How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
MTTR, spare parts and stand- by policy for ATB equipments R. Losito AB/ATB 23th Jan ATC/ABOC Days 1.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE P. Alves, M. Nonis, P. Pepinster, W. van Baaren 6 th ST Workshop – March 2003.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Introduction S. Baird 12 th September Accelerator Consolidation Workshop  Why are we here?  Boundary conditions  What is (not) included?  Outcome.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
J. Pedersen, ST/EL Consolidation of the CERN technical infrastructure and civil engineering. J. Pedersen ST 6 th ST workshop, Thoiry, 1 – 3 April 2003.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
IEFC 2010 Workshop How to keep the PS operational for the next 25 years. 12-February-2010 R.Brown EN/MEF/ABA.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
D&D Review 6 August PEP-II Minimal Maintenance State Upkeep Stan Ecklund (J. Seeman, S. DeBarger, D. Kharakh, M. Zurawel)
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
A second Thyristor Controlled Static Var Compensator for SPS
Extraction and beamline progress B.Goddard TE/ABT.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
How to keep the SPS running for another 25 years V. Chohan ( based on Input from N. Gilbert & many Equip. Groups) IEFC Workshop 12 th Feb 2010.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
13 January 2005 PS&SPS DAYS How can we restart AD in 2006? Slide 1 How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
Status of the machines over X-mas standby period, services required and plans for rapid start-up OP Group Meeting KH.
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
PS Complex Controls Renovation S Baird AB/ABP ATC/ABOC Days: Session Jan 2008.
What’s Falling Apart in the Injector Chain ? PS/SPS Days January 2005.
YETS & LS2 Works EN-EL / Power distribution
ABT-EC EYETS Activities 2nd reports
Situation of the Static Var Compensators at CERN.
TE-MSC activities in SPS during LS2
Ongoing consolidation of magnets
EYETS David Hay EN-OSS.
LIU – EVM status and next steps
AD consolidation activities in LS2
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Renovation of the 45-year old PS magnets
SPS activities during LS2 TE-EPC (Power Converter Group)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
YETS & LS2 Works EN-EL / Power distribution
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD
Experimental Areas – LS2 planning
ATS Consolidation Day 22nd May 2019 Beam Instrumentation
Presentation transcript:

How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010

How does one keep a year old running for another 25 years? LHC Performance Workshop Chamonix January 2010 accelerator

LHC Performance Workshop Chamonix January 2010 How does one keep a year old running for another 25 years? accelerator

How to keep the injectors running for another 25 years? Full IEFC workshop Feb. –Information collected by Machine Superintendents (EN/MEF/ABA) No upgrade in performance considered (treated elsewhere) Maintain current beam performance and availability for LHC lifetime LINAC2 not treated here –LINAC4 will be covered in Feb. LHC Performance Workshop Chamonix January 2010

How to keep the injectors running for another 25 years? Huge amount of information collected Review system by system = 12 slides –Vacuum, RF, Magnets, Kickers & septa, Beam Instrumentation, Interlocks, Cooling & Ventilation, Electricity, Power Convertors, Cabling, Handling, Dumps, RP, Tunnel Infrastructure etc…. LHC Performance Workshop Chamonix January 2010

Vacuum A report is in preparation for the injector chain First “estimate” –Operation to 2022 replace 50-70% of system hardware –Operation to 2035 replace 100% SPS –Spares (windows in target areas?) –TIDVG upgrade –MKE? Any major consolidation campaign (ABT, MSC, RF etc…) would involve a lot of vacuum activity LHC Performance Workshop Chamonix January 2010

RF PSB: Major work on C02, 4 & 16 systems HV power supplies, tuning supplies, interlocks, servos, plus cables, low-level & dampers etc. –12-15MCHf PS: Systems must be modernised C10 drivers, gap relays, ferrites, RF bypasses, Digital low- level systems, new feedback systems, cables –>10MChf SPS: Power couplers, replace tetrodes, wave-guides, replace low- level (200 & 800MHz), controls, dampers…. Plus major upgrades needed to increase intensity LHC Performance Workshop Chamonix January 2010

Magnets (EDMS no: ) Maintain a vigorous maintenance plan –Dielectric tests, endoscopic inspections, inter-turn testing, water hoses, maintain a healthy stock of spare coils and magnets PSB –Continue maintenance program + purchase spares PS –Continue maintenance program + purchase 20 additional sets of PFW (gives enough to re-equip all main dipoles) SPS: Water erosion, inter-turn shorts & fatigue of pole shim bolts –Continue systematic maintenance –Study of water erosion problems –Spare coils –Replace pole shim bolts in maintenance plan LHC Performance Workshop Chamonix January 2010

Beam transfer systems PSB & PS: –LINAC4 project – PSB injection systems new –Spare kickers, tanks, HV cables –Replace thyratrons, HV switches –Replace controls (PLC based solutions?) SPS –Replace septa HV generators, diluter –LSS4&6 new fast pulsed magnets –Spare MKDV/H magnets –Replace timing systems –Buy Thyratrons for 25 years of operation (single supplier) Some of this is included in present Consolidation programs LHC Performance Workshop Chamonix January 2010

Beam Instrumentation Wire scanner –New fast BWS prototype developed for installation from 2014, for PS SPS & LHC BLM –New system for PSB in 2013 (LINAC4) –PS and SPS afterwards Beam position & trajectory –PS system recently replaced –SPS replacement planned for 2013 –PSB to be planned (link to LINAC4?) Beam Current Transformers –Acquisition systems for PS complex are being replaced –Hardware (e.g. BCT torroids) will need replacing LHC Performance Workshop Chamonix January 2010

Electricity On top of existing Consolidation (44MCHf) PSB & PS –Replace all cabling (48 MCHF) –Replace low voltage switchboards, UPS, safety lighting etc. (14MCHf) –Renovate HV substations ME16, ME49 & M76 (2MChF) SPS (not including 18kV system actions already covered) –Replace 2 400/18kV transformers (8MCHf) –Replace SMB 18kV cable network (7MCHf) –Replace all TGBT switchboards (7MCHf) –Replace 40/72 18/4kV transformers (2.3MCHf) –Cable replacement in tunnel (40MCHf) –Remove unused cables (30MCHf) LHC Performance Workshop Chamonix January 2010

Power Converters PSB: 13MCHf installed cost –50% will need to be replaced by 2020 = 7 MCHf PS: MPS replaced = POPS –Replace TT2 power converters (4MCHf) –Auxiliary supplies?? SPS: –MPS renovation (7MCHf) –AuxPS and LHC transfer lines recently upgraded/installed – annual maintenance –Two static VAR Compensators will require replacement after 20 years operation (2022 & 2027) –North area power converters will need replacing (7MCHf) LHC Performance Workshop Chamonix January 2010

Access and safety systems PS: PPS renewal has started /4 –Current “obsolete” system will be maintained: outdated G64 systems etc. will be replaced SPS: PPS replacement is planned to start in /6? –Current “obsolete” system will be maintained Safety & Fire alarm systems will be maintained as long as necessary LHC Performance Workshop Chamonix January 2010

Interlocks Today PSB/PS do not have a beam interlock system –Studies are just starting on deployment of the LHC BIC type for PS (with new access system)?? PSB/PS Magnet interlocks –New WIC only installed for LINAC3 & LEIR –Current PSB/PS system has never been renovated, could be replaced with WIC (250kCHf) SPS: BIC is already in operation, the WIC is deployed for transfer lines only –Main ring magnet interlocks have never been renovated, could be replaced with WIC (800kCHf) LHC Performance Workshop Chamonix January 2010

Dumps, collimators.. Beam stoppers - Standard maintenance Slits: Critical elements –Very active, cannot be repaired, mechanics need to be standardised & spares built PSB Beam dump critical –no spare “history unknown” PS beam dump: Under Consolidation SPS –Scrapers: planned for consolidation –TIDVG Improved spare under constructions Experimental area equipment, target stations, collimators etc also need urgent maintenance LHC Performance Workshop Chamonix January 2010

Cooling & Ventilation Major Consolidation effort already planned in coming years –40MCHf, which includes a lot of work for LHC –Injectors = Controls, safety requirements for Legionnaire’s disease, spare parts, replace piping & valves… Additional actions to be considered for another 25 years –Complete replacement PS ventilation systems (asbestos!) –Replacement of PS chilled water circuits –Replace heat exchangers on Meyrin cooling stations –Renovate compressed air systems –Renovate production for dematerialized water LHC Performance Workshop Chamonix January 2010

Other systems Controls – ACCOR renovation project starting. –Should consider an ACCOR2? Cranes, lifts, handling equipment are in the existing Consolidation plan SC/RP radiation monitoring - Ramses deployment is in the existing Consolidation plan Tunnel Infrastructure under study - Civil Engineering LHC Performance Workshop Chamonix January 2010

Conclusions This is just a start –More detailed analysis at the IEFC meeting leading to a list of activities Some more detailed studies first cost/resource estimates –Some BUT DEFINITELY NOT ALL of these activities are included in current Consolidation programs. Strong and vigorous maintenance programs are very important Don’t cut Operations budgets, even if it looks attractive in the short-term…. LHC Performance Workshop Chamonix January 2010

+ =