Dedicated team (Russian) available to plug-in but need assistance (and all cables tested) Type IV installation –Slow –interference with type II-III installation –Extra interaction with new team Connector in situ –Communication with external company difficult - impossible to keep schedule as planned –The very first rack has 200 cables to reroute under the rack to absorb the extra length People

9 May 2006A.Ciocio - SCTSG13 Schedule Type II-III installation (from Marzio) by mid-June New schedule is expected this week Likely to go until end of June Type IV installationend of May – going into June Connector in situ/testingmid-June/end of June PS cratesmid-June (US side) – July (USA side) PP3 assembly, installation end of May All cables plugged into PP3end of June To meet this schedule we need continuous presence of people at CERN Last couple of weeks went relatively well but –Hard/inefficient to train/instruct/introduce so many people –Mistakes –Difficulties to direct people to tasks in the pit because underground access not requested or level4A not taken before hand Critical area in the type II-III acceptance installation and testing SCT participation very valuable to add to people who are resident NEED technical participation to go into July Our schedule

9 May 2006A.Ciocio - SCTSG14

9 May 2006A.Ciocio - SCTSG15 To work on cabling To sign up for shifts (and contact me because of unexpected changing in rate delivery/testing problems) Safety courses: 1) basic safety training course (level video in B55) 2) Level 4 for working in US15 + Oxybox (we have them) If you have an AIS LOGIN (used for EDH documents), you can follow the course from anywhere (even outside CERN) with AIS login by accessing If you have no AIS LOGIN, you need to register at the following address 3) Level 4A mandatory to enter the ATLAS underground areas This course is composed of 4 modules : Cryogeny, Evacuation, Installation and Magnet. Each of these modules is followed by a small test which you have to take and pass. If you do not yet have an AIS login, please contact the ATLAS secretariat and ask for this AIS account (they must be registered with ATLAS). If this is not possible, we will organize special training at CERN. 4) make the access request on EDH 5) get your safety boots & helmet (or borrow them) TRY TO GET AS MUCH AS POSSIBLE DONE BEFORE COMING TO CERN…

9 May 2006A.Ciocio - SCTSG16 LINKS Summary SCT Cables Web page Mapping, technical appendices, cables related documents Shifts Shift planner (developed by D. Robinson) works very well for planning the activities and have people to sign up Safety courses Level basic course for access underground and point 1 Level 4: with AIS login Level 4A: AIS login Overall Safety and Health Procedure Document PPSPS – Rack Wizard – ID installation Tuesday mornings, CRM (control room management) meetings Wednesday mornings ID/TC installation meeting