Middle School Expansion August 11, 2003
Brick going up on north side next to classrooms.
Rain test on new roof. Roof at 60% completion.
Main east west corridor.
Typical entrance detail to classrooms.
Main north south corridor. Looking to the the south.
Main east west corridor looking toward the west.
Vestibule looking toward the southwest.
Profile of building from the southwest corner.
Brickwork at about 20%.
View from Amethyst.
The Project is going well. We will be ready for students to use the modular at the start of the school year.
The six-classroom addition is on budget and on schedule. It will be ready for occupation as scheduled in early Rick Denney, Facilities Director