1 Float Ownership in Construction Project Khalid Al-Gahtani.

Slides:



Advertisements
Similar presentations
Construction Delays & CPM Schedules
Advertisements

Chapter 6 Practical Methods to Reveal CPM Covert Activities
Project management.
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Administering Lump Sum P/T Contracts via a Cost Loaded Schedule
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
Scheduling CTC-470.
X- FUNDAMENTAL SCHEDULING PROJESS
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Spring 2008, King Saud University Bar Chart Dr. Khalid Al-Gahtani 1 What is Activity An activity or task is a given kind and amount of work which: –Consumes.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
CE 405 – SCHEDULING CRITICAL PATH In order to be an effective Scheduler/ Project Manager – and realizing that you will have too many things demanding your.
Projmgmt-1/18 DePaul University Evaluating Schedule In MicroSoft Project Instructor: David A. Lash.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
SWE Introduction to Software Engineering
Project Management Techniques.
©Ian Sommerville 2006Software Engineering, 8th edition. Chapter 5 Slide 1 Project management.
1 KING FAHAD UNIVERSITY OF PETROLEUM AND MINERALS CONSTRUCTION ENGINEERING & MANAGEMENT DEPARTMENT CEM 510 ********** CONSTRUCTION DELAY COMPUTATION METHOD.
Delivery Methods  The Players from Handbook of Architectural Practice, Chapter 9.1 by Phillip Bernstein FAIA  Variables from Handbook of Architectural.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Prepared by: Michael Palazzo
Resources Management Dr. Ahmed Elyamany.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Chapter 3 Project Management
©Ian Sommerville 2006Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
©Ian Sommerville 2000Software Engineering, 7th edition. Chapter 5 Slide 1 Chapter 5 Project Management Modified by Randy K. Smith.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
4 th European Project Management Conference, London, 6-7 June 2001 Resource Critical Path Approach to Project Schedule Management Vladimir Liberzon, PMP.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery.
CONSTRUCTION MANAGEMENT CONSTRUCTION ENGINEERING & MANAGEMENT DEPT
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
BIS 360 – Lecture Two Ch. 3: Managing the IS Project.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Project management Lecture 10. Topics covered Management activities Project planning Project scheduling Risk management.
Advanced Project Management Project Time Management Ghazala Amin.
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Software Engineering, 8th edition. Chapter 5 1 Courtesy: ©Ian Sommerville 2006 Oct 13 th, 2008 Lecture # 6 Project management.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
1 Project management. 2 Topics covered Management activities Project planning Project scheduling Risk management.
PROGRAMMING Frank Ellis B.Sc. ARSM Thursday 26th March 2015
Project Management.
Risk Management. 7–2 Where We Are Now 7–3 Risk Management Process Risk –Uncertain or chance events that planning can not overcome or control. Risk Management.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Responsibility of Nonworking Days in Analyzing Delay claims Khalid S. Al-Gahtani; Ibrahim A. Al-Sulaihi; Abdullah Alsehaimi.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
1 Project management Organising, planning and scheduling software projects.
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
& Urban Planning Civil Engineering Department
Project management.
ENGINEERING MANAGEMENT (GE 404)
How to perform Time Impact Analysis / Window Analysis in Primavera P6
ENM448-Project Planning and Management
Project management Lecture 9
Activity on Node Approach to CPM Scheduling
FACULTY OF ENGINEERING CONSTRUCTION AND BUILDING DEPARTMENT
Presentation transcript:

1 Float Ownership in Construction Project Khalid Al-Gahtani

2 Total Float Legal Difficulties Who own As-planned TF? –Contract Terms –Type of Contract (Project Risk) How to fix responsibilities of TF Change? –Owner, or –Contractor

3 TF Increase with CP delay Activity A Activity B Activity C Activity D Activity E Activity F Original TF

4 TF Increase with CP Delay Activity A Activity B Activity C Activity D Activity E Activity F Increased TF Delay Original TF

5 TF Decrease with CP Acc. Activity A Activity B Activity C Activity D Activity E Activity F Original TF

6 TF Decrease with CP Acc. Activity A Activity B Activity C Activity D Activity E Activity F Original TF Reduced TF Acceleration Adjusted TF

7 TF Increase with NCP Acc. Activity A Activity B Activity C Activity D Activity E Activity F Original TF

8 TF Increase with NCP Acc. Original TF Increased TF Adjusted TF Activity A Activity B Activity C Activity D Activity E Activity F Acceleration

9 Total Float Computational Difficulties How distribute As-Planned TF value between: –Owner/Contractor(s) –Owner/Contractor(s)/Subcontractor(s) How to calculate TF Change How to distribute responsibilities of TF Change

10 Issues of TF Calculation in CPM Issues associated with float in CPM –Activity Constraints –Different Calendars on the schedule. –Lag Calendar –Methods for Updating Project Schedule. “Retained logic” or “Progress override” –Late Dates Scheduling. –P6 Time Calculations

11 Influence of TF on Project Risk Float Consumption, Time Project Risk, $ References (Gong 1997; Gong and Hugsted 1993; Gong and Rowings 1995; Lockhart and Roberds 1996; Zhong and Zhang 2003)

12 Float Ownership Issues Issues associated with float ownership –Resource leveling –Change Order –Increase Risk for the bearing party –Float Distributions among project parties –Prevent “Schedule Games” –Changing Float

FLOAT ALLOCATION APPROACHES Owner Ownership Float Approach Contractor Ownership Float Approach Project Float Approach Bar Approach 50/50 Allocation Approach Commodity Approach Path Distribution Approach Contract Risk Approach Total Float Management Approach Total Risk Approach 13

14 Float Ownership Concepts

15 Define responsibilities of TF Changes Delay/Acce. Type Credit/Discredit to: EC DelayOwner NE DelayContractor EN DelayWho own the Float Owner-directed-accelerationOwner Contractor AccelerationContractor Schedule AccelerationWho own the Float

16 Project Start Contract Type Cost+FeeLump Sum Owner owns the float Contractor owns the float % Maximum Distribute the float Owner % General Contractor % Distribute the float among the rest of the project parties Subcontractor % Other Contractor % General Contractor % Day-by-day + Commodity Analysis END

17

18 TF Ownership Example The following is an illustrative example of how the Total Risk Approach will be applied in a small project shown in Figures 3-5 to Figure 3-5 shows the CPM network for a factual project. The project assumes to follow a Traditional Delivery System that has the following types of contracts: –The contract between Owner and General Contractor is a Guaranteed Maximum Cost Contract, so both contract parties agree to share the project risk by 50%. –The contract between General Contractor and Subcontractor A is a Guaranteed Maximum Cost Contract, so both contract parties agree to share the project risk by 50%.

TF Ownership Example 19 The contract between General Contractor and Subcontractor B is a lump-sum. All the above contracts assume not have any protective terms that shift the risk to another party. The project As-planned Schedule The example has the following paths and associated float times: −CP = A-B-C-D = = 20 days −NCP1 = A-E-C-D = = 16 days (TF=4) −NCP2 = A-E-F-D = = 14 days (TF=6) −NCP3 = A-G-H-D = = 12 days (TF=8)

20 TF Ownership Example Figure 3-5: CPM As-planned schedule for the applied example

The next step is distributing the float of the nearest first critical path, which yields the following calculations:  TF (Owner) = = 2 days  TF (General Contractor) = = 1 day  TF (Subcontractor A) = = [4-2-1] = 1 day 21 TF Ownership Example

22 Figure 3-6: Update the As-planned schedule to distribute the second nearest critical path TF Ownership Example

After distributing the nearest first critical path, the CPM as-planned schedule is updated (Figure 3-6) to distribute the float of second nearest critical path. After updating the CPM schedule, the project paths are updated as following: –CP1= A-B-C-D = = 20 days –CP2 = A-E-C-D = = 20 days –NCP1 = A-E-F-D = = 18 days (TF=2) –NCP2 = A-G-H-D = = 12 days (TF=8) 23 TF Ownership Example

24 Figure 3-6: Update the As-planned schedule to distribute the second nearest critical path. TF Ownership Example

Now the second update schedule of previous steps becomes the first nearest critical path. The following calculations are followed to get the float distribution of this path float:  TF (Owner) = 5/5 = 1 days  TF (General Contractor) = 5/5 × 2 × 0.5 × 0 = 0 day  TF (Subcontractor B) = 5/5×2×0.5×1= [2-1] = 1 day 25 TF Ownership Example

26 Figure 3-7: Update the As-planned schedule to distribute the third nearest critical path. TF Ownership Example

The last path of the example project can be distributed by updating the previous updated as-planned schedule as shown in Figure 3-7. Now the new updated schedule has the following paths: –CP1= A-B-C-D = = 20 days –CP2 = A-E-C-D = = 20 days –CP3 = A-E-F-D = = 20 days –NCP1 = A-G-H-D = = 12 days (TF=8) 27 TF Ownership Example

As a result, the following calculation can be applied to distribute the float of the last path on the project:  TF (Owner) = + = 4 days  TF (General Contractor) = + = 4 day 28 TF Ownership Example

Figure 3-8 represents graphically the final TF distributions, using a bar chart technique. The example paths after distribution can be represented as follows: –CP= A-B-C-D = = 20 days –NCP1 = A-E-C-D = = 16 days (TF=4; OW=2, GC=1, SA=1) –NCP2 = A-E-F-D = = 14 days (TF=6; OW= 3, GC=1, SA=1, SB=1) –NCP3 = A-G-H-D = = 12 days (TF=8; OW=4, GC=4) 29 TF Ownership Example

30 Figure 3-8: As-planned bar chart for the example project A B C D E OW GCSA F OW GCSAOWSB G OW GC H OW GC Legends: OW= Owner’s Float, GC= General Contractor’s float, SA=Subcontractor A’s float, SB=Subcontractor B’ float TF Ownership Example

The first analysis schedule happened in day 7 of the analysis schedule (Figure 3-9). The owner caused a 2 Excusable Compensable delay (EC) in the activity B start time. As a result, all the noncritical paths on this example have been increased by 2 days on their float as shown in the following calculations: –CP= A-B-C-D = 5+ (6+2)+7+2 = 22 days –NCP1 = A-E-C-D = = 16 days (TF=6; OW=4, GC=1, SA=1) –NCP2 = A-E-F-D = = 14 days (TF=8; OW= 5, GC=1, SA=1, SB=1) –NCP3 = A-G-H-D = = 12 days (TF=10; OW=6, GC=4) 31 TF Ownership Example

32 Figure 3-9: Day 7 analysis on the example project Legends: OW= Owner’s Float, GC= General Contractor’s float, SA=Subcontractor A’s float, SB=Subcontractor B’ float, NE=Nonexcusable Delay, EC=Excusable and Compensable Delay A EC B C D E OW GCSAOW F GCSAOWSBOW G GC OW H GC OW TF Ownership Example

The next updated schedule occurred on day 10 when the Subcontractor A consumed 3 float days on the activity E (Figure 3-10). As a result, the noncritical paths affected are as follows: –CP= A-B-C-D = 5+ (6+2)+7+2 = 22 days –NCP1 = A-E-C-D = 5+(2+3)+7+2 = 19 days (TF=3; OW=4, GC=1, SA=1-3=-2) –NCP2 = A-E-F-D = 5+(2+3)+5+2 = 17 days (TF=5; OW= 5, GC=1, SA=1-3=-2, SB=1) –NCP3 = A-G-H-D = = 12 days (TF=10; OW=6, GC=4) 33 TF Ownership Example

34 Figure 3-10: Day 10 analysis on the example project Legends: OW= Owner’s Float, GC= General Contractor’s float, SA=Subcontractor A’s float, SB=Subcontractor B’ float, NE=Nonexcusable Delay, EC=Excusable and Compensable Delay A EC B C D E NE F SBGCOW G H TF Ownership Example

As show in the calculations, –the Subcontractor A consumed 2 disentitled days. –Consequently, this consumed float has been taken from other shared parties on this path (owner, General contractor, and Subcontractor B) 35 TF Ownership Example