Office of Safety & Health Consultation Office of Safety & Health Consultation presents Excavations & Trenching
Objectives In this course, we will discuss the following: Excavations/Trenching: Subpart P – Scope, application, and definitions applicable to this subpart – Specific excavation requirements – Requirements for protective systems 1926 Subpart P
Subpart and Standard Number of Serious Violations – FY
Subpart P - Appendices Appendix A - Soil Classification Appendix B - Sloping and Benching Appendix C - Timber Shoring for Trenches Appendix D - Aluminum Hydraulic Shoring Appendix E - Alternatives to Timber Shoring Appendix F - Selection of Protective Systems 1926 Subpart P
Definitions Excavation –Man-made cut, cavity, trench, or depression formed by earth removal. Trench –Narrow excavation –Depth is greater than the width, but not wider than 15 feet. Shield –Structure able to withstand a cave-in and protect employees (b)
Definitions Shoring –Structure that supports the sides of an excavation and protects against cave-ins. Sloping –Technique that employs a specific angle of incline on the sides of the excavation (b)
Competent person –Must have specific training in and be knowledgeable about: Soils classification Use of protective systems Requirements of the standard –Must be capable of identifying hazards, and authorized to eliminate them (b) Definitions
Weight of Soil Weight of soil varies with type and moisture content. One cubic foot weighs 110 pounds to 140 pounds. One cubic yard (27 cubic feet) of soil can weigh more than 3,000 pounds.
Excavation Hazards Cave-ins are the greatest risk. Other hazards include: – Asphyxiation due to lack of oxygen – Inhalation of toxic materials/fumes – Fire – Machinery moving near edge of excavation causing a collapse – Severing underground utility lines – Falls
Injury and Death Excavating is one of the most hazardous construction operations. Most accidents occur in trenches 5-15 feet deep. Usually no warning before a cave-in.
Specific Excavation Requirements (a) Surface encumbrances (b) Underground installations (c) Access and egress (d) Exposure to vehicular traffic (e) Exposure to falling loads (f) Warning system for mobile equipment (g) Hazardous atmospheres
Specific Excavation Requirements (h) Protection from hazards associated with water accumulation (i) Stability of adjacent structures (j) Protection of employees from loose rock or soil (k) Inspections (l) Fall protection
Surface Encumbrances All surface encumbrances that create a hazard to employees must be removed or supported to safeguard employees (a)
Estimated location of utility installations [sewer, telephone, fuel, electric, water lines] must be determined prior to opening an excavation (b)(1) Underground Installations
When utility companies or owners cannot respond to request to locate underground utility installations within 24 hours. –Employer may proceed with caution, provided detection equipment, etc. is used to locate utility installations (b)(2) Underground Installations
Exact location of underground installations must be determined by safe and acceptable means (b)(3) Underground Installations
(b)(3) Underground Installations
(b)(3)
(b)(4) Underground Installations Underground installations must be protected, supported or removed as necessary to safeguard employees.
(c)(1)(i) Structural Ramps Structural ramps used for access or egress of equipment must be designed by a competent person.
(c)(2) Egress - Trench Excavation Stairway, ladder, ramp, or other safe means of egress must be located in trench. Required if trench 4 feet or more in depth. Lateral travel distance no more than 25 feet.
Ramp, ladder or stairs required at 4 feet or deeper. 25 feet (c)(2) Egress - Trench Excavation
(c)(2) Egress - Trench Excavation
Is this correct? (c)(2) Egress - Trench Excavation
Exposure to Vehicle Traffic Employees exposed to public vehicular traffic must wear warning vests or other suitable garments marked with or made or reflectorized or high-visibility material (d)
(e) Employees must not be permitted to work under loads handled by lifting or digging equipment. Exposure to Falling Loads
(e) Exposure to Falling Loads Stand away from equipment that is being loaded or unloaded. Equipment operators may stay in their equipment during loading and unloading if equipment has proper cab shield or canopy.
(f) Warning System - Mobile Equipment Mobile equipment operated adjacent to excavation and operator cannot see edge of the excavation: –Warning system must be utilized. Barricades Hand or mechanical signals Stop logs
Warning System - Mobile Equipment (f) Is this correct?
Hazardous Atmospheres Testing conducted before employees enter the trench and regularly thereafter (g)(1)
Less than 19.5% or more than 23.5% oxygen A combustible gas concentration greater than 20% of the Lower Flammable Limit (LFL) Concentrations of hazardous substances that exceed OSHA’s Permissible Exposure Limits (PEL) Hazardous Atmospheres
Test at 4 feet if suspected –LEL –Oxygen –CO –H2S –Petroleum –Other toxics (g)(1) Hazardous Atmospheres
Emergency Rescue Equipment (g)(2)(i)
Emergency Rescue Equipment Emergency rescue equipment must be readily available where hazardous atmospheric conditions exist or expected to develop during work. –Breathing apparatus –Safety harness and line –Basket stretcher
(h)(1) Water Accumulation Employees must not work in excavations where there is accumulated water, or where water is accumulating. Unless precautions taken to protect workers: –Water removal to control level of water –Special support or shield systems
Water Accumulation (h)(1)
Water removal equipment and operations must be monitored by a competent person to ensure proper operation (h)(2) Water Accumulation
(h)(3) Water Accumulation Excavations subject to runoff from heavy rains require an inspection by a competent person.
Well Points Used to Remove Ground Water
What are the Hazards?
What are the hazards?
(i)(1) Stability of Adjacent Buildings Support systems such as shoring, bracing, or underpinning must be provided to ensure stability of structures.
Stability of Adjacent Structures Excavation below the foundation that could pose a hazard shall not be permitted except: ‘ – Underpinning provided – Stable rock – Registered professional engineer (RPE) has approved (i)(2)
Underpinning to prevent structural failure (i)(2)(i) Underpinning
Stability of Adjacent Structures Sidewalks, pavements and appurtenant structure must not be undermined unless supported to protect employees from collapse of such structures (i)(3)
Adequate protection provided to protect employees from loose rock or soil that could pose a hazard by falling or rolling from an excavation face. Protection of Employees (j)(1)
Belly bulge Fissures Extra load from spoil pile Potential Problems
Employees must be protected from equipment or materials that could fall or roll into excavations. –Materials and equipment must be kept 2 feet from edge of excavation or use retaining devices. Protection of Employees (j)(2)
Rule: 2 Feet (j)(2)
Two Feet From Edge (j)(2)
Extra Surface Loading
1. What’s the Hazard?
2. See it now…
(k)(1) Inspections – Competent Person Daily and before the start of each shift. As dictated by the work being done in the trench. After every rain storm and other events that could increase hazards, e.g., snowstorm, windstorm, thaw, earthquake, etc.
Inspections Frequency of testing should be increased if equipment is operating in trench as well as if welding, cutting, or burning is done in trench (k)(1)
(l)(1) Walkways provided when crossing over excavation. Standard guardrail installed when more than 6 feet above a lower level. Fall Protection
(a)(1) Protection of Employees Employees in an excavation must be protected from cave-ins by adequate protective system. –Except when: Made entirely in stable rock Excavation is less than 5 feet deep and examined by competent person
Sliding
Toppling
Tension Crack
Bulging
Heaving or Squeezing Soil Weight
Methods of Protection Sloping and benching Shoring (spaced sheeting, closed sheeting) Trench shield Other occasionally used systems
(a)(2) Protective Systems Protective systems shall have capacity to resist without failure all loads applied or transmitted to the system.
(e)(1)(ii) Installation and Removal Support systems must be installed and removed in a manner that protects employees from cave-ins.
Removal must begin at, and progress from, the bottom of the excavation. Members released slowly to note any indication of possible failure of remaining members. Installation and Removal (e)(1)(V)
(e)(2)(i) and (g)(2) Installation and Removal Excavations of material to a level not greater than 2 feet below the bottom of the support system or shield must not be permitted.
Deadly Trench Collapse
What’s the hazard?
Contains definitions Sets forth requirements Describes acceptable visual and manual test for use in classifying soils Soil Classification Appendix A
Definitions Cohesive soil –Clay, or soil with a high clay content, which has cohesive strength –Does not crumble –Can be excavated with vertical side slopes –Plastic when moist –Hard to break up when dry Appendix A Soil types
Definitions Granular soil –Gravel, sand, or silt, with little or no clay content –No cohesive strength –Cannot be molded when moist –Crumbles easily when dry Note: Some moist granular soils exhibit apparent cohesion Appendix A
Definitions Unconfined compressive strength –Load per unit area at which a soil will fail in compression Note: Estimated in the field by use of a pocket penetrometer, thumb penetration test, and other methods Appendix A
Roll into thread At least 2 inches in length Longer unbroken thread means more cohesive Thread Test Appendix A
Roll soil into a cigar shape Pinch between thumb and finger Longer ribbon means more cohesive Ribbon Test Appendix A
Thumb Penetration Test Appendix A
Pocket Penetrometer Appendix A
Type A Soil Most stable: clay, silty clay, and hardpan Not fissured Not subjected to vibration of any type Never been previously disturbed No seeping water Unconfined compressive strength greater than 1.5 tons per square foot (tsf) Appendix A
Type B Soil Medium stability: silt, sandy loam, medium clay and unstable dry rock Previously disturbed soils unless otherwise classified as type C Soils that meet the requirements of Type A but are fissured or subject to vibration Unconfined compressive strength less than 1.5 tsf and greater than 0.5 tsf Appendix A
Type C Soil Least stable: gravel, loamy sand, soft clay Submerged soil or dense, heavy unstable rock Soil from which water is freely seeping Unconfined compressive strength 0.5 tsf or less Appendix A
Contains definitions Sets forth requirements Configurations of sloping and benching Sloping and Benching Appendix B
Allowable Slopes Soil TypeHeight/Depth Ratio Slope Angle Stable rockVertical90° Type A¾ : 153° Type B1 : 145° Type C1 ½ : 134° Type A (short term)½ : 163° (For a maximum excavation depth of 12 ft) Table B-1
Excavations Made in Type “A” Soil Simple Slope
Excavations Made in Type “A” Soil Simple Slope – Short Term
Simple Bench Excavations Made in Type “A” Soil
Unsupported Vertically-Sided Lower Portion Excavations Made in Type “A” Soil
Unsupported Vertically-Sided Lower Portion
Multiple Bench Excavations Made in Type “A” Soil
Support or Shield System
Simple Slope Excavations Made in Type “B” Soil
Single Bench Excavations Made in Type “B” Soil
Multiple Bench
Support or Shield System Excavations Made in Type “B” Soil
Excavations Made in Type “C” Soil Simple Slope
Excavations Made in Type “C” Soil Support or Shield System
Excavations Made in Layered Soils A over B
Excavations Made in Layered Soils A over C
Excavations Made in Layered Soils B over A
Excavations Made in Layered Soils B over C
Excavations Made in Layered Soils C over A
Excavations Made in Layered Soils C over B
Benching and SlopingBenching
Timber Shoring for Trenches Need to determine soil classification Presentation of information Basis and limitations of the data Use of tables Examples to illustrate the use of tables Notes for all tables Appendix C
Aluminum Hydraulic Shoring Need to determine soil classification Presentation of information Basis and limitations of the data Use of tables Example to illustrate the use of the tables Footnotes, and general notes Appendix D
Horizontal Spacing 18” Max.. Vertical Spacing 4’ Max. 2’ Max. Vertical Rail Hydraulic Cylinder Vertical Aluminum Hydraulic Shoring (Spot Bracing) Figure No. 1
Vertical Rail 18” Max. Vertical Spacing 4’ Max. Plywood Hydraulic Cylinder Vertical Aluminum Hydraulic Shoring (With Plywood) 2’ Max. Figure No. 2 Horizontal Spacing
Vertical Spacing 4’ Max. 2’ Max. Hydraulic Cylinder Vertical Rail Vertical Aluminum Hydraulic Shoring (Stacked) Figure No. 3
Aluminum Hydraulic Shoring Waler System (Typical) Horizontal Spacing 2’ Max. Vertical Spacing 4’ Max.Hydraulic Cylinder Waler Upright Sheeting Figure No. 4
Alternatives to Timber Shoring Appendix E
Alternatives to Timber Shoring Appendix E
Selection of Protective Systems Illustrates a graphic summary of requirements contained in subpart P for excavations 20 feet or less in depth. Protective systems for use in excavations more than 20 feet in depth must be designed by a registered professional engineer in accordance with (b) and (c). Appendix F