Managing Exceeded Capacity. 10 September 2009 2 The Issue of Exceeded Capacity DNO Connection Charging Methodologies: customers who increase Maximum Capacity.

Slides:



Advertisements
Similar presentations
ISTISNA’.
Advertisements

July 2003 Structure of Electricity Distribution Charges Update and Proposals Martin Crouch Director, Distribution.
Update on IDNO/DNO working group DCMF 12 November 2009.
Generation Dominated Areas Oliver Day 5 April | Energy Networks Association - DCMF.
DCMF Treatment of pre 2005 generation – DNO position Nigel Turvey 29 April | Energy Networks Association.
Update from DCMF MIG Claire Campbell Chair – DCMF MIG 05 April | Energy Networks Association - DCMF.
Insert strapline Developing quality incentives Cemil Altin Head of European Gas Policy November 2006.
EDCM update Mo Sukumaran (on behalf of CMG)
RIIO-T1 impact on allowed revenues and network charges 6 September 2012.
A DNO Perspective by Stephen Parker for Structure of Charges Workshop 15 July 2003.
144A – Calculation of Value at Risk (VAR) Simon Trivella – 24 th May 2007 Distribution Workstream.
AQ Appeals and the BTU form Chris Warner. 2 AQ Appeals and the BTU form  Presentation reflects NGD’s view of UNC regime as drafted and is intended to.
July 2003 Structure of Electricity Distribution Charges Welcome and Introduction Charles Gallacher Deputy Director, Scotland.
Retail Energy Forum Andrew Neves Central Networks - CMG Chair 2 March | Energy Networks Association.
Enforcement of the Seveso II Directive Enforcement of the Seveso II Directive.
2011 Contribution Policy AESO Tariff Applications October 17 th, 2011.
GENFLEX TARIFF AND INCOPORATION OF THE MEC INTO THE NMD RULES
Breach of Contract and Remedies
TRANSACTION AND INDUSTRY REVIEW CONFERENCE NIGERIAN POWER SECTOR REFORM: AN OVERVIEW OF TCN AGREEMENTS.
The Building and Construction Industry Security of Payment Act 2002 (Vic) made simple Western Suburbs Law Association Tuesday 4 June 2013 Michael Heaton.
EDCM submission workshop Andrew Neves CMG Chair 12 May | Energy Networks Association - CMG.
Xoserve sense checks & validation Reasonable Endeavours Claims.
Code Administrators Working Group Introduction 28 August 2008.
1 st April 2010 energynetworks.org 1 Common Methodology Group Work PRESENTED BY Tony McEntee, ENW Workstream 4 Update Common Connection Charging Methodology.
18th May 2009 energynetworks.org 1 A PRESENTATION BY ERIKA MELÉN OF THE ENERGY NETWORKS ASSOCIATION Report from the ENA/ERA Theft of Energy Working group.
User Pays Funding – Potential Licence Mechanism Simon Trivella – January 21 st 2010 Governance Workstream.
ERS Procurement Methodology 09/04/2013 ERS Workshop Presented By: ERCOT Staff.
CcTLD/ICANN Contract for Services (Draft Agreements) A Comparison.
Draft Review Proposal 175 Encouraging Participation in the elective DM Regime Phil Broom 25 October 2007.
© British Gas Trading Limited 2011 DNO Losses Incentive- Summary.
EHV generation charging methodology change Harvey Jones.
Review Group 0221: User Commitment Best Practise guidelines for Gas and Electricity Network Operators Credit Cover (2005)
19 March 2010 energynetworks.org 1 PRESENTED BY Nigel Turvey Workshop on Distributed Generation Connected pre April March 2010.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
03 April 2009 energynetworks.org 1 Common Methodology Group Work Presentation from Workstream 4 Review of the Connection Charging Boundary in the CDCM.
1 EHV DG Charging Nigel Turvey. 2 Background Our current EHV charging methodology was not vetoed on 18 th February 2010 with the following treatment of.
Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October | Energy Networks Association - DCMF.
Energy Suppliers Forum CDCM/EDCM - CMG Update Mo Sukumaran – CMG 10 November | Energy Networks Association.
ElectraLink Update on DCUSA Activities. Charging Methodology CP Summary StatusCDCMEDCMCCCMBilling WG: Pre Consultation10 (DCP 133, 159, 160, 161, 165,
Update from DCUSA Michael Walls DCUSA Secretariat 04 August | Energy Networks Association - DCMF.
Provision of third party access to licence exempt electricity and gas networks Tony McEntee 5 April | Energy Networks Association - DCMF.
Construction Contracts
Review Group Modification Proposal Introduction of Enduring NTS Exit Capacity Arrangements.
DCUSA Update ElectraLink. Charging Methodology CP Summary StatusCDCMEDCMCCCMBilling WG: Pre Consultation8 (DCP 133, 158, 159, 160, 161, 163, 165, 168)
Governance and Charging Methodology for User Pays Services 10 th January 2007.
Structure of Charges Year-end review for DCMF 22 November 2007.
EDCM Workshop Workstream C Update Andy Pace - Chair 10 November | Energy Networks Association.
15 February 2006 TPCR second consultation: gas offtake Offtake Arrangements Workstream 15 February 2006.
CDCM Annual Review Workshop Mo Sukumaran SSEPD (on behalf of DNOs) 17 May May | Energy Networks Association - CMG.
Update from DCUSA Michael Walls DCUSA Secretariat 06 October | Energy Networks Association - DCMF.
GVC Group Update Andy Pace 6 October | Energy Networks Association - DCMF.
Uniform Grant Guidance Roundtable Discussion: October 5, 2015 Procurement 1.
FROM PRINCIPLES TO PLANNING Recent Developments in International Tax - Mexico FROM PRINCIPLES TO PLANNING.
EDCM update Andrew Neves CMG Chair 2 June | Energy Networks Association - DCMF.
WSPP Webinar Proposed Service Schedules Operating Reserve Service (D) Intra-Hour Supplemental Power (E) February 4, 2010.
Energy Market Issues for Biomethane Projects Workshop - 31 October 2011 RIIO-GD1 Environmental Incentives.
Proposed framework for charges for generators connected to the Distribution network Please note that the contents of this presentation are proposals at.
The Duke Save-A-Watt Proposal: An Economist’s Look James A. Polito, Ph.D. Director, Economic and Regulatory Analysis Indiana Office of Utility Consumer.
Demand Side Management Andy Pace 6 October | Energy Networks Association - DCMF.
Modification Proposal 0435: Arrangements to better secure firm gas supplies for GB customers Initial Workgroup discussion 1 November 2012.
Distribution Commercial Group Billing & Collection Management and Remedies Richard Smith Chair- EA Distribution Commercial Group.
7th DCMF on 19th June Connection Boundary Review Network charges comprise Connection Charges and ongoing Use of System (UoS) charges. The Connection.
HOW TO DRAFT CLAUSES WHICH COMPLY WITH REGULATION 330/2010
Loss of Mains Protection on DG Rectification Programme
Transmission Workstream 4th July 2007
Transmission: the Critical Link
Holistic view of Charging Modifications – In flight 11th June 2018
UNC Modification Proposal 0373
Chris Warner Network Code Manager
Presentation transcript:

Managing Exceeded Capacity

10 September The Issue of Exceeded Capacity DNO Connection Charging Methodologies: customers who increase Maximum Capacity pay connection charges for any works needed. Customers may also pay contribution for previous reinforcement Customers exceeding their Maximum Capacity –may avoid paying customer contributions and drive general network reinforcement expenditure –are a major problem (10% to 20% exceeding capacity) Existing charging and enforcement mechanisms provide minimal incentive for customers to manage their capacity within their contracted levels In DPCR5, Ofgem focussing on three themes: Environment, Customers and Networks To help attain these objectives, charging and commercial policies need to encourage efficient investment whilst delivering good customer service

10 September DNO Remedies for Breach Customers who exceed Max. Cap. in breach of connection agreement 12.3 The Customer not to exceed the Maximum Capacity; 12.4 Where Customer breaches Clause 12.3, it shall: upon written notice from the Company, reduce to within the Maximum Capacity; and where it wishes, propose a variation to the Maximum Capacity; or where it wishes submit a Modification Application Following a breach of Clause 12.3 the Company shall be entitled to charge the Customer (the Customer to pay on demand) such sum as the Company may require calculated in accordance with the Company’s charges. 5.6 The Company may without notice to the Customer, De-energise the Connection Point if: the Customer breaches Clauses 12.3, 5.7 If the Company De-energises the Connection Point as a result of breaches by the Customer, then the Customer shall pay on demand any costs incurred by the Company. Remedies are administratively burdensome. If no co-operation from Customer then only option is de-energisation If entry for de-energisation is refused, then enforcement through the County Court process as Electricity Code would not apply This remedy is ineffective: rarely if ever used by DNOs in practice

10 September Submitted CDCM Proposals CDCM submitted by the DNOs in compliance with SLC and has the same rate for Exceeded Capacity and for Maximum Capacity A proposal for a higher rate for Exceeded Capacity was withdrawn shortly before submission as Ofgem concern that it had not been fully justified Majority of DNOs agreed that this proposal should therefore not be included in the CDCM submission: All DNOs supported the CDCM In CDCM proposals, customers who exceed capacity will incur higher charges each month, but they may avoid connection charges Majority of DNOs (CE, CN, EDF-E, ENW) concerned that submitted CDCM provides insufficient incentives to customers to remain within Maximum Capacity and to promote efficient network investment

10 September Alternative Remedies (1) for Exceeded Capacity: 1. Charge for the Exceeded Capacity at a higher rate than the contracted Maximum Capacity Previously used by CN: proved effective in addressing issue Ofgem stopped CN using approach as were not satisfied that Exceeded Capacity charge was cost reflective Charge rate three times higher for Exceeded Capacity Following graph illustrates CN experience of the effectiveness, in terms of reducing excess over two years effect of reverting to the standard rate.

10 September CN Experience:

10 September Alternative Remedies (1) for Exceeded Capacity continued: 1. Charge for the Exceeded Capacity at a higher rate than the contracted Maximum Capacity Ofgem issues have been addressed 500MW model in CDCM produces annuitised costs of capacity at each voltage level Various proportions of these costs are included in the capacity charges. Costs are then DISCOUNTED to reflect contributions Exceeded Capacity charge is NOT DISCOUNTED as no contributions Proposed higher rate represents true cost of capacity: –not a penalty nor reflects future uncertain costs that may not materialise. –calculated the same as all other charges in the CDCM; and –is as cost reflective as all other charges in CDCM The expected IT billing costs of this proposal are unlikely to be any greater than for the current CDCM proposals

10 September Alternative Remedies (2) for Exceeded Capacity continued: 2. Levy connection charges through the supplier Where a breach occurs, connection charges payable but customer refuses to pay: levy the connection charge on the supplier Supplier then recovers costs from the customer Statutory rights on entry for de-energisation apply to non- payment of supplier charges: Remedy easier to enforce. Approach requires changes to DCUSA and NTC Approach may be disproportionate, especially for isolated incidences. Such one-off breaches can be ‘inadvertent’. Recurrence can be discouraged by a clear and appropriate cost message.

10 September Alternative Remedies (3) for Exceeded Capacity continued: 3. Pass-through of capacity breach investigation costs DNOs could levy costs in following up instances of Exceeded Capacity Costs would cover the transactional costs of actions such as –administrating capacities –contacting and visiting sites –processing stages towards de-energisation

10 September Conclusion: Current approach penalises customers who remain within Maximum Capacity or pay for increases The existing processes and remedies are ineffective Effective remedies are necessary to meet DPCR5 requirements Option 1) is another form of DSM, which Ofgem want DNOs to undertake Paying customers to constrain demand will be ineffective if others can drive reinforcement without bearing the cost CE, CN, EDF-E and ENW believe Option 1) is a proven cost reflective method of managing capacity and cost on the distribution network. If proposal not accepted, other approaches will have to be progressed through the various governance processes. The status quo and submitted CDCM approach do not work and changes are required.