Mathew Watkins: Project Manger Larry Wu: Hardware Engineer Eric Robbins : Software Engineer Libby John: Systems Engineer Sponsor: Jeff Smith Advisor: Dr. Yong-Kyu Jung A.I.R Automated Individual Remote October 4, 2006
Microcontroller 16F690 THERMISTOR LON MOD VAV Controller TV Tuner TV CH 3 Video Module Display Pillow Speaker DEMONSTRATION SPDT
Deliverable 2006 Due DateDeliverablePrimary Member Status 09/04/2006Summary of ResearchLibby John 09/27/2006PCB #1Matthew Watkins 10/01/2006LON ModuleLarry Wu 10/09/2006Communications Documentation Libby John 11/15/2006PCB #2Matthew Watkins 11/21/2006Program CodeEric Robbins 12/01/2006Technical Report & User Manual Libby John Completed In Progress Not Started Behind 11/21 Program Code 10/9 Communications Documentation 12/1 Technical Report and User Manual 9/4 Summary of Research 10/1 LON Module 11/15 PCB #2 9/27 PCB#1
Milestones 2006 Due DateMilestonesStatus 09/13/2006Primary Research Completed 09/20/2006Schematic and PCB Layout 09/27/2006Prototype Demo 10/04/2006TV Tuner Module 10/11/2006Setpoint Feedback 10/18/2006Enclosure Options 10/25//2006GUI Presentation 11/1/2006 System Demonstration 11/8/20062 nd PCB 11/15/2006PCB Populated Completed In Progress Not Started Behind
Open Actions Status What action: Fixing the video generator Who has responsibility: Matt What is status: Completed Expected Date:
Open Actions Status What action: GUI for the program Who has responsibility: Eric What is status: In Progress Expected Date:
Open Actions Status What action: Setpoint Feedback to µc Who has responsibility: Larry What is status: Behind Schedule Expected Date:
Open Actions Status What action: Power budget Who has responsibility: Libby What is status: In Progress Expected Date:
Earned Value Total Number of hours worked: __70/504_ Estimate of manpower needed: _300_ Total Baseline hours: _1000_ SPI: 1.6 CPI: 2.5 Projection: –Scope: No change –Time: On time –Cost: Above Cost
Earned Value Analysis WEEK 1 9.6, 6.4 WEEK 2 5.0, 3.3 WEEK 3 3.6, 2.4 WEEK 4 2.5, 1.6