EM660 PROJECT MANAGEMENT Class 5.

Slides:



Advertisements
Similar presentations
Project Management Techniques and tools Move mouse over arrow to enter presentation End Show.
Advertisements

CP Chapter 4 Schedule Planning.
Estimating, scheduling and budgeting
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Developing a Project Plan
Advanced Project Management - CPH
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
Critical Path and Gantt
Creating the Project Plan
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 8-1.
Eleanor Roosevelt High School
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Time Management
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
CHAPTER 4 MANAGING PROJECT PROCESSES. THE CONCEPT A project is an interrelated set of activities that has a definite starting and ending point and that.
PERT/CPM Models for Project Management
Project Management. What is a Project? One Time Effort Identifiable Start/End Points Specific Objectives Multiple Tasks Resources from Across the Organization.
Project Time Management
Importance of Project Schedules
Project Management Techniques.
Roberta Russell & Bernard W. Taylor, III
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
HIT241 - TIME MANAGEMENT Introduction
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Software Project Management Task Estimating and Scheduling
Scheduling Sequence & Time.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
PROJECT MANAGEMENT Approaches By- Rahul Jain. Plan your work first…..then work your plan.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Chapter 16 – Project Management
Project Management: PERT/CPM
L6 – Project Time Management - II
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
Project Time Management
Project Time Management
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

EM660 PROJECT MANAGEMENT Class 5

Class 5 Agenda Chapter 12 Networks Chapter 13 Report Format Chapter 12 Homework problems due 2/19/15 Problems 12-14 and 12-17 in book

Change MS Projects to Work Saturdays http://office.microsoft.com/en-us/project-help/change-working-days-for-the-project-calendar-HA102809468.aspx

Change MS Projects to Work Saturdays (cont.)

Change MS Projects to Work Saturdays (cont.)

MS Project Tutorial On Highlighting Critical Path

Network Scheduling Techniques Chapter 12 Scheduling techniques (below) present masses of complex, technical, cost, & deadline data to management, teams and customers. 1) Gantt or bar charts 2) Milestone charts 3) Networks 4) PERT – Program Evaluation and Review Technique 5) ADM – Arrow Diagram Method (critical path method) 6) PDM – Precedence Diagram Method 7) GERT – Graphical Evaluation and Review Technique

PERT CHART Program Evaluation and Review Technique The Program (or Project) Evaluation and Review Technique, commonly abbreviated PERT, is a statistical tool, used in project management, that is designed to analyze and represent the tasks involved in completing a given project. First developed by the United States Navy in the 1950s, it is commonly used in conjunction with the critical path method (CPM).

Activity on the Node

Computing Drag Critical Path DRAG (Devaux's Removed Activity Gauge) is the amount of time that an activity on the critical path (i.e., the longest path through the project) is adding to the project’s duration or, alternatively, the amount of time by which the project completion would be pulled in by reducing a critical path activity’s duration to zero. 

Computing Drag(cont.) If an activity has nothing in parallel, its DRAG is equal to its duration. If an activity has other paths in parallel, its DRAG is whichever is less: its duration or the total float of the parallel activity with the least total float.

Activity on the Arrows (we will only use activity on the nodes)

Terminology PERT activity: the actual performance of a task which consumes time and requires resources (such as labor, materials, space, machinery). It can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be performed until the predecessor event has occurred. optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes). most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal. expected time (TE): the best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time).

Terminology (cont.) TE = (O + 4M + P) ÷ 6float or slack is a measure of the excess time and resources available to complete a task. It is the amount of time that a project task can be delayed without causing a delay in any subsequent tasks (free float) or the whole project (total float). Positive slack would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule. critical path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount. critical activity: An activity that has total float equal to zero. An activity with zero float is not necessarily on the critical path since its path may not be the longest. fast tracking: performing more critical activities in parallel crashing critical path: Shortening duration of critical activities

Time Management NOTE: The PMP certification exam presents scheduling in the Time Management Chapter. NOTE: There is no such thing as project management software. MS Project is helpful for scheduling “what if” scenarios and status report functions. For this reason, this chapter involves a little manual math to understand MS Project.

Advantages of Network Scheduling Plan and predict Provide visibility Evaluate alternatives Identify slack Obtain facts Act a time network Identify critical paths Schedule risk analysis Basic report structure Reveal interdependencies Facilitate “what if” PERT & /CPM identify where the greatest effort should be placed to keep a project on schedule. Alternate plans may be developed & different scenarios tried, with the results presented in a well organized manner.

Disadvantages of Network Scheduling Time and labor intensive. Decision-making ability reduced Lacks functional ownership in measurements Lacks historical data for time-cost elements. Assumes unlimited resources. Requires too much detail.

Terms EVENT – similar to milestones -when activities start or finish. ACTIVITY – links the events. DURATION – amount of time to finish activity. EFFORT – amount of actual work performed during duration (50% or 2 weeks in 1 month). CRITICAL PATH – The longest path; shows the shortest possible time to complete project.

House II Homework-Draw Network on Board

House III-Put in MS Projects MS Project Gantt Chart

Definitions

Gantt Chart

Slack Time

Slack Time

Tracking Gantt in MS Project

Critical Path The Critical Path helps the project manager to: Proves how long the project will take. Determines where to focus effort. Signals immediate action. Determines which items can be crashed and which can float. Note: There is no slack on the critical path and crashing non-critical path items won’t help improve delivery times.

Slack of Task C

Earliest Start/Latest Start

Slack Slack is the amount of time a task can be delayed without delaying the project end date. Slack time = TLS – TES where TES is earliest start date and TLS is latest start date that won’t delay project. Slack lets you assign new employees to non-critical tasks, reallocate resources to shorten the overall project time, or gives the team some flexibility to juggle their schedules.

Calculating Slack The critical path has no slack, so the ES and LS will be identical Do a forwards and backwards path to determine the ES and LS for non-critical tasks.

Forward Pass ES(successor)=ES(current)+DUR(current) Use the highest value on “join”

Backward Pass LS(Predecessor)=LS(current)-DUR(Predecessor) Use the lowest value on “join”

Show videos

Forward Pass ES of A =0

Forward Pass ESB =ESA+DURA

Forward Pass Similarly for C & D

Forward Pass ESE =Greatest of 7,13,16

Backward Pass LSE = ESE

Backward Pass LSF = LSE-DurF

Backward Pass LSB = LSE-DurB

Backward Pass LSC = LSE-DurC

Backward Pass LSD = LSF-DurD

Backward Pass LSA = LSD-DurA

Backward Pass Slack=LS-ES

Work Problem 12-13 on Board

Resource Allocation (p. 508) Resource allocation involves moving resources from activities with slack to activities on the critical path, cutting overall project completion time.

Crashing Crashing is making cost and schedule trade-offs to get the greatest schedule reduction for the least amount of cost. Crashing, by definition, almost always results in increased costs. If your estimated project completion date is after the customer’s desired date, you can ask for more time or crash the schedule and report the potential cost increase. It depends on which of your triple constraints is the primary driver.

Crashing Example (Fig. 12-16) Activity Normal Time Crash Time Time Savings Normal $ Crash $ Extra Cost Cost per Month A 4 2 10,000 14,000 4,000 2,000 B 6 5 1 30,000 42,500 12,500 C 8,000 9,500 1,500 D 12,000 18,000 6,000 E 7 40,000 52,000 F 3 20,000 29,000 9,000 3,000

Crashing Example (Fig. 12-16) Crash critical path activities only, lowest cost activity first! While activity C is the lowest cost per month ($1,500), it is not on the critical path. Start with activity A ($2,000 per month).

Network Before Crashing Crash A for 2mos

After Crashing A Crash F for 3mos

After Crashing F

After Crashing E Crash B for 1mo

After Crashing B 1mo

Project Cost versus Duration

Crash House II Perform resource allocation and crash your House II for House III homework.

Reducing Project Time (p.510) Elimination of some parts of the project. Adding more resources (crashing). Substituting easier activities or components. Concurrent engineering (fast tracking). Shortening critical path activities (allocation). Increasing the number of work days (O.T.).

Project Graphics Chapter 13 Good graphical displays are a prime means for tracking cost, schedule & performance (triple constraints). The information can be used for: Cutting project costs & reducing time scales. Coordinating and expediting planning. Eliminating idle time. Obtaining better subcontractor control. Better troubleshooting procedures. Allow more time for making better decisions.

Reporting to an Audience Upper management requires top level information, project costs & communication. At the operational level, stakeholders are looking for operating costs, performance and greater detail. The ability to communicate is a prerequisite for successful project management. The format of that communication depends on the audience.

Gantt Charts Gantt charts list activities, their duration, schedule dates and progress. Pros include: simple to understand and easy to change. Cons include: No linkage or network interdependence, slack or critical paths.

Milestone Charts Similar to Gantt charts but only show major events. Pros include: good tools for reporting to management and the customer. Milestone show when requirements are complete.

Network Diagrams Critical path analysis, shows hidden linkages better than any other chart. Complex, multi-step projects are hard to resolve manually, computer software helps.

Other charts…… Variation against a cost or time target or budget (performance measurements). Distribution of wealth (where is our money going?). Logic diagrams showing a process flow with no consideration of time or cost. Statistical Process Control Charts.

Next Week Chapter 12 Homework problems due on 2/19/15, Problems 12-14 and 12-17. For House III crash House II and add resources and costs—remember, only crash tasks on the critical path and start with the lowest cost Quiz 2 on 2/26/15 Read Chapter 14 thru 16.